Bid Publish Date
05-Oct-2026, 3:38 pm
Bid End Date
15-Oct-2026, 4:00 pm
Location
Progress
The procurement is issued by Mahudha Nagar Palika for the supply, installation, testing and commissioning of Crematoria Bed (V2) – Q3. The contract covers SITC of goods with additional RCC installation work. An ISO 9001 certification requirement applies to the bidder or OEM. The contract includes an option to increase or decrease quantity by up to 25% during or after award, with delivery timelines anchored to the original order. The absence of BOQ items is noted, signaling a compact but high-critical installation scope suitable for local government crematorium modernization.
Product/Service: Crematoria Bed (V2) with SITC
Standards: ISO 9001 certified bidder or OEM
Quantity: up to +/-25% variation at bid/contract time
Delivery/Installation: RCC work included where required
Payments/Delivery: Terms aligned to original delivery period with extension rules
Option clause permits 25% quantity variation during contract
ISO 9001 certification mandatory for bidder or OEM
SITC scope including RCC installation; full cost in bid
Not specified in available data; verify in ATC/Corrigendum and final contract
Delivery period starts from last date of original delivery order; extended time may apply per option clause with minimum 30 days
Not specified; confirm LD or performance bond in final ATC
Must hold ISO 9001 certification (bidder or OEM)
Experience with SITC of crematorium equipment preferable
Compliance with all ATC and Corrigendum submission requirements
Quantity
3
Bid Type
Two Packet Bid
Bid Validity
120 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Min. Avg. Annual Turnover
3
OEM Avg. Turnover
3
Past Performance
10 %
Experience Required
1 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Crematoria Bed (V2) (Q3)
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
15
Delivery Locations
1
Delivery Cities
Kheda
Delivery Pincodes
387335
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Patel Bhoomikaben Dahyalal | 387335,NEAR POST OFFICE, MAHUDHA. DIST. KHEDA | Kheda | Gujarat | 387335 | 3 | 15 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST registration certificate
PAN card
ISO 9001 certification proof (bidder or OEM)
Experience certificates related to crematorium equipment installation
Financial statements or turnover proof (if requested in ATC)
Technical bid documents and product specifications
OEM authorizations or vendor registrations
Any certificates referenced in ATC or Corrigendum
Bidders must ensure ISO 9001 certification for themselves or the OEM, submit all required documents listed in ATC (GST, PAN, experience certificates, technical bids, OEM authorizations), and include SITC scope with RCC installation if applicable. The bid should reflect the 25% quantity variation clause and comply with delivery terms from original order date.
Submit GST certificate, PAN card, ISO 9001 proof, experience certificates for crematorium projects, financial statements if requested, technical bid with product specs, OEM authorizations, and any certificates mentioned in ATC/Corrigendum to avoid rejection.
Technical scope includes Supply, Installation, Testing and Commissioning of Crematoria Bed (V2) with RCC installation where required; ensure ISO 9001 certified supplier and include complete SITC pricing; delivery terms align to the original order date with possible 25% quantity variation.
Delivery period begins from the last date of the original delivery order. Option clause allows up to 25% quantity variation; extra time is calculated by (additional/original) × original period, minimum 30 days, with possible extension up to the original delivery period.
Bidder or OEM must hold ISO 9001 certification. Ensure all relevant product certifications are uploaded; non-submission may lead to rejection as per ATC and Corrigendum.
Scope includes Supply, Installation, Testing and Commissioning of Crematoria Bed (V2) with RCC installation included as per site needs; price must cover all components and services across SITC, installation, and commissioning.
RCC work is included as part of the installation scope where specified; bidders must plan for structural concrete works if required and align timelines with SITC activities to ensure integrated commissioning.