Bid Publish Date
24-Jul-2020, 5:45 pm
Bid End Date
03-Aug-2020, 3:00 pm
EMD
₹20,68,000
Value
₹10,85,64,730
Location
Progress
Public procurement opportunity for The issuing authority IRQP of Bakhtiyarpur-Mokama Section of NH-31 Left Part from CH-153. 300 (Junction of NH-30 and NH-31) to CH-168. 300 (Achuara) Via Bakhtiyarpur More, Sabnima, Athmalgola, Kalyanpur For The Year 2020-21. in BIHAR issued by. Submission Deadline: 03-08-2020 15: 00: 00. View full details and respond.
Tender Type
Open
Tender Fee
₹10,000
Tender Fee Exemption
No
EMD Exemption
No
Category
CIVIL
Bid Submission Start
24-07-2020 17:50:00
Bid Validity
120
Processing Fee
₹5,900
Tender Currency
INR
Bid Currency
INR
Ranking Sequence
L1 Ranking
Estimated Value Visibility
Y
Bid To RA
No
Organization Hierarchy
Government of Bihar->Road Construction Department->SOUTH BIHAR WING, PATNA->CENTRAL ROAD CIRCLE, PATNA->ROAD DIVISION, PATNA CITY
Approving Authority
SANJAY KUMAR SINGH (SE)
Tender Creator
Mr KAUNTEY KUMAR (EXECUTIVE ENGINEER)
Pre-Bid Discussion Type
Not Required
| Type | Amount | Currency | Mode | Exemption |
|---|---|---|---|---|
| EMD | ₹20,68,000 | INR | Challan,Internet Payment Gateway(IPG)|Bank Guarantee | No |
| Tender Fee | ₹10,000 | INR | Internet Payment Gateway(IPG),Challan| | No |
| Tender Processing Fee | ₹5,900 | INR | Internet Payment Gateway(IPG),Challan| | No |
Registration CERTIFICATE
Total value of civil engineering construction work performed in last five years.
Power of attorney of signatory Bid
Work Experience of Similar nature
Maximum Quantities of work done as prime contractor in any one year during last five years.
Bidding Capacity in lakh
Existing commitments and ongoing works
Work for which Bid already submitted
Availability of key items of Contractor's Equipment
Key Personnel
Affidavit
Undertaking
I.T. & S.T. Registration & clearance Certificate
Labour License
Character Certificate
NOC for Debar (If required)
Other Document as per NIT (If any)
Legal Status of Bidder.
Place of Registration.
Principal place of Business
Work Experience of Similar nature
Maximum Quantities of work done as prime contractor in any one year during last five years.
Bidding Capacity in lakh (More than the total Bid value of present work = A*N*3-B=Rs. ____.Where A = Maxm. Value of work executed in any one yr during last 5 yrs. N= Nos of years for completion of works. B=Value of existing commitments & ongoing works to be completed in period)
Existing commitments and ongoing works
Work for which Bid already submitted
Evidence of accesses to Financial Resources (Evidence of access to or availability of creadit facilities (10% of estimated cost), certified by bankers (Not more than 3 months old). (Rs in Lakhs).
Proposed methodology and programme of construction. (Justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
Time of Completion ( 6 months)
Registration No.
Bid Validity- Bids shall remain valid for a period not less than 120 days after the deadline date. A Bid valid for a shorter period shall be rejected by the ...
Bid Validity- Bids shall remain valid for a period not less than 120 days after the deadline date. A Bid valid for a shorter period shall be rejected by the Employer as non-responsive
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
NIT
NIT
GENERAL_DOCUMENT
GENERAL_DOCUMENT
TENDER_DOCUMENT
CORRIGENDUM
CORRIGENDUM
CORRIGENDUM
BOQ
I.R.Q.P. of Bakhtiyarpur-Mokama section of NH-31 Left Part from Km 153.300 ( Junction of N.H. 30 and N.H. 31 ) to Km 168.300 ( Junction of new Alignment of N.H. 30 and old existing N.H. 31 ) via Athmalgola , Barh , Pandarak, More for the Year 2020-21
I.R.Q.P. of Bakhtiyarpur-Mokama section of NH-31 Left Part from Km 153.300 ( Junction of N.H. 30 and N.H. 31 ) to Km 168.300 ( Junction of new Alignment of N.H. 30 and old existing N.H. 31 ) via Athmalgola , Barh , Pandarak, More for the Year 2020-21
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Attachment | Rate | Estimated Cost | Mandatory | Price Trends |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | I.R.Q.P. of Bakhtiyarpur-Mokama section of NH-31 Left Part from Km 153.300 ( Junction of N.H. 30 and N.H. 31 ) to Km 168.300 ( Junction of new Alignment of N.H. 30 and old existing N.H. 31 ) via Athmalgola , Barh , Pandarak, More for the Year 2020-21 | I.R.Q.P. of Bakhtiyarpur-Mokama section of NH-31 Left Part from Km 153.300 ( Junction of N.H. 30 and N.H. 31 ) to Km 168.300 ( Junction of new Alignment of N.H. 30 and old existing N.H. 31 ) via Athmalgola , Barh , Pandarak, More for the Year 2020-21 | 1 | Work | - | - | PART1BOQ.pdf | ₹10,85,64,726 | ₹10,85,64,726 | Yes |