Salem Steel Plant of Steel Authority of India Limited (SAIL) invites bids for BUSH ASSEMBLY FOR COIL CAR ROLL and BUSH ASSEMBLY FOR SNUBBER ROLL. Scope includes procurement of bush assemblies, with delivery terms stated as 12 weeks from order placement and F.O.R Salem Steel Plant through the GeM portal. Estimated value not disclosed; EMD details specify ₹1,000 per item and ₹5,000 if bidding on all items. The tender permits quantity variation up to 25% during contract execution. MSE bidders may benefit from Udyam registration/NSIC. Inspection at plant after receipt is noted, with payment terms of 100% within 30 days of receipt and acceptance. Clear emphasis on adherence to supplied drawings and specifications, with price offers to be on a fixed basis. This tender emphasizes local supply conditions and GST considerations managed by bidders. Unique clause: option to scale quantity and corresponding delivery time adjustment using a defined formula, ensuring minimum 30 days extension where applicable. Unique differentiator includes reliance on supplier’s capability to meet FOB/CIF-like cost inclusions via GeM and compliance with MSME preferences. This procurement is positioned as a targeted, location-specific opportunity in Salem, Tamil Nadu for capital equipment components.
Bush assemblies for coil car roll
Bush assemblies for snubber roll
Delivery: 12 weeks from order placement
Location: Salem Steel Plant, Salem, Tamil Nadu
EMD: ₹1,000 per item; ₹5,000 for all items
Payment: 100% within 30 days after receipt & acceptance
Inspection: at Salem Steel Plant after receipt
Price: FOB/F.O.R Salem Steel Plant basis on GeM with P&F, freight, and insurance
Quantity flexibility: +/- 25% during contract
EMD required: ₹1,000 per item, ₹5,000 for all items; MSME exemption possible with Udyam/NSIC
Delivery timeline: 12 weeks from order; quantity can vary ±25% with adjusted delivery period
Payment terms: 100% within 30 days after receipt and acceptance at Salem Steel Plant
100% payment within 30 days after receipt and acceptance at Salem Steel Plant Stores; GST handling as per actuals or applicable rate, whichever lower
Delivery to commence from order; 12 weeks specified; option to adjust delivery time if quantity changes up to 25%
Not specified in provided terms; ensure compliance with delivery timelines and acceptance testing per drawings
Must meet MSME preference eligibility with valid Udyam certificate and NIC code
Experience in supplying bush assemblies or related rolling mill components
Possess GST registration and financial capability to undertake fixed-price contract
Quantity
24
Category
BUSH ASSMEBLY FOR COIL CAR ROLL
Bid Type
Two Packet Bid
Bid Validity
60 (Days)
Bid Type
Service
Evaluation
Item wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
BUSH ASSMEBLY FOR COIL CAR ROLL , BUSH ASSEMBLY FOR SNUBBER ROLL
Payment Timelines
Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
84
Delivery Locations
1
Delivery Cities
Salem
Delivery Pincodes
636013
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Jagadish A | 636013,Salem Steel Plant, A Unit of Steel Authority of India Limited | Salem | Tamil Nadu | 636013 | 12 | 84 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates for similar bush assembly supply
Financial statements/balance sheet for last 2-3 years
EMD submission proof (or Bid Securing Declaration)
Technical bid documents showing compliance with drawings
OEM authorization (if applicable)
Udyam registration (for MSME preference) with NIC code (if claiming exemption)
Key insights about TAMIL NADU tender market
Bidders must register on GeM, submit GST and PAN, provide EMD of ₹1,000 per item (₹5,000 if bidding all items), attach signed technical specifications, and confirm 12-week delivery from order. MSMEs may use Udyam NSIC exemptions. Ensure drawings are attached and price is F.O.R Salem Steel Plant.
Submit GST certificate, PAN card, experience certificates for similar assemblies, financial statements, EMD proof or Bid Securing Declaration, technical bid with signed specifications, OEM authorization if applicable, and Udyam certificate or NSIC (for MSME preference). Inspection conducted at plant after receipt.
Delivery is 12 weeks from order placement. Quantity variation up to ±25% is allowed with the extended delivery period calculated as (additional quantity/original quantity) × original delivery period, minimum 30 days. Delivery is F.O.R Salem Steel Plant with inspection at the plant.
The contract requires 100% payment within 30 days after receipt and acceptance at Salem Steel Plant Stores. GST will be reimbursed as actuals or applicable rate, whichever is lower, subject to quoted GST percentage.
Yes, MSE preferences are available subject to submission and verification of valid Udyam certificate with the NIC code for the quoted bush assembly items. Ensure eligibility before submitting technical bid and price offers.
The EMD is ₹1,000 per item; ₹5,000 if bidding on all items. Bidders may submit a Bid Securing Declaration in lieu of EMD. MSMEs may be exempted from EMD on proof of Udyam NSIC registration.
Inspection occurs at Salem Steel Plant after receipt of the consignment. Acceptance is required prior to final payment; items must comply with drawings and signed technical specifications attached with the bid.
Prices must be quoted on a fixed, firm basis through GeM for F.O.R Salem Steel Plant, including P&F, freight, and insurance charges. Prices remain firm until supplies are completed, with no price bid format allowed alongside technical offers.