Gujarat State Electricity Corporation Limited (GSECL) is inviting bids from qualified contractors for a critical transformer shifting project at Gandhinagar Thermal Power Station. This open tender aims to enhance operational efficiency by relocating ESP HV Rectifier Transformers across Units 3, 4, and 5. The project involves detailed planning, safe disconnection, transportation, and reinstallation of high-voltage transformers, with a completion timeline of 18 months. Bidders must meet strict eligibility criteria, including technical experience and financial stability, and submit their proposals electronically through the NPROCURE portal. The tender process includes multiple evaluation stages, focusing on technical competence and cost-effectiveness. Download the detailed tender document to review specifications, terms, and conditions. This opportunity is ideal for electrical contractors and firms specializing in power plant electrical works, transformer handling, and infrastructure upgrades, contributing to Gujarat’s energy infrastructure development.

Scope Of Work

• Relocate ESP HV Rectifier Transformers between the top and ground floors of Units 3, 4, and 5 at Gandhinagar TPS.
• Perform detailed site survey to plan the shifting process.
• Ensure safety protocols are strictly followed during all activities.
• Disconnect transformers from existing connections following standard procedures.
• Transport transformers using suitable lifting and transportation equipment.
• Reinstall transformers at the designated locations with proper alignment and connections.
• Test and commission the transformers post-shifting to ensure operational readiness.
• Coordinate with plant operations to minimize downtime.
• Prepare and submit progress reports at each stage.

Task Description
Planning Site survey, risk assessment, and method statement preparation
Disconnection Safely disconnect transformers from existing connections
Transportation Use of cranes, trucks, and safety measures
Reinstallation Proper positioning, electrical connections, and grounding
Testing Insulation, load testing, and operational checks
Handover Final documentation and approval

• Key deliverables include: detailed work plan, safety compliance reports, and commissioning certificates.
• The work must be completed within 18 months from the date of contract signing.

Technical Specifications

The transformers involved are high-voltage electrostatic precipitator (ESP) rectifier transformers with the following parameters:

Parameter Specification
Voltage Rating 11 kV / 3.3 kV
Power Capacity As per existing transformers
Cooling Type Oil-cooled
Insulation Level Class H
Transportation Method Heavy-duty crane and transport vehicles

Sequential process for technical execution:

  1. Conduct site survey and prepare method statement.
  2. Obtain necessary approvals and safety clearances.
  3. Disconnect transformers following electrical safety norms.
  4. Use cranes and specialized equipment for lifting.
  5. Transport transformers to designated locations.
  6. Reinstall with proper electrical and grounding connections.
  7. Perform insulation and operational testing.
  8. Finalize commissioning and handover documentation.

Financial Requirements

The estimated budget for this transformer shifting project ranges from INR 25 Lakhs to INR 35 Lakhs, inclusive of all labor, materials, transportation, and testing costs. The financial breakdown is as follows:

Cost Component Estimated Cost
Material and Equipment INR 10 Lakhs
Labor and Skilled Work INR 12 Lakhs
Transportation INR 3 Lakhs
Testing and Commissioning INR 2 Lakhs
Contingencies INR 3 Lakhs

Payment terms are linked to project milestones:

  • 30% advance upon contract signing.
  • 40% after completion of disconnection and transportation.
  • 30% after successful testing and commissioning.
    All payments are subject to submission of relevant certificates and reports.
Advertisement

Tender Data

Bid Details

Tender Type

Open

Sector

Power and Energy

Tender Fee

₹1,770

Contract Form

Works

Completion Period

18  Months

Currency Type

Single

Bid Submission Start

12-10-2026 18:00:00

Document Download End

30-10-2026 18:00:00

Bid Validity

180 Days

Additional Tender Data

Commercial Details

Tender Category

Service

Bid To RA

No

Item Category

Miscellaneous Works

Authority & Contact

Officer Inviting Bids

CHIEF ENGINEER (G)

Bid Opening Authority

CHIEF ENGINEER (G)

Address

CHIEF ENGINEER (GEN.), GUJARAT STATE ELECTRICITY CORPORATION LTD, Gandhinagar TPS.

Contact Details

[email protected]

Authority Records

GUJARAT STATE ELECTRICITY CORPORATION LIMITED

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 1

GTPS_Tender _ EW-359_26_09_2026.pdf

TENDER_DOCUMENT

Authority & Contact

Department

Thermal Power Station, Gandhinagar

Officer Inviting Bids

CHIEF ENGINEER (G)

Bid Opening Authority

CHIEF ENGINEER (G)

Contact Details

[email protected]

Address

CHIEF ENGINEER (GEN.), GUJARAT STATE ELECTRICITY CORPORATION LTD, Gandhinagar TPS.

Categories 12

Advertisement

Bidding Process

Process Timeline

1. Preliminary Stage

05-11-2026 15:00

2. Technical Stage

05-11-2026 15:10

3. Price Bid

Required Forms

Preliminary

Tender Fee Form

Library-Standard

Required

Emd Fee Form

Library-Standard

Required

Technical

PARTY DETAILS

User Defined Template-Standard

Required

Stop Deal And Black List

User Defined Template-Standard

Required

Certificate-A

User Defined Template-Standard

Required

Bidder Confirmation

User Defined Template-Standard

Required

Price

GTPS Price Bid EW-359

User Defined Template-Secured

Required

Required Documents

Stage - Preliminary Stage

1

Attach scan copy of Tender Fee & EMD

Required

Stage - Technical Stage

1

Attach scan copy of supporting documents as per tender

Required

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Eligibility Criteria

  • ✓ Must have valid electrical contractor license and experience in transformer handling.
  • ✓ Must submit all required documents, including tender fee and EMD, for preliminary approval.
  • ✓ Must provide supporting technical documents as per tender specifications.
  • ✓ Must demonstrate financial stability with relevant turnover and past project experience.
  • Key financial eligibility:
Criteria Minimum Requirement
Annual Turnover INR 50 Lakhs
Past Projects At least 2 similar transformer shifting projects in the last 3 years
EMD As specified in tender document
  • ✓ Bidders should not be blacklisted or debarred by any government authority.
  • ✓ Must comply with all safety, environmental, and quality standards mandated by the authorities.

Frequently Asked Questions

Key insights about GUJARAT tender market

What is the deadline for bid submission?

The bid submission deadline is 30th October 2026 at 6:00 PM. Ensure all documents are uploaded before this time to avoid disqualification.

How can I download the tender documents?

Tender documents are available for free on the official NPROCURE portal under tender notice EW-359. Click the download link and review all specifications thoroughly.

What are the key eligibility requirements?

Eligible bidders must have valid electrical licenses, experience in transformer shifting, submit EMD and tender fee, and provide supporting technical documents as specified. Refer to the detailed eligibility criteria for full details.

Is a site visit mandatory before bidding?

A site visit or pre-bid meeting is not mandatory but recommended for better understanding. Arrangements can be made upon request to facilitate site inspection.

What are the payment terms for the project?

Payments will be made in installments: 30% advance, 40% after disconnection and transportation, and 30% after successful testing and commissioning. All payments are subject to submission of relevant certificates.