Compute Servers,External Storage Platform 1,External Storage Platform 2,Archive Application and Arc
Metnet : An E-governance Intra-imd Portal New Delhi
SOUTH DELHI, DELHI
Menu
Bid Publish Date
24-Oct-2025, 3:15 pm
Bid End Date
19-Dec-2025, 3:00 pm
EMD
₹30,00,000
Progress
Quantity
35
Category
GPU Compute System
Bid Type
Two Packet Bid
South Asian University invites bids for a comprehensive suite of high-performance computing and data center infrastructure, including Master System, Compute System, GPU Compute System, PFS Storage Disk Arrays, PFS Storage IO nodes, Smart Rack Solution, Fire Detection and Suppression System, Rodent Repellent System, UPS, Ethernet Network Switch, IB Switch, Remote Monitoring System, SW Stack, plus Installation, Training and Documentation, with Warranty and Support for 5 years, One onsite HPC Linux expert, and Year 6–7 AMC. The bid includes an EMD of ₹3,000,000 and a flexible quantity option of up to 25% increase during contract execution. Delivery terms align with the option clause, starting from the last date of original delivery order, with minimum extension rules described. Location details are not specified and require clarification. This tender emphasizes turnkey HPC and data center deployment with long-term support.
Master System and Compute System procurement for HPC workloads
GPU Compute System and PFS Storage Disk Arrays with IO nodes
Smart Rack Solution and Fire/Rodent protection systems
Uninterruptible Power Supply (UPS) and Ethernet/IB Switches
Remote Monitoring System and Software Stack
Installation, Training, Documentation, 5-year Warranty
Onsite HPC Linux expert and AMC for years 6-7
EMD of ₹3,000,000 required; bid security along with bid submission
Option clause allows ±25% quantity changes; delivery timelines adjust accordingly
5-year warranty with Year 6-7 AMC; onsite HPC expert included in scope
Not specified in provided data; bidders should review ATC for terms related to payments, milestones, and penalties.
Delivery period tied to last date of original delivery order; additional time as per option clause with minimum 30 days.
Not detailed in available data; ATC may include LD and performance bond terms—verify during bid submission.
Experience in large-scale HPC/data-center hardware deployment
Demonstrated capability to provide onsite HPC Linux expert services
Financial capacity to mobilize ₹3,000,000 EMD and multi-year AMC commitments
Metnet : An E-governance Intra-imd Portal New Delhi
SOUTH DELHI, DELHI
Centre For Development Of Advanced Computing (c-dac)
PUNE, MAHARASHTRA
Controller General Of Defence Accounts
Oil India Limited
GAUTAM BUDDHA NAGAR, UTTAR PRADESH
Indian Army
JABALPUR, MADHYA PRADESH
Tender Results
Loading results...
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) |
|---|---|---|---|---|---|---|
| 1 | Master System | HPC master node | 2 | piece | vineetg | 56 |
| 2 | Compute System | CPU compute node | 10 | piece | vineetg | 56 |
| 3 | GPU Compute System | GPU compute node | 3 | piece | vineetg | 56 |
| 4 | PFS Storage Disk Arrays | 1000TB Lustre | 1 | piece | vineetg | 56 |
| 5 | PFS Storage IO nodes | I/O node | 4 | piece | vineetg | 56 |
| 6 | Smart Rack Solution | Cooling - Rack - nodes - switch etc | 1 | piece | vineetg | 56 |
| 7 | Fire Detection and Suppression System | Fire Detection and Suppression System | 1 | piece | vineetg | 56 |
| 8 | Rodent Repellent System | Ultrasonic Rodent Repellers | 1 | piece | vineetg | 56 |
| 9 | UPS | UPS with 30 min backup | 1 | piece | vineetg | 56 |
| 10 | Ethernet Network Switch | 48-port 1Gig Ethernet Network Switch | 2 | piece | vineetg | 56 |
| 11 | IB Switch | 64-port (32 OSFP) Managed NDR 400Gb/s | 1 | piece | vineetg | 56 |
| 12 | Remote monitoring System | Integrated | 1 | piece | vineetg | 56 |
| 13 | SW Stack | Workload Manager - Cluster Management - OS etc | 1 | number | vineetg | 56 |
| 14 | Installation | Installation | 1 | unit | vineetg | 56 |
| 15 | Training and Documentation | Training and Documentation | 1 | unit | vineetg | 56 |
| 16 | Warranty and Support for 5 years | Five years OEM NBD onsite warranty | 1 | unit | vineetg | 56 |
| 17 | One onsite HPC Linux expert | Manpower for three months post commissioning | 1 | unit | vineetg | 56 |
| 18 | Year 6 AMC | 6th Year Comprehensive AMC | 1 | unit | vineetg | 1,825 |
| 19 | Year 7 AMC | 7th Year Comprehensive AMC | 1 | unit | vineetg | 1,825 |
Discover companies most likely to bid on this tender
GST registration
Permanent Account Number (PAN) card
Experience certificates for similar HPC/data-center deployments
Financial statements demonstrating capacity for large-scale procurement
EMD submission receipt showing ₹3,000,000
Technical bid documents and compliance certificates
OEM authorizations and software stack qualifications
Extended Deadline
19-Dec-2025, 3:00 pm
Opening Date
19-Dec-2025, 3:30 pm
Extended Deadline
12-Dec-2025, 3:00 pm
Opening Date
12-Dec-2025, 3:30 pm
Extended Deadline
08-Dec-2025, 11:00 am
Opening Date
08-Dec-2025, 11:30 am
Extended Deadline
02-Dec-2025, 11:00 am
Opening Date
02-Dec-2025, 11:30 am
Extended Deadline
21-Nov-2025, 6:00 pm
Opening Date
21-Nov-2025, 6:30 pm
Bidders must submit GST registration, PAN, experience certificates for similar HPC deployments, financial statements, EMD ₹3,000,000, technical bid documents, OEM authorizations, and software stack qualifications as described in the ATC.
The purchaser may alter order quantity by up to 25% at contract placement and during currency. Delivery extension is calculated as (additional quantity ÷ original quantity) × original delivery days, with a minimum of 30 days.
The EMD is ₹3,000,000. Bidders must provide a valid bid security deposit in approved form, as specified in the ATC, to participate in the tender.
The contract includes a 5-year warranty with Year 6 and Year 7 AMC. An onsite HPC Linux expert is included for the initial period, with annual maintenance commitments extending into subsequent years.
Categories include Master System, Compute System, GPU Compute System, PFS Storage Disk Arrays, PFS Storage IO nodes, Smart Rack, Fire/Suppression, Rodent Repellent, UPS, Ethernet/IB switches, Remote Monitoring, SW Stack, Installation, Training, and Documentation.
Review the ATC uploaded by SAU; confirm the 19-item BOQ scope, request clarifications on item quantities, and ensure bid pricing accommodates potential 25% quantity variations per the option clause.
Sign up now to access all documents
Main Document
OTHER
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Choose from flexible plans to access tender documents instantly
Main Document
OTHER
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS