Progress
The Indian Army, Department Of Military Affairs, inviting bids for multiple automotive electrical and lighting components located in NAGAON, ASSAM (782001). Procurement scope covers items within the CATEGORY listing: ASSY AC COMPRESSOR SP 17, ASSY CONDENSER COMPLETE 24 V, KIT MASTER CYLINDER MINOR, HEAD LIGHT BULB, FOG LAMP BULB. Estimated value and exact quantities are not disclosed in the data, but the BOQ comprises five items with non-disclosed quantities. The tender emphasizes supply-chain flexibility via a 25% quantity variation clause and extended delivery periods under option clauses, making both initial and amended delivery planning critical. Bidders must ensure compliance with documentation and organizational stability criteria to participate. Unique aspects include a government defense procurement context and mandatory certificate uploads for Vendor Code creation.
Product category: automotive electrical components and lighting
Quantities: not disclosed (BOQ shows 5 items with N/A quantities)
EMD/Estimated value: not disclosed
Experience: defense procurement context implies need for compliance and traceability
Quality/Testing: standard automotive parts compliance presumed; no explicit standards listed
25% quantity variation right for purchase and during contract
Mandatory PAN, GSTIN, cancelled cheque, EFT mandate for bid submission
Vendor Code creation required; upload of necessary certificates
Not specified in data; subject to AtC and Corrigendum if issued
Delivery period starts from last date of original delivery order; extended time due to option clause; minimum 30 days
Not specified in data; likely governed by standard defense procurement LD terms if any
Not under liquidation, court receivership, or bankruptcy
Valid PAN and GSTIN, and EFT mandate
Capability to supply automotive electrical components and lighting for defense material
Quantity
7
Category
ASSY AC COMPRESSOR SP 17
Bid Type
Two Packet Bid
Bid Validity
30 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
OEM Avg. Turnover
1
Past Performance
80 %
Experience Required
1 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
ASSY AC COMPRESSOR SP 17 , ASSY CONDENSER COMPLETE 24 V , KIT MASTER CYLINDER MINOR , HEAD LIGHT BULB , FOG LAMP BULB
Max Delivery Days
21
Delivery Locations
1
Delivery Cities
Nagaon
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | Nagaon | Nagaon | - | - | 1 | 21 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
GEM_GENERAL_TERMS_AND_CONDITIONS
ASSY AC COMPRESSOR SP 17
TATA HMV 8X8
ASSY CONDENSER COMPLETE 24 V
TATA HMV 8X8
KIT MASTER CYLINDER MINOR
TATA HMV 8X8
HEAD LIGHT BULB
TATA HMV 8X8
FOG LAMP BULB
TATA HMV 8X8
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | ASSY AC COMPRESSOR SP 17 | TATA HMV 8X8 | 1 | nos | buyer@98 | 21 | |
| 2 | ASSY CONDENSER COMPLETE 24 V | TATA HMV 8X8 | 1 | nos | buyer@98 | 21 | |
| 3 | KIT MASTER CYLINDER MINOR | TATA HMV 8X8 | 1 | nos | buyer@98 | 21 | |
| 4 | HEAD LIGHT BULB | TATA HMV 8X8 | 2 | nos | buyer@98 | 21 | |
| 5 | FOG LAMP BULB | TATA HMV 8X8 | 2 | nos | buyer@98 | 21 |
Discover companies most likely to bid on this tender
PAN Card copy
GSTIN copy
Cancelled Cheque copy
EFT Mandate certified by bank
Undertaking of legal/financial standing (no liquidation/bankruptcy)
Any certificates required for vendor code creation
Technical bid documents as per ATC and Corrigendum (if issued)
Key insights about ASSAM tender market
Bidders should prepare PAN, GSTIN, cancelled cheque, and EFT mandate; ensure vendor code creation; provide undertaking against liquidation; submit certificates as per ATC/Corrigendum; comply with 25% quantity variation clause and defense procurement delivery terms.
Required documents include PAN, GSTIN, cancelled cheque, EFT mandate, vendor code related certificates, and any certificates for OEM authorization; ensure accuracy and legibility to avoid bid rejection; upload all requested materials with the bid.
No explicit TPS in data; bidders should align to standard automotive electrical compressor specs used in defense kits; ensure compatibility with 24V condenser assemblies and related lighting components per project scope.
Delivery period begins from the last date of the original delivery order; option clause may extend time; minimum extension required is 30 days; exact calendar dates depend on contract and quantity variation exercised.
EMD amount is not disclosed in the provided data; bidders should monitor official ATC/Corrigendum; ensure funds are ready to meet standard defense EMD requirements once published.
Submit PAN, GSTIN, cancelled cheque, and EFT mandate; ensure corporate eligibility with no liquidation; verify vendor code status via the procurement portal; include all required certificates to avoid bid rejection.