TenderDekho Logo
Closed GEM

Chennai Petroleum Corporation Limited Scaffolding, Articulated Boom Lift & Scissor Lift Supply, Erection & Dismantling Tender Chennai 2025

Bid Publish Date

02-Dec-2025, 9:56 am

Bid End Date

30-Dec-2025, 2:00 pm

EMD

₹1,42,000

Value

₹4,68,02,020

Generate Docs

Progress

RA
Issue02-Dec-2025, 9:56 am
Reverse Auction14-Feb-2026, 5:00 pm
Award02-Mar-2026, 2:56 am
Explore all 4 tabs to view complete tender details

Quantity

1

Bid Type

Two Packet Bid

Categories 16

Tender Overview

The Procuring Organization is Chennai Petroleum Corporation Limited, issuing a service-centric tender for Supply, Erection & Dismantling of Scaffolding and Articulated Boom Lift & Scissor Lift to support pipeline inspection and thickness gauging during the pre-shutdown phase of Refinery-III M&I Shutdown. The estimated contract value is ₹46,802,019.52 with an earnest money deposit of ₹142,000. Location details are unspecified in the summary, but the engagement targets the Refinery-III facility. A key differentiator is the combination of scaffold systems with boost-lift machinery for complex inspection tasks, necessitating coordinated erection and dismantling with safety compliance.

The bid opportunity requires bidders to demonstrate capability to mobilize, install, operate, and remove scaffolding alongside articulated boom lifts and scissor lifts in refinery environments, aligning with pre-shutdown timelines. The contract scope emphasizes on-site logistics, safety management, and coordination with refinery maintenance teams.

Keywords embedded include: tender in Chennai, CPCL procurement, scaffolding and lift equipment, pre-shutdown maintenance bid, and refinery inspection support.

Technical Specifications & Requirements

  • Product/Service: Supply, Erection & Dismantling of Scaffolding, Articulated Boom Lift, and Scissor Lift for pipeline inspection and thickness gauging
  • Scope: Support during Pre Shutdown of Refinery-III M&I Shutdown
  • Estimated Value: ₹46,802,019.52; EMD: ₹142,000
  • Equipment: Onsite scaffolding systems + mobile elevating work platforms (MEWP)
  • Context: Integration with refinery inspection services and thickness gauging procedures
  • Deliverables: Erection, systematic dismantling, and removal with safety sign-off
  • Compliance: Maintain site safety, PPE adherence, and coordination with CPCL
  • Experience/Capability: Demonstrated ability to mobilize and execute scaffold and lift operations in refinery environments
  • Location: Refinery-III facility (refinery context implied)
  • Terms: Optional contract quantity/duration variation up to 25%; excess settlement option for additional charges with supporting documents

Terms, Conditions & Eligibility

  • EMD: ₹142,000; payment terms per contract
  • Quantity/Duration Variation: Allowed up to 25% increase/decrease at contract issue and post-issue period
  • Excess Settlement: Additional charges permitted up to a specified percentage of item-level value with appropriate documentation
  • Documentation: Submit standard tender documents and any site-specific safety certifications as required by CPCL
  • Warranty/Support: Not explicitly stated; refer to tender terms for service-level expectations
  • Eligibility: Demonstrated capability to handle refinery safety-critical scaffolding and MEWP operations; coordination with CPCL M&I Shutdown teams
  • Delivery/Execution: Mobilization and demobilization aligned with pre-shutdown schedule; ensure compliance with safety norms

Key Specifications

  • Product/service names and categories: Scaffolding supply, erection & dismantling; articulated boom lift; scissor lift

  • Quantities/values: Estimated contract value ₹46,802,019.52; EMD ₹142,000

  • Standards/qualifications: refinery safety compliance; MEWP operation in high-risk environments

  • Delivery/installation: On-site mobilization at Refinery-III for pre-shutdown; dismantling post-work

  • Experience: Proven ability to perform scaffolding and MEWP operations in refinery settings

  • Terms: 25% quantity/duration variation permitted; excess settlement option with documentation

Terms & Conditions

  • Key Term 1: Quantity or duration may be adjusted up to 25% at contract issue

  • Key Term 2: Excess settlement allows additional charges with documented justification

  • Key Term 3: EMD amount is ₹142,000; standard bid documents required

Important Clauses

Payment Terms

Payment terms aligned to contract milestones with EMD compliance; exact terms to be defined in contract

Delivery Schedule

Mobilization for pre-shutdown activities; on-site erection, operation, and dismantling of scaffolding and MEWP within shutdown window

Penalties/Liquidated Damages

Penalties for delays or non-compliance to safety and workmanship standards; details to be specified in contract

Bidder Eligibility

  • Experience in supplying and operating scaffolding and MEWP in refinery environments

  • Financial stability evidenced by statements

  • Ability to mobilize quickly for pre-shutdown activities

Additional Tender Data

Commercial Details

Tender Category

Service

Bid To RA

No

Bid To RA Enabled

Yes

Item Category

Custom Bid for Services - CPCLV25456 Supply, Erection & Dismantling of Scaffolding and Articulated Boom Lift & Scissor Lift for Pipeline Inspection/ Thickness gauging in various units of Refinery-III, during Pre Shutdown of Refinery-III M&I Shutdown ..

