Bid Publish Date
16-Aug-2026, 12:16 pm
Bid End Date
07-Sep-2026, 1:00 pm
Location
Progress
Nhpc Limited seeks SITC for Synchronization Check Relay/Module in Kathua, Jammu & Kashmir. The procurement involves installation, testing & commissioning and associated charges. The scope is billed under a single contract with an option to adjust quantity by up to 25%, at contracted rates, across the delivery window. Eligible bidders must be manufacturers or authorized dealers with ISO certification and proven SITC experience in power plants or 132 kV substations. The tender emphasizes prior performance data and a 1-year satisfactory operation post-commissioning as minimum proof of capability.
Synchronization Check relay/module
SITC experience in power plants or 132 kV substations
Performance reports with 1-year post-commissioning data
Delivery period tied to last date of original delivery order with 30-day minimum extension
Quantity adjustment up to 25% during contract
EMD: Bid security requirements not specified in data; bidders must verify statutory demand.
Delivery: Quantity may vary by up to 25% at contracted rates; delivery starts after original order date.
Eligibility: Manufacturer or authorized dealer with ISO manufacturing certification; two similar SITC projects in seven years required.
Manufacturer of synchronization check equipment OR authorized dealer/channel partner for that manufacturer
ISO certification for manufacturing the specified equipment
Two similar SITC projects in last seven years with performance reports
No cross-quoting for multiple manufacturers via single bidder
Quantity
7
Category
SYNCHRONIZATION CHECK RELAY
Bid Type
Two Packet Bid
Bid Validity
120 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
3 Days
EMD Required
Yes
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
SYNCHRONIZATION CHECK RELAY , Installation, Testing & commissioning Charges
Advisory Bank
State Bank of India
ePBG Percentage
5%
ePBG Duration (Months)
19
Payment Timelines
Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
90
Delivery Locations
1
Delivery Cities
Kathua
Delivery Pincodes
184201
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Ashok Kumar | 184201,Sewa II Power Station, NHPC Limited, Mashka, Tehsil Basohli, Distt. Kathua, Jammu and Kashmir (Post office Khairi- 176325 for postal address), KATHUA, 184201 | Kathua | Jammu And Kashmir | 184201 | 4 | 90 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST certificate
PAN card
ISO manufacturing certification
Authorized dealer certificate (if quoting via dealer)
Experience certificates for two similar SITC projects in last seven years
Client performance reports showing 1 year satisfactory operation
Factory visit/production capability documents (if requested)
Any OEM authorization letter (valid for duration of tender)
Key insights about JAMMU AND KASHMIR tender market
Bidders must be manufacturers or authorized dealers with ISO certification. Prepare two SITC project proofs older than seven years, client performance reports for 1 year post-commissioning, OEM authorization if quoting via dealer, and meet the 25% quantity option terms. Ensure IS compliance and submission of required documents.
Submit GST, PAN, ISO certification for manufacturing, dealer authorization if applicable, two SITC project certificates, client performance reports, and OEM authorization letters. Include post-commissioning performance proof and any service/support commitments per buyer terms.
Provide evidence of at least two SITC installations of Synchronization Check modules in plants or 132 kV switchyards within seven years, each achieving satisfactory operation for at least one year post-commissioning, with client references.
The purchaser may increase or decrease quantity up to 25% of bid/contracted quantity. Delivery period starts after the last date of the original order; if extended, time scales via (additional/original quantity) × original period, minimum 30 days.
Manufacturing ISO certification is mandatory; OEM authorization if bidding through a dealer. Ensure no cross-quota bids for multiple manufacturers; maintain performance documentation as proof of capability.
Be the original equipment manufacturer or an authorized dealer with valid certificate; provide ISO certification and ensure previous two SITC projects meet the capacity/132 kV criteria, with one-year performance evidence.
Provide client performance reports demonstrating satisfactory operation for at least one year after commissioning, including maintenance records, uptime statistics, and service response metrics from each referenced project.
Delivery time adjusts with the formula: (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum extension of 30 days; original delivery baseline remains the reference unless extended.