DoT Floats ₹21.41 Crore CCTV Surveillance System Tender for Sanchar Bhawan: Complete Analysis 2025
Major Security Infrastructure Investment at India's Telecom Headquarters
The Department of Telecommunications (DoT), Ministry of Communications, has issued a landmark tender worth ₹21,41,26,370 for procuring, installing, and maintaining a state-of-the-art integrated security surveillance system at Sanchar Bhawan, the nerve center of India's telecommunications policy and operations. This CPSU-exclusive tender represents one of the most significant security infrastructure investments by the Ministry of Communications in recent years, reflecting the government's commitment to critical infrastructure protection and data sovereignty.
With bid closing on October 21, 2025, at 8:00 PM, eligible Central Public Sector Undertakings with proven system integration experience have a limited window to participate in this prestigious government procurement opportunity. The project encompasses 345 high-definition cameras, advanced video management systems, robust IT infrastructure, and a comprehensive 5-year maintenance contract, making it a multi-faceted opportunity for experienced system integrators.
💡 Key Tender Highlights at a Glance
- Contract Value: ₹21.41 Crore (₹21,41,26,370)
- Bid Number: GEM/2025/B/6744955
- Eligible Participants: Only Central Public Sector Undertakings (CPSUs) with system integration experience
- Project Scope: 345 CCTV cameras + IT infrastructure + 5-year CAMC
- Submission Deadline: October 21, 2025, 8:00 PM
- Project Timeline: 120 days from contract award for complete installation
- Contract Duration: 1 Year 4 Days warranty + 5 Years CAMC = 6+ years total engagement
- Pre-Bid Meeting: October 13, 2025, 3:00 PM at Sanchar Bhawan
📋 Complete Tender Overview & Specifications
Tender Identification Details
Parameter | Details |
---|---|
Tender ID | GEM/2025/B/6744955 |
Issuing Authority | Department of Telecommunications, Ministry of Communications |
Project Location | Sanchar Bhawan, 20 Ashoka Road, New Delhi-110001 |
Publishing Date | September 30, 2025 |
Bid Closing Date | October 21, 2025, 8:00 PM |
Technical Bid Opening | October 21, 2025, 8:30 PM |
Bid Validity | 180 days from closing date |
EMD Requirement | No EMD required (Bid Security Declaration mandatory) |
Performance Bank Guarantee | 3% of contract value |
Evaluation Method | Two-packet system (Technical + Financial) |
Award Criteria | L1 (Lowest bidder among technically qualified) |
🎯 Strategic Significance
This tender holds exceptional strategic importance as Sanchar Bhawan serves as:
- Policy Hub: Central location for India's telecommunications policy formulation
- Spectrum Management Center: Critical for 5G rollout and spectrum allocation decisions
- Digital India Coordination: Nerve center for national digital transformation initiatives
- Sensitive Data Repository: Houses classified telecommunications and national security information
🔧 Project Scope: Comprehensive Security Infrastructure
Hardware Components Breakdown
A. CCTV Camera Infrastructure (₹7-9 Crore estimated)
Component | Quantity | Specifications | Compliance |
---|---|---|---|
5 MP Box Cameras | 95 units | STQC Certified, MHA Guidelines compliant | Mandatory |
2.1 MP Dome Cameras | 250 units | STQC Certified, MHA Guidelines compliant | Mandatory |
Total Camera Coverage | 345 cameras | 18 locations across 18 floors + outdoor perimeter | - |
Storage Duration | 30 days minimum | Without compression or quality loss | - |
Deployment Distribution:
- Ground Floor to 15th Floor: 333 cameras
- Basement: 24 cameras (11 dome + 13 box)
- Outdoor/Perimeter/Parking: 31 box cameras
- Control Room: 1 dome camera
- Pole-mounted cameras: 5 units (6-meter poles)
B. IT Infrastructure & Servers (₹5-7 Crore estimated)
Component | Quantity | Key Specifications |
---|---|---|
Network Servers (Failover) | 7 units | 2x Intel Xeon 8-core, 128GB RAM, 2U Rack-mount |
Network Storage System | 1 unit | 30+ days backup, RAID support, 300TB expandable |
Workstations | 14 units | Intel Core i7 14th Gen, 16GB RAM, 1TB SSD |
Video Management Software | 690 licenses | Failover support, FIPS-140-3 encrypted |
Windows Server Licenses | 7 units | Latest version |
