Tender Overview
Organization: Advanced Weapons And Equipment India Limited, under the Department Of Defence Production. Procurement: Plug Bore No-Go Gauge for Barrel 9X19mm Machine Pistol (DRG. No. 2101 05 02 00 00 000 00GA). EMD: ₹34,383. Location details incomplete; tender includes an option clause allowing quantity variation up to ±50%, with calculated extension rules. Vendors must sign a Non-Disclosure Agreement (NDA) to access drawings, and drawings may be updated as minor or major changes at supply order time. Pre-qualification requires SAF registration and VRRF capacity assessment. This TE invites registered vendors to participate after NDA clearance and drawing access. The tender is published with risk disclosures and standard confidentiality terms to safeguard drawings.
Technical Specifications & Requirements
- No explicit technical specifications provided in the public data.
- Notable terms: LD at 0.5% per week (or part thereof) to a maximum of 10% of delayed supply value.
- Drawings access contingent on NDA; drawings may be revised (minor vs major) and updated at supply order.
- NDA is mandatory before TOD; SAF vendor registration via VRRF process for tendered item; possible requirement to register if unregistered.
- Delivery period and exact quantities are governed by the option clause; delivery calculations follow the (Extended Quantity / Original Quantity) × Original Delivery Period formula, minimum 30 days.
- No BOQ items; scope appears to be dependent on drawings and SAF/VRRF approvals.
Terms, Conditions & Eligibility
- EMD: ₹34,383. Compliance with NDA and access to drawings is prerequisite.
- Delivery terms: Option clause allows +/- 50% quantity changes; delivery period adjusted accordingly with minimum 30 days.
- Penalties: LD at 0.5% per week up to 10% of delayed value.
- Documentation: NDA, SAF registration via VRRF, drawing access post-NDA, technical compliance evidence.
- Pre-qualification: Vendors must be capable to manufacture per drawing/specifications; registration for tendered store via SAF.
- Confidentiality: NDA binding; drawings may be released only after NDA and TOD prerequisites are met.