Tender Overview
The procurement is issued by the Armed Forces Tribunal under the Department of Defence for the Provn of Storage Rack in the Union Territory of Ladakh. Scope involves supply of storage racks; however, the exact quantity and estimated value are not disclosed. The tender features an option clause allowing a 50% quantity increase/decrease at contracted rates, with delivery timing tied to the original delivery order and extended periods. This defines a flexible, quantity-adjustable procurement to support field storage needs in high-altitude conditions. The unique location and military context warrant strict delivery and compliance discipline. Bidders must align with the option-based delivery framework and ensure readiness to scale with demand as per contract execution.
Technical Specifications & Requirements
- Product category: storage racks (provn) for Ladakh deployment
- No specific technical specs published; bidders should prepare for standard storage rack dimensions and load-bearing capacity suitable for military deployment
- The tender establishes an option clause: up to 50% quantity variation during and after contract; time extension calculation: (additional quantity ÷ original quantity) × original delivery period, minimum 30 days; if original period < 30 days, new period equals original period
- Focus on timely delivery, robust construction for harsh terrain, and adherence to contractual delivery timelines; no BOQ items are listed
- Because no concrete standards are specified, bidders should highlight their capability to meet generic storage rack requirements with quality assurance
Terms & Eligibility
- The tender includes an option clause enabling a 50% quantity variation at contracted rates
- Delivery period adjustments begin from the last date of the original delivery order; extended periods follow the same rule
- The formula ensures a minimum extension of 30 days for additional delivery time
- The terms require bidders to comply with the option clause and deliver as per contract adjustments; no other explicit EMD or eligibility criteria are disclosed in the available data
- Submission must align with general defence procurement norms and prepare for potential scale-up in Ladakh deployment