Tender Overview
Organization: Indian Army (Department Of Military Affairs) in BHIWANI, HARYANA. Procures an integrated IT hardware bundle including ALL In One PC, Desktop PC with Accessories, UPS, Printer, and NAS 4 TB. Estimated value: โน300,000. No start/end dates provided; BOQ lists 5 items but individual quantities are not specified. Unique requirement: quantity may swing by up to 25% during contract placement and currency, with adjusted delivery timelines. This tender targets government IT provisioning and bulk supply capability across army facilities.
Technical Specifications & Requirements
- Scope covers IT hardware bundles: ALL In One PC, Desktop PC + peripherals, UPS power backup, Printer, and NAS 4 TB storage.
- BOQ items show 5 lines but no itemized specifications or quantities; bidders must prepare for flexible quantities within the 25% option clause.
- Delivery period is tied to the last date of the original delivery order; any extension follows the option clause with formula: (Increased quantity รท Original quantity) ร Original delivery period, minimum 30 days.
- No explicit technical standards or certifications listed; bidders should assume standard government IT compliance and ensure hardware compatibility with common Army IT environments.
- Estimated value implies modular pricing for combined bundle; suppliers should present itemized pricing to reflect the 5-item scope.
Terms, Conditions & Eligibility
- Option Clause allows +/- up to 25% quantity variation at contract award and during the currency at contracted rates.
- Delivery timeline is governed by the last date of the original delivery order; minimum extension time is 30 days if original period is shorter.
- EMD details are not specified; bidders should confirm payment security requirements and bid security norms with the purchasing authority.
- The tender requires compliance with miscellaneous Buyer Added Terms and Conditions; bidders must be prepared to accommodate quantity fluctuations and extended delivery as per clause.
- No start date, end date, or exact delivery locations beyond the stated city/state are provided; bidders should verify site access and installation requirements with Indian Army procurement officials.