The estimated project cost is approximately โน75,71,468.37. The financial bid should include a detailed breakdown of costs for materials, labor, equipment, and overheads. Payment terms are aligned with project milestones, with an initial mobilization advance and subsequent payments based on work progress.
| Cost Component |
Estimated Amount |
| Material & Equipment |
As per actuals |
| Labor |
As per tender norms |
| Overheads |
As applicable |
| Total Estimated Cost |
โน75,71,468.37 |
Bidders must submit a Bank Guarantee or Bank Solvency Certificate for at least 20% of the bid amount. Payment schedule:
- 10% advance on mobilization.
- 70% on completion of foundation and tower erection.
- 20% after successful testing and commissioning.
All payments are subject to verification and approval by GETCO authorities.