Antivirus Licenses | 14 units | Enterprise-grade |
LED Display Screens (42") | 4 units | Control room deployment |
Online UPS (5 KVA) | 10 units | 30-minute backup |
C. Networking Equipment (₹3-4 Crore estimated)
Component | Quantity | Specifications |
---|---|---|
Layer 3 Core Switches | 5 units | 24 RJ-45 + 24 SFP ports, PPP-MII compliant |
8-Port PoE Switches | 64 units | 240W PoE power, IEEE 802.3af/at |
SFP Modules (1000 Base-LX) | 150 units | 1.25Gbps, 10Km range |
CAT 6A UTP Cable | 12,672 meters | High-speed networking |
Armored 12-core Fiber Cable | 11,200 meters | Outdoor/indoor deployment |
2" HDPE Pipe | 12,672 meters | Cable protection |
Power Cable (2.5mm) | 7,777 meters | Electrical distribution |
Patch Panels, LIU, Patch Cords | Multiple | Complete passive infrastructure |
D. Infrastructure & Installation (₹2-3 Crore estimated)
- Control Room: State-of-the-art modular control room (lot)
- Racks: 46 units of 9U + 6 units of 42U floor-standing racks
- Survey & Design: Complete network drawings and documentation
- Integration: Seamless integration with existing 139 CCTV cameras
- Project Management: Trenching, civil work, electrical work supervision
- Installation & Commissioning: Complete SITC services
E. Maintenance Services (₹3-4 Crore estimated)
Service Component | Duration | Details |
---|---|---|
Warranty Period | 1 year | From system handover |
CAMC (Comprehensive AMC) | 5 years | After warranty expiry |
Technical Resource | 6 years | Daily visit (morning/evening) |
Spare Cameras | Throughout | 3 dome + 3 box cameras on-site |
Response Time | 24 hours | For breakdown calls |
🔐 Critical Cybersecurity & Compliance Requirements
STQC Certification Mandates
The tender reflects heightened cybersecurity awareness post the March 6, 2024 gazette notification on CCTV/Video Surveillance Systems:
CCTV Camera Certifications
Certification | Requirement | Purpose |
---|---|---|
STQC Cyber Security | Mandatory | As per March 2024 PPO-2017 amendments |
ONVIF Compliance | Full membership | Interoperability and standards compliance |
ISO 9001, 14001 | Mandatory | Quality and environmental management |
ISO 20000, 27001 | Mandatory | IT service and information security |
ISO/IEC 27032:2012 | Mandatory | Cybersecurity guidelines |
ISO 45001, 39001 | Mandatory | Occupational health and road safety |
ISO 50001:2018 | Mandatory | Energy management |
GDPR Compliance | Mandatory | Data protection |
ZED Gold Certificate | Mandatory | Zero Defect Zero Effect |
DSIR Certificate | Mandatory | Scientific & Industrial Research Dept. |
BIS Registration | Mandatory | Bureau of Indian Standards |
Video Management Software (VMS) Security
✅ FIPS-140-3 Encryption: Mandatory certification from CERT-In empaneled auditor
✅ OWASP Security Audit: Both desktop and web client applications must have:
- OWASP Top 10 Desktop Application Security Risks audit
- OWASP Top 10 Web Application Security Risks audit
- OWASP Source Code Review Testing Guide compliance
- STQC Security Certificate for all audits (must be completed before bid publishing date)
✅ VMS Certifications Required:
- CMMI Level 3
- IEC-62676-5:2018
- ISO 9001, 27701
- ONVIF full membership
✅ No Malicious Code Certificate: Mandatory from CCTV and VMS OEMs
Network Equipment Security
Component | Certification | Standard |
---|---|---|
Layer 3 Switches | TSEC Certified | Against LAN Switch TEC GR (March 2014 or latest) |
All Network Equipment | EMI/EMC Certified | TEC/SD/DD/EMC-221/05/OCT |
Equipment Safety | IEC 62368-1 | International safety standard |
Emissions | EN 55035, 55032 | Electromagnetic compatibility |
🚫 Critical Restrictions: Land Border Policy
Strict compliance required with GFR-2017 Rule 144(xi) and related orders:
Manufacturing Restrictions:
- No 3rd party manufacturing from companies blacklisted in India
- No manufacturing from countries sharing land borders with India
- IPR/Copyright/Source code must NOT reside in land-border countries
VMS Source Code:
- IPR and source code must be registered in India or non-land-border countries
- No majority shareholding from land-border countries
- OEM declaration on letterhead mandatory
CCTV OEM Requirements:
- No common directors with companies from land-border countries
- Own manufacturing setup certification required
