The scope of work involves the construction of a flood protection wall along the left bank of the Harnav-Guhai Link Canal at Ch. 910 meters, located in Vijaynagar, Sabarkantha district, Gujarat. Key deliverables include:
- Site preparation and clearing
- Excavation and foundation work
- Construction of the flood protection wall as per the provided BoQ and technical specifications
- Installation of necessary reinforcements and drainage systems
- Final finishing and quality checks
The process involves:
- Mobilization of resources and site setup
- Execution of earthworks and foundation laying
- Wall construction using specified materials
- Quality assurance and safety compliance
- Final inspection and handover
Bidder must review the detailed tender documents, including the BoQ, test schedules, and technical guidelines, available for download.
| Specification |
Details |
| Length of Wall |
910 meters |
| Material |
Reinforced concrete as per standards |
| Completion Period |
3 months |
| Estimated Cost |
15,185,820 INR |