Bid Publish Date
08-May-2026, 8:30 pm
Bid End Date
30-May-2026, 8:00 pm
EMD
₹3,50,000
Value
₹70,00,000
Location
Progress
Quantity
6
Category
Electric or Gas Cremation Furnace
Bid Type
Two Packet Bid
The Indian government defence wing, the Dg Of Defence Estate, invites bids for a multi-item supply contract in Bareilly, Uttar Pradesh covering Electric or Gas Cremation Furnace, Stainless Steel 2 Tap & 3 Tap Chiller Commercial Water Dispenser, Cemented Benches (3-seater), Hand Pump, and RO System. Estimated contract value: ₹7,000,000.00 with an EMD of ₹350,000.00. The scope includes supply, installation, testing and commissioning of all five items. The BoQ lists 5 items with no detailed technical specs provided. The option clause permits quantity variation up to 25% during and after contract award, with time extension rules anchored to the original delivery period and a minimum 30 days ceiling. GST applicability to be assessed by bidders.
EMD amount and bid security requirements with GST implications
SITC scope including installation and commissioning; option clause enabling 25% quantity variation
Delivery timeline linked to original delivery order date; extended period rules with minimum 30 days
GST applicability to be assessed by bidder; reimbursement as actuals or applicable rate (whichever is lower); no fixed payment schedule specified in data
Delivery commences from last date of original delivery order; option for increased quantity requires recalculated delivery time: (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days
Not explicitly specified in data; ATC may contain LD provisions; potential for time-extension under option clause
Eligibility to supply SITC of five listed items with installation
Experience in defence estate or government procurement preferred
Ability to provide OEM authorizations and after-sales support
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Electric or Gas Cremation Furnace , Stainless Steel 2 Tap 3 Tap Chiller Commercial Water Cooler Dispenser , Cemented Benches 03 seater , Hand Pump , R.O. System
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Electric or Gas Cremation Furnace
As per specification document
Stainless Steel 2 Tap 3 Tap Chiller Commercial Water Cooler Dispenser
As per specification document
Cemented Benches 03 seater
As per specification document
Hand Pump
As per specification document
R.O. System
As per specification document
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | Electric or Gas Cremation Furnace | As per specification document | 1 | number | [email protected] | 30 | |
| 2 | Stainless Steel 2 Tap 3 Tap Chiller Commercial Water Cooler Dispenser | As per specification document | 1 | number | [email protected] | 30 | |
| 3 | Cemented Benches 03 seater | As per specification document | 2 | number | [email protected] | 30 | |
| 4 | Hand Pump | As per specification document | 1 | number | [email protected] | 30 | |
| 5 | R.O. System | As per specification document | 1 | number | [email protected] | 30 |
Discover companies most likely to bid on this tender
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates for similar SITC projects
Financial statements (latest audited/attested)
Emd/Security deposit proof
Technical bid documents
OEM authorizations or manufacturer approvals as applicable
Any ATC-specified certifications or compliance documents
Key insights about UTTAR PRADESH tender market
Bidders should prepare SITC-capable proposals covering supply, installation, testing and commissioning for five items. Include EMD ₹350,000, GST assessment, and OEM authorizations. Ensure alignment with the option clause permitting up to 25% quantity variation and compute delivery timelines accordingly.
Submit GST registration, PAN, latest financial statements, experience certificates for similar SITC projects, EMD receipt, technical bid, and OEM authorizations. Additional ATC-specified documents may be requested; ensure compliance with all listed in Terms and Conditions.
Five items: Electric or Gas Cremation Furnace, Stainless Steel 2 Tap & 3 Tap Chiller Water Dispenser, Cemented Benches (3-seater), Hand Pump, RO System. The BoQ data lacks explicit quantities; bidders must refer to ATC for exact item counts and specs.
The estimated value is ₹7,000,000.00. Bidders should price the full SITC scope, including installation and commissioning, while accounting for possible quantity revisions up to 25% as per the option clause.
Delivery time for additional quantity is calculated as (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum of 30 days. The purchaser may extend to the original delivery period during option exercise.
The tender data shows no explicit brand/OEM constraints; OEM authorizations may still be required as part of the submission in the ATC. Verify the ATC document for any brand-specific criteria.
Bidders must determine GST applicability themselves; the purchaser will reimburse GST at actuals or prevailing rate, whichever is lower, subject to the quoted GST percentage.
Scope includes Supply, Installation, Testing and Commissioning of the five listed items; post-installation support may be required per ATC terms, with timelines tied to original order dates and delivery schedules.