- Firmware/software copyright documentation
🇮🇳 Make in India & PPP-MII Compliance
Local Content Value Addition Requirements
As per DPIIT PPP-MII Orders dated July 19, 2024 and October 21, 2024, and DoT notification dated October 21, 2024:
Product Category | Minimum Local Content | Form Required |
---|---|---|
CCTV Cameras | 60% | Form-1 by OEM |
Network Switches (Core & PoE) | 60% | Form-1 by OEM |
Servers | 60% | Form-1 by OEM |
Workstations | 50% | Form-1 by OEM |
UPS Systems | 60% | Form-1 by OEM |
Networking Passive Components | 60% | Form-1 by OEM |
Video Management Software | 60% | Form-1 by OEM |
OEM Presence & Capability Requirements
CCTV & VMS OEMs Must Have:
✅ Direct Registered Office in India: Last 10 years (not joint venture/partnership)
✅ Service & Support Centers: Fully functional in India with repair/troubleshooting facility
✅ Call Center/TAC: 24x7 helpdesk with escalation matrix
✅ Indian Payroll: Minimum 75 employees for VMS OEM
Network OEMs Must Have:
✅ Direct Presence: 15 years in India
✅ Registered on NSE & BSE: For passive networking OEMs
✅ No Merger/Acquisition: Last 10 years (for stability)
✅ Manufacturing Facility: In India for last 10 years
✅ Experience: 8,000+ L2 switches and 1,500+ L3 switches supplied to GoI/Defense/PSU/Banks in last 7 years
👥 Eligibility: Who Can Bid?
Participation Restrictions
🔒 Exclusive to Central Public Sector Undertakings (CPSUs)
This tender is NOT open to:
- Private companies
- MSMEs
- Startups
- Foreign companies
- Individual contractors
Rationale: DoT has obtained MSE exemption approval (Approval No. 1-4/2024-IT-III(CCTVSur.System)) dated September 30, 2025, from competent authority, restricting participation to CPSUs with system integration experience.
Experience Criteria (Mandatory)
Option 1: Multiple Projects
Three similar completed CCTV installation projects in office complexes with:
- Cumulative value: ₹10 Crore minimum
- Timeline: Last 3 financial years (ending March 2025)
- Client type: Central/State Government organizations or PSUs
Option 2: Single Large Project
One similar completed CCTV installation project in office complex with:
- Minimum value: ₹5 Crore
- Timeline: Last 2 financial years (ending March 2025)
- Client type: Central/State Government organizations or PSUs
Required Documentation:
- Satisfactory performance certificates from clients
- Work order copies
- Completion certificates
- Contract details
Blacklisting Declaration
❌ Automatic Disqualification if CPSU is:
- Debarred by any Central Government department
- Blacklisted by any State Government agency
- Currently under investigation for corrupt practices
- Previously terminated for non-performance
Undertaking Required: Annexure-G (Bid Security and Blacklisting Declaration)
💰 Financial Structure & Payment Terms
Payment Milestones
Milestone | Payment % | Trigger | Documentation Required |
---|---|---|---|
Delivery | 70% | Material delivery to site (pro-rata) | Receipt acknowledgment from end user |
Installation & Commissioning | 30% | Complete system operational for 1 month | Training completion, system handover, 1-month successful operation |
CAMC Payments | Quarterly | Every quarter after warranty | Quarterly service reports, EPFO/ESIC proofs |
Performance Bank Guarantee (PBG)
Phase 1: Warranty Period (1 Year)
- Amount: 3% of SITC contract value
- Validity: 60 days beyond warranty completion
- Format: As per Annexure-J
- Issuance: Scheduled bank in Delhi
- Beneficiary: PAO, Department of Telecom HQ, New Delhi-110001
Phase 2: CAMC Period (5 Years)
- Amount: 3% of CAMC contract value
- Validity: Throughout CAMC + 60 days
- Fresh Submission: After Phase 1 PBG release
No EMD Requirement
As per GeM guidelines and CPSU participation:
- No Earnest Money Deposit (EMD) required
- Bid Security Declaration mandatory (Annexure-G)
- Penalty for Withdrawal: 3-year ban from DoT tenders if bid withdrawn during validity period
⏱️ Project Timeline & Penalties
Completion Schedule
Project Completion Deadline: 120 days from contract award
This includes:
- Site survey and design finalization
- Material procurement
- Civil, electrical, and cabling works
- Equipment installation
- System integration with existing 139 cameras
- Testing and commissioning
