Bid Publish Date
02-Oct-2026, 3:10 pm
Bid End Date
16-Nov-2026, 9:00 am
EMD
₹1,40,000
Progress
Indian Institute Of Technology (Iit), Department Of Higher Education invites bids for a Solar Light system focused on illumination, energy conservation, and green energy promotion. The tender sets an EMD of ₹140,000 and contemplates a flexible quantity with a +/- 25% option. The payment schedule is a three-stage process: 50% on contract execution, 40% on final installation, commissioning, training, and handover, and 10% after a 5-year post-commissioning period subject to SLA compliance. The BOQ shows 0 total items, indicating a framework or incomplete itemization but the procurement scope remains clear. A key differentiator is the option clause enabling quantity adjustments during contract execution and the extended period, with delivery timelines tied to the last date of the original order. The organization’s objective centers on scalable solar lighting deployment aligned with energy efficiency goals.
Solar Light system for illumination and energy conservation
EMD amount: ₹140,000
Delivery period: based on original delivery date; minimum 30 days extension when quantity increases
Payment terms: 50% on contract execution, 40% on final installation and handover, 10% after 5-year period
Quantity variation: up to ±25% during contract and currency of contract
EMD₹140000 required; mode unspecified
50% upfront payment on contract execution
25% quantity variation rights during and after contract
50% upon contract execution with invoicing and verification; 40% on final installation and handover with IIT Kharagpur approval; 10% after 5-year post-commissioning, subject to SLA and penalties
Delivery period linked to last date of original order; extended time computed as (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days; option to extend within original delivery period
LD/penalties may apply based on SLA compliance during post-commissioning period; details not specified in excerpt
Demonstrated capability to supply and install solar lighting systems or similar energy-efficient lighting
Financial stability evidenced by financial statements
GST registration and PAN card,
Quantity
100
Bid Type
Two Packet Bid
Bid Validity
120 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
3 Days
EMD Required
Yes
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
Yes
Bid Splitting Applied
No
Min. Avg. Annual Turnover
35
OEM Avg. Turnover
100
Past Performance
40 %
Experience Required
3 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Solar Light for the purpose of Illumination, Energy Conservation and Green Energy Promotion Policy
Advisory Bank
State Bank of India
ePBG Percentage
3%
ePBG Duration (Months)
62
Max Delivery Days
30
Delivery Locations
1
Delivery Cities
Medinipur West
Delivery Pincodes
721302
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Suman Chakraborty | 721302,MECHANICAL ENGINEERING, INDIAN INSTITUTE OF TECHNOLOGY KHARAGPUR | Medinipur West | West Bengal | 721302 | 100 | 30 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
TECHNICAL
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
16-Nov-2026, 3:30 am
Opening Date
17-Nov-2026, 3:30 am
Discover companies most likely to bid on this tender
GST registration certificate
PAN card
Experience certificates demonstrating relevant solar lighting installations
Financial statements / turnover evidence
EMD submission receipt
Technical bid documents demonstrating capability for installation and handover
OEM authorization or vendor/dealer authorization for solar components (if required)
Bidders should submit the mandatory documents listed in the terms, including GST, PAN, experience certificates, and financial statements, along with the EMD of ₹140,000. Ensure compliance with the three-stage payment terms and the 25% quantity variation option; verify installation and handover requirements with IIT Kharagpur.
Required documents include GST registration, PAN, experience certificates for solar installations, financial statements, EMD payment receipt, technical bid documents proving installation capability, and OEM authorizations if applicable. Ensure submission aligns with IIT Kharagpur ATC and handover terms.
Payment is in three phases: 50% on contract execution, 40% on final installation, commissioning, training, and handover, and 10% after 5 years post-commissioning, contingent on SLA compliance and deduction of penalties where applicable.
The EMD is ₹140,000. Submit via the approved method and ensure it is valid through the bid evaluation period; failure to provide EMD may disqualify the bidder from the procurement process.
The purchaser may increase or decrease the quantity by up to 25% of bid quantity at contract placement and during the contract currency at contracted rates, with delivery time adjustments as specified in the option clause.
No explicit technical standards are listed in the tender excerpt; bidders should prepare to demonstrate technical capability through installation experience, OEM authorizations, and compliance with SLA-based performance during the post-commissioning period.
The final 10% payment is released after the end of the 5-year post-commissioning period, subject to SLA compliance and absence of penalties; ensure documentation of commissioning and handover milestones to claim this payment.
Delivery time for increased quantity is calculated as (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum of 30 days; extensions may be allowed within the original delivery period at the purchaser's discretion.