NMDC Steel Limited seeks supply of gear box bevel and gear box worm/bevel components under a GeM-based procurement process. The scope centers on the supply of goods only, with delivery constrained to within 180 days from order placement. The contract contemplates a multiplier option clause allowing up to 25% quantity variation during contract execution at contracted rates, and requires shock-proof packaging to prevent transit damage. The selection emphasizes the supplierβs stated make/model and adherence to GeM ATC terms, including NSL NS stores inspection and GST clarity. The opportunity is characterized by a fixed delivery cadence, inspection at destination, and payment tied to GRN-based acceptance, with a 30-day payment window post-GRN.
Technical Specifications & Requirements
- Delivery period: 180 days from order date; supplier bears timely performance risk under LD terms.
- Packaging: Shock-proof, properly packed to avoid loss/damage; responsibility lies with supplier for arrival integrity.
- Inspection: At NSL Stores; documentation-supported assessment of material.
- Certificates with dispatch: GC/WC, MTC, Test Run Certificate, Dimension Certificate, One-to-One Fitment Certificate; accompanying details for all brought-out items.
- GST: Item-wise GST percentage confirmation required.
- Payment terms: 100% payment within 30 days of GRN generation and material acceptance.
- Warranty/guarantee: As per GeM GTC; standard GeM warranty framework applies.
- Penalties: Delay penalty at 0.5% of basic order value per week for un-delivered quantity.
Terms, Conditions & Eligibility
- Delivery window: 180 days; option to extend per clause with quantity variation up to 25%.
- Mode of submission: Bids via GeM Portal only; no alternate submission.
- Quoted make: Bidders must specify the exact make in bid documents.
- Inspection plan: NSL Stores inspection plan based on available documents.
- Payment: 100% payment within 30 days of GRN after receipt/acceptance.
- GST clarity: Provide item-wise GST percentage; ensure GST compliance for all items.
- Packaging responsibility: Ensure secure packaging for damage-free delivery; supplier liability ends on arrival.
- Warranty: As per GeM GTC; standard warranty terms apply.