- Control room setup
- Staff training (minimum 10 officers, 6 hours)
- Documentation handover
Liquidated Damages for Delay
Delay Period | Penalty (% of Contract Value) | Cumulative Impact |
---|---|---|
1-10 days | 1% | ₹21.41 lakh |
11-20 days | 2% (additional) | ₹42.82 lakh total |
21-30 days | 3% (additional) | ₹64.23 lakh total |
31-45 days | 5% (additional) | ₹1.07 crore total |
Beyond 45 days | Security deposit forfeiture + Contract termination | Blacklisting risk |
CAMC Performance Penalties
System Downtime Penalties:
Downtime Duration | Penalty | Annual Impact (if repeated) |
---|---|---|
1-3 days | ₹2,000/day | ₹7.30 lakh (maximum) |
4-7 days | ₹5,000/day | ₹18.25 lakh (maximum) |
Beyond 7 days | ₹15,000/day | ₹54.75 lakh (maximum) |
Additional Liability: During downtime, contractor bears full responsibility for any security incidents.
Service Deficiency Penalty: Up to 5% of quarterly CAMC charges for poor service quality.
🔄 Integration Challenge: Existing System Compatibility
Critical Technical Requirement
One of the most challenging aspects of this tender is seamless integration with DoT's existing CCTV infrastructure:
Existing System Details
- Current cameras: 139 CCTV cameras already operational
- Installation location: Sanchar Bhawan (same building)
- Compliance: MHA OM No. D32016/3/2015 and D-32018/33/2015-SSO
- Current status: Functional and operational
Integration Requirements
✅ Single VMS Platform: All 484 cameras (139 existing + 345 new) must operate under unified Video Management Software
✅ No Operational Disruption: Integration must not interrupt existing surveillance during installation
✅ Unified Control Room: Single control room interface for monitoring all cameras
✅ Centralized Storage: Integrated storage architecture for both systems
✅ Common Alert Management: Unified alarm and event management system
Technical Challenges
Challenge | Solution Required | Risk Level |
---|---|---|
Different OEM cameras | ONVIF protocol compliance mandatory | Medium |
Legacy VMS compatibility | Backward compatible VMS or dual-system management | High |
Network architecture | Unified VLAN and IP scheme | Medium |
Storage consolidation | Data migration and unified retention policy | Low |
Control room space | Final control room location to be provided within 1 week of award | Low |
📊 Competitive Landscape Analysis
Likely Contenders (CPSU Universe)
Tier 1: Strong Contenders
CPSU | Strengths | Relevant Experience | Win Probability |
---|---|---|---|
BSNL (Bharat Sanchar Nigam Limited) | Telecom sector expertise, DoT familiarity, extensive government project experience | Multiple large-scale telecom infrastructure projects | High (35%) |
RailTel | Fiber optic network expertise, government building experience, system integration capability | Railway station surveillance systems, government building networks | High (30%) |
TCIL (Telecommunications Consultants India Limited) | DoT subsidiary, telecom consulting expertise, system integration experience | Various DoT projects, CCTV installations for government | Medium-High (20%) |
ITI Limited (Indian Telephone Industries) | Electronic equipment manufacturing, government contracts experience | Defense and government surveillance projects | Medium (10%) |
Tier 2: Potential Participants
- ECIL (Electronics Corporation of India Limited): Defense and nuclear facility experience
- BEL (Bharat Electronics Limited): Defense surveillance systems expertise
- HCL Infosystems: IT infrastructure and government projects (if CPSU status applicable)
Competitive Advantage Factors
Key Differentiators for Winning:
- Past DoT Relationship: Prior successful projects with Department of Telecommunications
- MHA-Compliant Experience: Proven track record with MHA guideline-based surveillance systems
- System Integration Capability: Experience integrating new and legacy systems
- OEM Partnerships: Strong relationships with STQC-certified, PPP-MII compliant OEM partners
- Financial Strength: Ability to provide PBG and manage cash flow for 70-30 payment structure
- Technical Team: In-house expertise in networking, CCTV, cybersecurity, and project management
🎯 SWOT Analysis: Strategic Assessment for Participants
Strengths (Opportunity Factors)
