Bid Publish Date
11-Aug-2026, 4:42 pm
Bid End Date
02-Sep-2026, 12:00 pm
EMD
₹2,01,846
Location
Progress
Damodar Valley Corporation announces a tender for Retrofitting of all 11 KV VCBs of one complete Unit Switchgear at 2x600MW RTPS DVC in Purulia, WEST BENGAL. Quantity: 1. Submission Deadline: 02-09-2026 12: 00: 00. Last date to apply is approaching fast!
Quantity
1
Bid Type
Single Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
Yes
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
Yes
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Retrofitting of all 11 KV VCBs of one complete Unit Switchgear at 2x600MW RTPS DVC
Advisory Bank
PUNJAB NATIONAL BANK
ePBG Percentage
3%
ePBG Duration (Months)
30
Payment Timelines
Payments shall be made to the Seller within 15 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
100
Delivery Locations
1
Delivery Cities
Purulia
Delivery Pincodes
723133
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Vikas Kumar | 723133,Damodar Valley Corporation (RTPS), PO : Nildih, Dumdumi, Purulia | Purulia | West Bengal | 723133 | 1 | 100 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
Certificate (Requested in ATC)
OEM Authorization Certificate
Additional Doc 1 (Requested in ATC)
Additional Doc 2 (Requested in ATC)
Compliance of BoQ specification and supporting document *In case any bidder is seeking exemption from Experience / Turnover Criteria
the supporting documents to prove his eligibility for exemption must be uploaded for evaluation by the buyer