Organization: NLC Tamil Nadu Power Limited. The procurement scope covers the supply of radial pads for the thrust bearing of Pump Model 700VM to NTPL stores in Tuticorin, Tamil Nadu 627713. The contract is for the Only supply of Goods, with inspection at the consignee site (NTPL stores, Tuticorin) and material test certificate verification by the buyer’s lab. OEM-only eligibility is indicated, with post-award payment via online RTGS and submission of an EFT mandate. The bid allows quantity adjustments up to 25% during or after contract, and delivery timelines are linked to the original delivery period plus any extendable time. Unique conditions include mandatory uploading of all certificates and documents, and a bank-backed performance security submission.
Technical Specifications & Requirements
- Scope of supply: Only supply of radial pads for thrust bearing of Pump Model 700VM.
- Inspection: Post-receipt inspection at NTPL stores, Tuticorin; pre-dispatch inspection not applicable unless ATC specifies.
- Documentation: Material Test Certificate to be sent with supply; buyer’s lab results determine acceptance.
- Certifications/Documentation: PAN, GSTIN, cancelled cheque, EFT mandate (bank-certified); OEM authorization required; all certificates uploaded with bid.
- Payment & Security: Online RTGS payment by the buyer; performance security through PBG or online payment; complete contract number and seller name in transfer details.
Terms, Conditions & Eligibility
- Option Clause: Purchaser may increase/decrease quantity up to 25% during contract; extended delivery time computed as (increased quantity/original quantity) × original delivery period, with a minimum of 30 days.
- Bidders’ eligibility: OEM requirement specifies involvement of Rotycan Turbotech Pvt Ltd, Vadodara; only OEMs may bid.
- Delivery & acceptance: Delivery period linked to original delivery date; acceptance based on Material Test Certificate results from the Buyer’s lab.
- Submission requirements: PAN, GSTIN, cancelled cheque, EFT mandate; upload all relevant certificates and documents; online payment transfer proof to be uploaded within 15 days of award.
- Inspection: Post-receipt inspection at NTPL stores; pre-dispatch inspection not standard unless ATC applies.