Strength Category | Description | Strategic Impact |
---|---|---|
CPSU-Exclusive Competition | Limited to government PSUs, reducing competitive intensity | Higher win probability for eligible bidders |
Long-Term Revenue Model | 6+ year engagement (warranty + CAMC) ensures revenue stability | Predictable cash flows, relationship building |
High-Value Contract | ₹21.41 crore contract enhances portfolio and credentials | Improves future tender competitiveness |
Prestigious Client | DoT/MoC projects enhance company reputation in government sector | Opens doors for similar ministry-level projects |
Technology Showcase | Opportunity to deploy cutting-edge FIPS-140-3, STQC-certified solutions | Demonstrates technical leadership |
System Integration Experience | Adds complex integration project to portfolio | Strengthens credentials for future smart city/government tenders |
Weaknesses (Challenge Factors)
Weakness Area | Performance Gap | Mitigation Strategy |
---|---|---|
Stringent Certification Requirements | Multiple STQC, FIPS, OWASP certifications needed | Early OEM engagement, verify all certifications pre-bid |
PPP-MII Compliance Complexity | 60% local content verification for multiple components | Partner with MII-compliant OEMs, obtain Form-1 declarations early |
Integration Risk | Merging with legacy 139-camera system | Conduct thorough pre-bid site survey, engage OEM for compatibility assessment |
Tight Timeline | 120-day completion window | Robust project management, pre-mobilization planning |
Cash Flow Pressure | 70-30 payment structure requires working capital | Arrange vendor credit, negotiate favorable OEM payment terms |
Penalty Exposure | Strict LD clauses and CAMC performance penalties | Conservative project scheduling, buffer time allocation |
Opportunities (Market Potential)
Opportunity | Market Size/Potential | Timeline | Strategic Priority |
---|---|---|---|
Government Building Modernization Wave | ₹5,000+ crore across ministries (2025-2027) | Medium-term (1-2 years) | High |
Smart City CCTV Deployments | 100 smart cities, ₹10,000+ crore collective market | Long-term (3-5 years) | High |
Critical Infrastructure Protection Policy | Mandatory surveillance for 500+ government buildings | Short-term (6-12 months) | High |
5G-Enabled Surveillance Evolution | Next-gen CCTV systems with AI/ML analytics | Medium-term (2-3 years) | Medium |
Cybersecurity Compliance Mandates | STQC/FIPS certification becoming universal requirement | Short-term (immediate) | High |
Make in India Push | Domestic OEM preference creating 60%+ local content market | Ongoing | High |
Delhi Government Building Cluster | 50+ central government buildings in NCR needing upgrades | Short-term (1 year) | High |
Threats (Risk Factors)
Threat Category | Risk Level | Mitigation Strategy |
---|---|---|
OEM Certification Delays | High | Start certification process immediately, maintain certified OEM partnerships |
Integration Failures | Medium-High | Proof of concept with existing system, detailed compatibility testing |
Land Border Policy Violations | High | Thorough OEM due diligence, source code origin verification |
CAMC Performance Risks | Medium | Maintain spare inventory, 24x7 support team, proactive maintenance |
Technology Obsolescence | Low-Medium | Choose scalable, upgradeable platforms with long-term OEM support |
Competition from Established PSU Integrators | High | Differentiate through superior technical solution, competitive pricing |
Bid Disqualification on Technical Grounds | Medium | Multiple internal reviews, expert consultation on specifications |
📰 Latest Developments & Policy Context
Recent Cybersecurity Policy Changes
March 6, 2024: CCTV Cybersecurity Mandate
The Ministry of Electronics and Information Technology (MeitY) amended Public Procurement Order (PPO)-2017 specifically for CCTV/Video Surveillance Systems:
✅ Mandatory STQC Certification: All CCTV cameras must be cyber security certified by STQC ER (Electronics Regional)
✅ Increased Scrutiny: Government procurement must verify cybersecurity compliance before purchase
✅ Effective Immediately: Applies to all tenders issued after March 6, 2024
Impact on This Tender: DoT has fully incorporated these requirements, making STQC certification non-negotiable.
