• Supply and installation of 315 mm diameter HDPE pipelines for village tank filling.
• Survey and marking of pipeline routes in Survey Nos. 787, 788, 761 (Vadasan) and Survey No. 412 (Sayajinagar).
• Excavation and trenching as per technical specifications.
• Laying of HDPE pipes ensuring proper alignment and slope.
• Connection to existing sluice valves at Ch. 12100 Mt.
• Testing and commissioning of pipeline for leak-proof operation.
• Restoration of affected areas post-installation.
• Compliance with technical specifications outlined in tender documents.
| Technical Parameters |
Specifications |
| Pipe Diameter |
315 mm |
| Material |
HDPE |
| Length of pipeline |
Approx. 12,100 meters |
| Connection points |
Existing sluice valves |
| Project Duration |
9 months |
- Preparation of site and survey.
- Procurement of materials.
- Laying of pipelines.
- Connection and testing.
- Final inspection and handover.