Tender Overview
Uttar Pradesh Power Corporation Limited (UPPCL) invites bids for the repair, maintenance and installation-related services of substation equipment, specifically the repairing and overhauling of 33 KV isolators (B.S.I. & L.S.I.) at CB No. 03, Mandishyam Nagar, installed at 220 KV S/S Sikandrabad, and complete overhauling of the 36 kV VCB mechanism at the same bay. The estimated total value is ₹19,942.00 (including GST), based on a single job order with labor and testing tasks to be performed by the contractor. Scope includes dismantling damaged jaws/blades, fitting fresh jaws, alignment adjustments, drive mechanism inspection, cleaning porcelain and vacuum components, and verification of tripping/closing operations up to 70% DC voltage. Administrative approval is requested to procure via GEM within division powers. Location: Bulandshahr, Uttar Pradesh. Unique aspect: limited tender for specified maintenance work, with a quantity of 1 job and GST 18% applied.
Technical Specifications & Requirements
- Work scope: Repairing and overhauling of 33 KV isolators B.S.I. & L.S.I. for CB-03, Mandishyam Nagar, at 220 KV S/S Sikandrabad; complete overhaul of 36 KV VCB mechanism for the same bay.
- Key activities: dismantle damaged jaws/blades, replace with department-supplied parts if needed, realign mechanism, adjust coupling rod, set drive insulator/torque components, oiling/greasing, and ensure proper tripping/closing operations.
- Testing/verification: check DC voltage trip at 70%, verify megger values for breaker poles; confirm thorough cleaning of drive insulators and vacuum interrupters.
- Delivery/ownership: contractor provides all labour and testing tools (T&P) at their cost; material/components as required per scope; GST at 18%; total project value after GST ₹19,942.00.
- Standards/Compliance: no explicit standards listed; work performed under administrative approval for internal divisional procurement; deliverables are targeted to ensure safe, reliable operation of 33 KV and associated switchgear.
Terms, Conditions & Eligibility
- EMD: not specified in the provided terms; bidders should prepare standard bid security if applicable per division policy.
- Delivery timeline: scope mentions month of October 2005 in the administrative note, but current tender does not specify a new delivery deadline; bidders should seek clarification for a definitive timeline.
- Payment terms: not detailed in the terms; candidates should confirm payment schedule with the executive engineer prior to submission.
- GST compliance: 18% GST applied to total project value; invoice should reflect GST and base price separately.
- Documentation: ensure submission of OEM/authorizations and experience documents as per divisional procurement norms; include technical bid and compliance certificates.
- Penalty/loi: no explicit liquidated damages listed; bidders should verify any contingencies during contracting.
- ATC/ATC-like clauses: Administrative approval process indicates single, limited tender; ensure adherence to supply chain and local procurement rules.