Nfr Construction of the Indian Railways invites bids for a Power Generator DG Set up to 900 KVA. The scope covers Supply, Installation, Testing and Commissioning with a bid quantity option of ±25% and a minimum extension framework. The EMD is ₹56,640. This procurement requires OEM/Authorized Reseller involvement, and mandates a 3-year govt procurement track record. A functional service centre is required in the state of each consignee location or established within 30 days of award. Bidders must ensure GST compliance and OEM authorization, with the option clause guiding delivery timelines.
Technical Specifications & Requirements
- Scope of supply includes: Supply, Installation, Testing and Commissioning of the DG Set up to 900 KVA.
- Delivery/extension rules allow up to 25% quantity variation during contract and extension of delivery period with a minimum of 30 days.
- OEM involvement required for installation, testing and commissioning; OEM authorization or service provider authorization must be furnished.
- Service centre obligation: functional centre in each consignee state; if not present, must be established within 30 days of award.
- Experience requirement: bidder or OEM must have at least 3 years of supplying similar Govt/PSU projects; contracts to be submitted.
- GST advisory: bidder bears applicable GST; reimbursement as actuals or as per applicable rate.
- BOQ items: none listed; scope remains governed by overall terms and conditions.
- Delivery terms: commenced from the last date of original delivery order; option-driven extensions governed by the clause.
Terms, Conditions & Eligibility
- EMD: ₹56,640.
- Experience criteria: 3 years in manufacturing/supplying similar category products to Central/State Govt or PSU; primary product value basis for bunch bids.
- Manufacturer Authorization: OEM/Original Service Provider details required if bidding via distributor.
- Service Centre: mandatory in consignee state; if absent, establish within 30 days and provide proof for payment release.
- Scope & payment terms: supply, installation, testing and commissioning; payment terms not explicitly specified in the document.
- GST: bidder responsible for GST; reimbursement as per actuals or applicable rates, whichever is lower.
- Option clause: purchaser may increase/decrease quantity by up to 25%; delivery time recalculated as per formula with minimum 30 days.