Bid Publish Date
07-Nov-2026, 11:54 am
Bid End Date
17-Nov-2026, 12:00 pm
Location
Progress
Organization: Rourkela Steel Plant (Sail) in Odisha. Procurement: Spare for mixing and balling drum DC motor drive controller (400KW). Delivery timeline: within 12 weeks from order placement, with packaging to prevent transit damage; anti-static bags for electronic cards. Eligibility: OEM/OES or authorized dealer/representative; bid-specific authorization must accompany submission. Inspection will be conducted jointly by MM (Inspection) and Indenting Department at RSP stores. This procurement includes delivery of complete documentation (TC/GC) at delivery and a 12-month guarantee from commissioning or 18 months from supply, whichever date is earlier. Unique aspects include on-site commissioning support for software upgrades at no cost and visible company emblem/part number on the material body for traceability. The scope is limited to supply of goods with no service components beyond commissioning assistance.
Spare for mixing and balling drum DC motor drive controller, 400KW
Delivery timeline: 12 weeks from order placement
Warranty: 12 months from commissioning; 18 months from supply date
Packaging: anti-static bags for electronics cards
Identification: supplier emblem and part number visible on body
Inspection: joint MM and indenting department inspection at RSP stores
Documentation: TC and GC provided at delivery; operating manual included
OEM/OES or authorized dealer eligibility with authorization
12-week delivery from order; price fixed till delivery
12-month warranty from commissioning; 18 months from supply
Emblem/part number must be fixed on material; anti-static packaging
Joint inspection by MM and indenting dept; TC/GC at delivery
Not explicitly defined; standard procurement practice implies milestone/credit terms post-delivery with inspection acceptance
Delivery within 12 weeks from order placement; packaging must ensure safe transit
Not specified in terms; implied LD could apply for delays as per standard MM policy
Must be OEM/OES or authorized dealer with valid bid-specific authorization
Bid shall include dealership certificate if the bidder is an authorized dealer
No unsolicited bids from non-OEM vendors
Quantity
1
Bid Type
Two Packet Bid
Bid Validity
60 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
CONTROLLER, ARMATURE, MM: 598P006069000A1UK
Payment Timelines
Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
90
Delivery Locations
1
Delivery Cities
Sundargarh
Delivery Pincodes
769011
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| AJIT KUMAR SAHOO | 769011,PS-II STORE, SAIL - ROURKELA STEEL PLANT | Sundargarh | Odisha | 769011 | 1 | 90 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST registration certificate
PAN card
Bid-specific authorization letter from OEM/OES or dealership certificate
Experience certificates (if any) related to similar drive controllers
Financial statements (as applicable)
Technical compliance certificates for the drive controller
TC and GC to be submitted at delivery
On-delivery manual/instruction document
Bidders must be OEM/OES or authorized dealers with a valid bid-specific authorization letter or dealership certificate. Prepare TC/GC, MC/operating manual, and ensure emblem/part number is fixed on the body. Delivery is within 12 weeks and price remains firm till delivery; inspection is joint at RSP stores.
Submit GST registration, PAN, bid-specific OEM authorization or dealership certificate, relevant experience certificates, financial statements, technical compliance documents, and TC/GC at delivery. Include operating manual and emblem/part number visibly fixed on the item body.
Delivery must occur within 12 weeks from order placement. Items should be properly packaged, with electronics cards in anti-static bags. Joint inspection by MM and indenting department occurs post-delivery at RSP stores, before final acceptance.
The item carries a 12 months guarantee from commissioning at site and up to 18 months from the date of supply, whichever is earlier, ensuring post-commissioning support for software/version upgrades if needed.
Submit a valid bid-specific authorization from the OEM/OES or a dealership certificate issued by the OEM/OES. Unauthorized bidders will be deemed ineligible; only OEM/OES or authorized representatives are eligible.
Inspection is joint between MM (Inspection) and the indenting department. It occurs after delivery at RSP modernisation stores and requires the TC and GC to be presented for verification and acceptance.
Electronics cards must be supplied in anti-static bags. Material bodies should carry the supplier emblem and part number visibly. Packaging must protect against transit damage and multiple handlings per the tender terms.