Bharat Heavy Electricals Limited Structural Steel Sole Plate Tender 2026 - ATC Provisions, Inspection & Materials

Bid Publish Date

08-Aug-2026, 11:20 am

Bid End Date

21-Aug-2026, 6:00 pm

Progress

Issue08-Aug-2026, 11:20 am
AwardPending

Tender Overview

Bharat Heavy Electricals Limited (BHEL) invites bids for STRUCTURAL STEEL SOLE PLATE-1, -2, -3. The tender contemplates multiple-quantity procurement with an option clause permitting up to 25% quantity variation at contracted rates. Delivery sequencing starts from the last date of the original delivery order, with extended time proportional to added quantity, minimum 30 days. The buyer reserves rights to terminate for non-compliance or delivery failure, and emphasizes material testing as a key acceptance criterion. The project involves pre- and post-dispatch inspection by approved agencies and requires submission of certification alongside the bid. This tender lacks BOQ items and has unspecified location details.

Technical Specifications & Requirements

  • Inspection: Pre-dispatch inspection at supplier premises (if ATC selected) by TPIA; Post-receipt inspection at BHEL, Bhopal.
  • Certifications: Bidder must upload all requested certificates; material test certificates must accompany supply and will be evaluated by Buyer’s Lab.
  • Acceptance: Lab results govern item acceptance; failure triggers rejection.
  • ATC: Internal acceptance clauses referenced; ensure compliance with supplier form and attachments.
  • Delivery & Terms: Quantity adjustments permissible up to 25%; delivery period linked to original delivery date with minimum 30 days extension; termination rights reserved for non-performance.
  • BOQ: Not available; itemized quantities are not published in the current data.

Terms, Conditions & Eligibility

  • EMD/Security: Specific EMD amount not disclosed in ATC; bidders should rely on standard tender security provisions.
  • Delivery: Extended delivery time calculation is (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days.
  • Inspection & Quality: Pre-dispatch and post-receipt inspections; material test certificates mandatory with supply.
  • Termination: Buyer can terminate for material non-compliance, delivery delay, insolvency, or misrepresentation.
  • Documentation: Upload required certificates/documentation; non-compliance risks rejection.

Key Specifications

  • Product/service names: STRUCTURAL STEEL SOLE PLATE-1, STRUCTURAL STEEL SOLE PLATE-2, STRUCTURAL STEEL SOLE PLATE-3

  • Quantities: Not published in BOQ; quantity variation up to 25% permitted

  • EMD/Estimated value: Not disclosed in ATC

  • Category: Structural steel components for industrial use

  • Quality/Compliance: Material Test Certificate mandatory; Buyer lab to determine acceptance

  • Delivery: Original delivery period; extended period via option clause with minimum 30 days

  • Standards/Testing: Pre-dispatch inspection, post-receipt inspection; ATC forms to be filled

Terms & Conditions

  • Option clause allows up to 25% quantity variation at contracted rates

  • Delivery period extends proportionally with added quantity, min 30 days

  • Material Test Certificate required; lab results govern acceptance

Important Clauses

Payment Terms

Not specified in ATC; standard tender terms apply with security deposit as per buyer policy

Delivery Schedule

Delivery starts from the last date of original delivery order; extended time proportional to quantity increase, min 30 days

Penalties/Liquidated Damages

Not explicitly stated; termination rights exist for delays or non-compliance

Bidder Eligibility

  • Experience in supplying structural steel components for industrial projects

  • Financial stability evidenced by annual turnover and financial statements

  • Capability to provide Material Test Certificates and OEM authorizations if required

Tender Data

Bid Details

Quantity

160

Category

STRUCTURAL STEEL SOLE PLATE -1

Bid Type

Two Packet Bid

Bid Validity

90 (Days)

Bid Type

Service

Evaluation

Item wise evaluation

Inspection Required

No

RA Qualification Rule

H1-Highest Priced Bid Elimination

Tech Clarification Time

3 Days

Preference & Exemptions

EMD Required

No

MII Purchase Preference

Yes

MII Preference Band

L1+20%

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

Yes

Requirements

Warranty Period

1 years

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

Yes

Item Category

STRUCTURAL STEEL SOLE PLATE -1 , STRUCTURAL STEEL SOLE PLATE-2 , STRUCTURAL STEEL SOLE PLATE-3

Payment Timelines

Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

Delivery Details

Max Delivery Days

60

Delivery Locations

1

Delivery Cities

Bhopal

Delivery Pincodes

462022

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Arun Kumar462022,BHARAT HEAVY ELECTRICAL LTD, PIPLANIBhopalMadhya Pradesh4620226060-

Authority Records

MINISTRY OF HEAVY INDUSTRIESHEAVY INDUSTRY DEPARTMENT

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 6

GeM-Bidding-9727929.pdf

Main Document

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Categories 6

Required Documents

1

GST registration certificate

2

Permanent Account Number (PAN) card

3

Experience certificates for similar structural steel sole plate supplies

4

Financial statements or turnover evidence

5

Material Test Certificate (MTC) for supplied items

6

OEM authorization (if applicable)

7

Technical compliance certificates relevant to structural steel components

8

Any ATC-compliant filled forms referenced in buyer terms

Frequently Asked Questions

Key insights about MADHYA PRADESH tender market

How to bid for structural steel sole plate tender in BHEL 2026

To bid for the BHEL sole plate procurement, ensure you meet eligibility criteria, upload GST and PAN, furnish experience certificates for similar steel plate supplies, and attach Material Test Certificates. The bid requires pre- and post-dispatch inspection, OEM authorizations if applicable, and adherence to specified option clause allowing up to 25% quantity variation.

What documents are required for BHEL steel plate bid 2026

Submit GST registration, PAN, company financials, experience certificates for similar projects, Material Test Certificate, OEM authorization (if applicable), and technical compliance certificates. Ensure all documents are uploaded with the bid submission as per ATC requirements to avoid rejection.

What are the delivery terms for BHEL sole plate procurement

Delivery starts from the last date of the original delivery order. If quantity increases, extended delivery time is (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum extension of 30 days. The buyer may extend up to 25% of contracted quantity during currency.

What inspections are required for BHEL structural steel plates

Pre-dispatch inspection is conducted at supplier premises if ATC requires, by the nominated agency (TPIA). Post-receipt inspection occurs at BHEL, Bhopal. Material Test Certificates are mandatory, and lab results govern acceptance.

What standards or certifications must be provided for this tender

Bidders must provide Material Test Certificate with steel plates and any applicable OEM authorizations. While specific IS/ISO standards are not listed in the data, ensure compliance with standard material testing practices and any organization-specified ATC forms.

When is the price variation allowed for this BHEL tender

Price variation is allowed through the option clause permitting up to 25% quantity variation at contracted rates. The extended delivery time is calculated per the formula but must include a minimum extension of 30 days.

What happens if I fail to deliver as per terms in BHEL tender

The Buyer reserves rights to terminate the contract or parts thereof for material non-compliance or failure to deliver within stipulated periods. Additional grounds include insolvency, misrepresentation, or failure to replace/reject defective material promptly.

What is required for post-delivery acceptance at BHEL Bhopal

Post-receipt inspection at BHEL, Bhopal is mandatory. Acceptance hinges on favorable lab results from the Buyer’s Lab. Ensure all supplied material has valid Material Test Certificates and is compliant with the ATC terms.