Bid Publish Date
12-Oct-2026, 11:25 am
Bid End Date
22-Oct-2026, 12:00 pm
Location
Progress
Hindustan Petroleum Corporation Ltd invites bids for the procurement of a Programmable Logic Controller (PLC) – Q3 category. The tender details include an option to increase or decrease the bid quantity by up to 25%, with extended delivery time calculations. No BOQ items are listed and the Estimated Value and EMD amounts are not disclosed. The process includes MSE purchase preference provisions and compliance with the Local Content (PP-LC) policy. Bidders should be manufacturers to qualify for MSE benefits, and documentation must support eligibility under local-content rules. The tender emphasizes supplier capability to adapt volume within the defined percentage, and adherence to MoP&NG local-content amendments where applicable. This opportunity requires precise alignment with the outlined option clause and local-content certification as part of bid evaluation.
Option to increase/decrease quantity up to 25% at order and during contract
MSE purchase preference with manufacturer requirement and price matching within policy
PP-LC policy adherence; local-content certification and verification required
Not specified in the data; standard HPCL tender terms to apply once defined
Delivery period to commence from the last date of the original delivery order; extended time formula applies during option exercise
Not specified in the provided terms; penalties to be disclosed in the formal bid documents
Bidder must be a manufacturer to claim MSE purchase preference
OEM authorization or authorized dealership for PLC products
Compliance with Local Content policy (PP-LC) and documentary evidence
Quantity
1
Bid Type
Two Packet Bid
Bid Validity
120 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
3 Days
EMD Required
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Programmable Logic Controller (PLC) (Q3)
Advisory Bank
ICICI
ePBG Percentage
5%
ePBG Duration (Months)
24
Payment Timelines
Payments shall be made to the Seller within 15 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
1825
Delivery Locations
1
Delivery Cities
Visakhapatanam
Delivery Pincodes
530014
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Malla Tanmaya Lakshman | 530014,Visakh Raipur Pipeline Project, Visakh Dispatch Station, VR ATP AREA , NAVAL BASE POST, VISAKHAPATNAM - 530014 | Visakhapatanam | Andhra Pradesh | 530014 | 1 | 1825 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
22-Oct-2026, 6:30 am
Opening Date
23-Oct-2026, 6:30 am
Discover companies most likely to bid on this tender
GST registration certificate
PAN card
Experience certificates (relevant PLC supply/installation work)
Financial statements (past 3 years)
EMD/Security deposit documents (as per vendor terms)
Technical bid documents (compliance with PLC specifications)
OEM authorization or dealership certificates (if applicable)
Documentation supporting MSE status and local content certification
Key insights about ANDHRA PRADESH tender market
Bid for the PLC tender in India by confirming manufacturing status, uploading MSE documentary evidence, and ensuring compliance with PP-LC local-content policy. If L-1, an MSE seller may match price within policy margins for 100% contract value share.
Submit GST registration, PAN, three-year financials, PLC experience certificates, OEM authorizations, and technical bid documents. Include MSE status proof and local-content certification to leverage PP-LC preferences where applicable.
The purchaser may alter bid quantity by up to 25% at contract award and during the currency, with time extensions calculated as (increased quantity/original quantity) × original delivery period, minimum 30 days.
Bidders must adhere to PP-LC policy; bidders with ≤20% local content are 'Non Local Supplier' and must provide verifiable local-content certifications as part of the bid evaluation.
Delivery period commences from the last date of the original delivery order; extended durations follow the option clause formula, ensuring minimum 30 days when calculating additional time.
Penalty details are not specified in the available data; formal bid documents typically outline LD or penalties, so bidders should expect standard HPCL terms once issued.
Provide OEM authorization certificates or agency letters as part of the technical bid to demonstrate legitimate distribution, installation capability, and compliance with PLC product lines.
Scope: supply and related documentation for Programmable Logic Controllers under Q3 category; specific quantities and installations are defined by contract award and updated via the option clause.