Tender Overview
Organization: Mahanadi Coalfields Limited (Coal India Limited). Procurement: Proximity Warning Device compliant with DGMS Circular No. 06 of 2020, including supply, installation, testing and commissioning. EMD: ₹118,000. Delivery window: 120 days from the order date, with testing days confined to the first 60 days. OEM: BEML (as per ATC). ATC notes: option to adjust quantity up to ±25% of bid quantity during and after contract; successful bidders must adhere to extension rules and delivery recalculation. Scope: delivery to site, complete installation and acceptance testing with commissioning. The tender emphasizes adherence to acceptance criteria and rework/rectification within 30 days of notification for any non-conformity. Location details are not specified in the data. A unique differentiator is the DGMS standard alignment and OEM specification for proximity warning devices.
Technical Specifications & Requirements
- Product category: Proximity Warning Device (DGMS Tech Circular No. 06 of 2020) with compliance to the circular.
- OEM: BEML (as per ATC).
- Scope of supply: Supply, Installation, Testing and Commissioning (SITC).
- Delivery period: 120 days from order date; testing days: 2 days within first 60 days.
- Quality/defect policy: defective goods rejected at consignee end; replacement/rectification required within 30 days of notification; contractor bears all rectification costs.
- Documentation: Vendors must upload all requested certificates in line with Bid Document, ATC, and Corrigendum; includes compliance with GeM GTC and Purchase Manual 2020.
- Penalty/extension: Option to increase/decrease quantity by 25%; delivery time recalculated as (additional quantity/original quantity) × original delivery period, minimum 30 days.
- Testing: 2 testing days within 60-day window; rigorous acceptance criteria apply for SITC deliverables.
Terms, Conditions & Eligibility
- EMD: ₹118,000 as security deposit; payment andBG details per ATC.
- Delivery: 120 days from PO date; extended delivery rules apply under option clause.
- Warranty/Rectification: Rectification/replacement at supplier cost within 30 days of notification; no extra payment for rectification.
- OEM/ATC: OEM specified as BEML; comply with Buyer Uploaded ATC document for submission details.
- Documentation: Ensure submission of all certificates and documents sought; non-upload leads to rejection per ATC.
- Contract framework: Governed by GeM GTC, Buyer-Added ATC, and CIL Purchase Manual 2020 with amendments.
- Acceptance: Final inspection at consignee end determines conformity and potential rejection.