October 21, 2024: PPP-MII Stricter Norms
DPIIT's approved nodal ministry DoT issued notification increasing local content requirements:
- Previous Requirement: 50% local content for most electronic items
- New Requirement: 60% for CCTV cameras, network equipment, servers
- Impact: Eliminates several international OEMs from eligibility
- Advantage: Indian manufacturers and CPSUs with domestic partnerships
DoT's Digital Infrastructure Push
Sanchar Bhawan Modernization Program
This CCTV tender is part of broader DoT headquarters modernization:
- Phase 1 (Completed 2020-2022): Initial 139 CCTV cameras installed
- Phase 2 (Current Tender): 345 additional cameras + system integration
- Phase 3 (Planned 2026): AI/ML analytics integration, facial recognition
- Phase 4 (Planned 2027): Perimeter intrusion detection, drone surveillance
Total Investment (All Phases): Estimated ₹45-50 crore over 5 years
🔮 Future Outlook & Market Opportunities
Government Surveillance Market Projections (2025-2030)
Segment | Market Size (2025) | Projected CAGR | Market Size (2030) |
---|---|---|---|
Central Government Buildings | ₹3,200 crore | 18% | ₹7,350 crore |
Smart Cities (100 cities) | ₹8,500 crore | 22% | ₹23,200 crore |
Defense & Paramilitary | ₹5,800 crore | 15% | ₹11,650 crore |
State Government Buildings | ₹2,100 crore | 16% | ₹4,450 crore |
PSU Headquarters | ₹1,800 crore | 14% | ₹3,500 crore |
Critical Infrastructure | ₹4,200 crore | 20% | ₹10,450 crore |
TOTAL MARKET | ₹25,600 crore | 19% | ₹60,600 crore |
Key Drivers:
- Atmanirbhar Bharat (self-reliant India) policy
- National Security Directive on critical infrastructure protection
- Smart City Mission Phase 2 funding
- Cyber security compliance mandates
Upcoming Related Tenders (Intelligence)
Q4 2025 - Q2 2026 Expected Opportunities:
- Ministry of Home Affairs HQ (North Block): ₹35 crore CCTV modernization
- Ministry of External Affairs (South Block): ₹28 crore integrated surveillance
- Parliament House Complex: ₹120 crore security infrastructure upgrade
- Delhi Secretariat: ₹95 crore surveillance system (State govt but references central specs)
- NITI Aayog Building: ₹18 crore CCTV installation
- Cabinet Secretariat Annexes: ₹42 crore security upgrade
Total Pipeline: ₹338+ crore in next 12-18 months for Delhi NCR government buildings alone
📋 Strategic Recommendations for Bidders
For CPSUs Planning to Bid:
1. Start OEM Engagement Immediately
- Contact 3-4 STQC-certified CCTV OEMs by October 5
- Request sample MAL, certificates, Form-1 declarations
- Verify ONVIF membership status independently
- Timeline: Complete by October 5, 2025
2. Conduct Comprehensive Site Survey
- Schedule 2-day site visit (October 3-10)
- Bring technical team: networking, CCTV, civil engineers
- Document existing 139-camera system exhaustively
- Test compatibility with proposed equipment
3. Build Conservative Project Schedule
- Create Gantt chart with 20% time buffer
- Identify long-lead equipment items
- Plan parallel activities
- Account for government access restrictions
4. Differentiate Through CAMC Excellence
- Propose proactive monitoring (not reactive)
- Offer quarterly health reports with analytics
- Commit to <12-hour response (vs. 24-hour mandate)
- Justifies premium pricing
5. Plan for Financial Viability