Authority Records

MINISTRY OF PETROLEUM AND NATURAL GASCHENNAI PETROLEUM CORPORATION LIMITED

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 8

GeM-Bidding-8660072.pdf

Main Document

Scope Of Work Document

SCOPE_OF_WORK

Other Documents

OTHER

Payment Terms & Condition

PAYMENT

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Required Documents

1

GST registration certificate

2

Permanent Account Number (PAN) card

3

Experience certificates for similar scaffolding and MEWP projects

4

Financial statements or turnover proof (as applicable)

5

EMD deposit receipt or bank guarantee

6

Technical bid documents demonstrating capability to supply, erect, operate, and dismantle scaffolding, boom lifts, and scissor lifts

7

OEM authorization or dealership certificates for lift equipment (if required)

8

Safety certifications and site-access credentials (as applicable)

Corrigendum Updates

2 Updates
#1

Update

23-Dec-2025

Extended Deadline

30-Dec-2025, 2:00 pm

Opening Date

30-Dec-2025, 2:30 pm

#2

Update

16-Dec-2025

Extended Deadline

23-Dec-2025, 2:00 pm

Opening Date

23-Dec-2025, 2:30 pm

Reverse Auction Schedule

Completed

Start

14-Feb-2026, 5:00 pm

End

16-Feb-2026, 5:00 pm

Duration: 48 hours

Reverse Auction Document

✅ RA concluded. Check financial results for final rankings.

Technical Results

S.No Seller Date Status
1
ARROW ENGINEERING ENTERPRISES   Under PMA
16-12-2025 11:19:56
2
B.B.N. ENGINEERING PRIVATE LIMITED   Under PMA
23-12-2025 13:16:51
3
INDIA INSULATION PRIVATE LIMITED   Under PMA
23-12-2025 13:17:06
4
LAKSHYARAJ ASSOCIATES   Under PMA
27-12-2025 16:53:27
5
MAAGNUS INFRATECH   Under PMA
27-12-2025 13:12:41
6
R/L Construction & Commercial Services   Under PMA
27-12-2025 16:52:53
7
SRI ENGINEERING WORKS   Under PMA
16-12-2025 10:46:04
8
SRI GANAPATHY ENTERPRISES   Under PMA
15-12-2025 13:33:34
9
sri lakshmi enterprises   Under PMA
30-12-2025 13:44:21
10
VINAYAGA ENTERPRISES   Under PMA
16-12-2025 12:15:24

Financial Results

Rank Seller Price Item
L1
B.B.N. ENGINEERING PRIVATE LIMITED( MSE Social Category:General )    Under PMA
Item Categories : Custom Bid for Services - CPCLV25456 Supply, Erection & Dismantling of Scaffolding and Articulated
L2
SRI ENGINEERING WORKS   Under PMA
Item Categories : Custom Bid for Services - CPCLV25456 Supply, Erection & Dismantling of Scaffolding and Articulated
L3
ARROW ENGINEERING ENTERPRISES( MSE Social Category:OBC )    Under PMA
Item Categories : Custom Bid for Services - CPCLV25456 Supply, Erection & Dismantling of Scaffolding and Articulated
L4
VINAYAGA ENTERPRISES( MSE Social Category:SC )    Under PMA
Item Categories : Custom Bid for Services - CPCLV25456 Supply, Erection & Dismantling of Scaffolding and Articulated

Contract / Result Documents 4

Please sign in or create an account to view contract details and download result documents.

Frequently Asked Questions

Key insights about TAMIL NADU tender market

How to bid for Chennai CPCL scaffolding tender 2025

Bidders must submit GST, PAN, experience certificates, financials, EMD ₹142,000, and technical bid. Demonstrate refinery-scale scaffolding and MEWP capability, provide OEM authorizations if required, and confirm adherence to safety standards for pre-shutdown work.

What documents are required for CPCL scaffolding bid 2025

Required documents include GST certificate, PAN, experience certificates for similar projects, financial statements, EMD receipt, technical bid detailing capability to supply erection/dismantling of scaffolding and lifts, and OEM authorizations if applicable.

What are the equipment specifications for lift systems in CPCL tender

Equipment must include verified scaffolding systems, articulated boom lifts, and scissor lifts suitable for refinery inspections. Emphasis on safety compliance, on-site performance during pre-shutdown, and compatibility with pipeline thickness gauging tasks.

What is the EMD amount for CPCL pre-shutdown tender

The EMD amount is ₹142,000. It must accompany the bid as per CPCL terms, with the tender submission detailing payment method and validity period during evaluation.

When is the delivery/mobilization period for CPCL scaffold bid

Mobilization must align with the refinery's pre-shutdown schedule for Refinery-III. Exact dates are provided in the contract; bidders should prepare rapid deployment capabilities and safety-compliant execution plans.

What standards or certifications are required for CPCL lift tender

Required standards include refinery safety compliance for MEWP, equipment-specific certifications, and OEM authorizations if specified. Ensure the equipment meets regulatory requirements and safety norms for high-risk industrial deployments.

How to handle quantity variation in CPCL tender 25%

Contract allows up to 25% variation in quantity or duration at issue and post-issue. Bidders should price flexibly and document capability to scale mobilization, with plans for additional resources and logistics.

What is the scope of pre-shutdown works for CPCL scaffolding

Scope includes supply, erection, operation, and dismantling of scaffolding and MEWP to support pipeline inspection and thickness gauging during Refinery-III M&I Shutdown, ensuring safe access and procedural compliance.