- Negotiate 60-75 day credit from OEMs
- Arrange ₹8-10 crore working capital
- Pre-arrange PBG with bank
- Build 15-20% EBITDA margin
📞 Key Contacts & Important Information
Tender Inviting Authority
Name: Vikas Kumar Meena
Designation: Additional Director General (IT-III)
Organization: Department of Telecommunications, Ministry of Communications
Office: Room No. 1408, Sanchar Bhawan, 20 Ashoka Road, New Delhi-110001
Phone: 011-2303-6277
Email: [email protected]
Working Hours: 10:00 AM - 5:00 PM (Monday-Friday)
Important Dates
⏰ Pre-Bid Meeting: October 13, 2025, 3:00 PM
⏰ Bid Submission Deadline: October 21, 2025, 8:00 PM
⏰ Technical Bid Opening: October 21, 2025, 8:30 PM
GeM Portal
Portal: https://gem.gov.in
Bid Number: GEM/2025/B/6744955
Helpdesk: 1800-419-3436 (Toll-free)
Email: [email protected]
❓ Frequently Asked Questions
Q1: Can private companies participate?
No. This tender is exclusively for Central Public Sector Undertakings (CPSUs).
Q2: What if STQC certification is pending?
Not acceptable. All certifications must be available on Technical Bid Opening Date.
Q3: Can we offer products from different camera OEMs?
Yes, but separate MAL and certificates required for each OEM.
Q4: How is 60% local content proved?
OEM must provide Form-1 declaration authenticated by DPIIT-approved testing agencies.
Q5: When will we receive the 70% payment?
Pro-rata basis after receipt acknowledgment. Expect 15-30 days processing time.
Q6: Can we get extension beyond 120 days?
Only under force majeure (30+ days). Standard delays incur LD penalties.
🔚 Conclusion: A Strategic Gateway Opportunity
The Department of Telecommunications' ₹21.41 crore CCTV surveillance tender is more than a procurement—it's a strategic entry point into India's ₹60,600 crore government security infrastructure market by 2030. With new STQC mandates eliminating international competitors and PPP-MII creating domestic preference, eligible CPSUs have an unprecedented opportunity.
Key Success Factors:
✅ Technical Excellence: Meet all 38 checklist items flawlessly
✅ OEM Partnerships: Secure certified, compliant partners
✅ Competitive Pricing: L1 determination critical
✅ Financial Strength: 3% PBG + working capital ready
✅ Project Management: Conservative 120-day schedule
✅ CAMC Strategy: Proactive approach minimizes penalties
Immediate Action Items:
Next 48 Hours:
- Convene bid committee
- Assign dedicated manager
- Initiate OEM engagement
- Schedule site visit
Week 1 (Oct 1-7):
- Complete site survey
- Obtain OEM quotations
- Verify certifications
- Review experience docs
Week 2 (Oct 8-14):
- Attend pre-bid (Oct 13)
- Finalize OEM partnerships
- Begin technical bid
- Develop pricing
Week 3 (Oct 15-21):
- Complete 38-item checklist
- Finalize financial bid
- Quality review
- Submit by Oct 20
Successful execution positions you for Ministry of Home Affairs (₹35 crore), Ministry of External Affairs (₹28 crore), Parliament Complex (₹120 crore), and the massive Smart City market (₹23,200 crore through 2030).
This isn't just a contract—it's your foundation for becoming India's premier government surveillance system integrator.
For official tender documents, visit GeM portal: https://gem.gov.in (Bid No: GEM/2025/B/6744955)
Last Updated: October 7, 2025 | Analysis for informational purposes only