Bid Publish Date
15-Sep-2026, 10:55 am
Bid End Date
25-Sep-2026, 11:00 am
Location
Progress
The procurement opportunity is issued by the Rourkela Steel Plant, a unit of the Steel Authority of India Limited, for the supply of goods under a proprietary basis from SKF Engineering and Lubrication India Pvt. Ltd. The contract allows an option to order up to 25% more quantity at contracted rates and requires delivery within 20 weeks from PO placement. The scope is strictly supply of goods, with inspection at RSP stores and fitment/guarantee documentation required. The engagement targets OEM/OES or authorized dealers with a clear authorization path for bids.
Product category: proprietary SKF lubrication equipment supply
Delivery timeline: 20 weeks from PO placement
Inspection: MM(Inspection), RSP STORES against fitment and guarantee certificates
Warranty: 12 months from commissioning or 18 months from supply (whichever earlier)
Price: Firm till delivery; 25% quantity variation allowed at contract time and during currency
Delivery terms: full quantities in one or more consignments as required by PO
Packaging: materials packed to safeguard during transit
EMD/guarantee: Submit as per terms; ensure GST invoice in consignee name with GSTIN
Delivery: 20 weeks from PO; quantity variation up to 25%
Warranty: 12 months from commissioning or 18 months from supply
GST payable as actual; invoice in consignee name with GSTIN; GST portal payment proof required
Delivery within 20 weeks of PO; option quantities may extend delivery as per clause with minimum 30 days
Not specified in data provided; standard contract penalties may apply for delayed delivery
Proprietary basis purchasing from OEM SKF Engineering and Lubrication India Pvt. Ltd.
Bids from OEM/OES or their authorized dealer/channel partner with bid-specific authorization
Compliance with exact materials, dimensions and tolerances per SKF specifications
Quantity
25
Category
20211401000401
Bid Type
Two Packet Bid
Bid Validity
60 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
20211401000401 , 20211401000394 , 20211401000393 , 20211401000391 , 20211401000399 , 20211401000396 , 20211401000397 , 20211401000398
Payment Timelines
Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
140
Delivery Locations
1
Delivery Cities
Sundargarh
Delivery Pincodes
769011
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| AJIT KUMAR SAHOO | 769011,PS-II STORE, SAIL - ROURKELA STEEL PLANT | Sundargarh | Odisha | 769011 | 2 | 140 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
20211401000401
Refer Attachment for Specification of 20211401000401
20211401000394
Refer Attachment for Specification of 20211401000394
20211401000393
Refer Attachment for Specification of 20211401000393
20211401000391
Refer Attachment for Specification of 20211401000391
20211401000399
Refer Attachment for Specification of 20211401000399
20211401000396
Refer Attachment for Specification of 20211401000396
20211401000397
Refer Attachment for Specification of 20211401000397
20211401000398
Refer Attachment for Specification of 20211401000398
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | 20211401000401 | Refer Attachment for Specification of 20211401000401 | 2 | ea | ajitkumar.sahoo | 140 | |
| 2 | 20211401000394 | Refer Attachment for Specification of 20211401000394 | 4 | ea | ajitkumar.sahoo | 140 | |
| 3 | 20211401000393 | Refer Attachment for Specification of 20211401000393 | 4 | ea | ajitkumar.sahoo | 140 | |
| 4 | 20211401000391 | Refer Attachment for Specification of 20211401000391 | 4 | ea | ajitkumar.sahoo | 140 | |
| 5 | 20211401000399 | Refer Attachment for Specification of 20211401000399 | 4 | ea | ajitkumar.sahoo | 140 | |
| 6 | 20211401000396 | Refer Attachment for Specification of 20211401000396 | 4 | ea | ajitkumar.sahoo | 140 | |
| 7 | 20211401000397 | Refer Attachment for Specification of 20211401000397 | 2 | ea | ajitkumar.sahoo | 140 | |
| 8 | 20211401000398 | Refer Attachment for Specification of 20211401000398 | 1 | ea | ajitkumar.sahoo | 140 |
Discover companies most likely to bid on this tender
GST registration certificate
PAN card of bidder
Experience certificates demonstrating OEM/authorized dealer status
Financial statements (latest audited/management accounts)
EMD/Security deposit documents (if applicable per terms)
Technical bid documents detailing fitment certificate and guarantee certificate
OEM authorization or bid-specific authorization from SKF
Product specifications compliance certificates and packaging details
Bidders must be OEM/OES or authorized SKF dealers with bid-specific authorization. Submit GST, PAN, financials, experience certificates, and OEM authorization. Ensure compliance with fitment and guarantee certificates and provide 20-week delivery from PO.
Required documents include GST registration, PAN, experience certificates, latest financial statements, OEM authorization, bid authorization if partnering, and technical certificates showing conformity to SKF specifications and packaging details.
Delivery must be completed within 20 weeks from PO placement, with options to increase quantity up to 25% at contracted rates; extended delivery time calculated per clause, minimum 30 days.
Warranty must be 12 months from commissioning or 18 months from supply, whichever is earlier; ensure fitment and guarantee certificates accompany the supply.
Invoices must be raised in the consignee name with the GSTIN; GST payable as actual or applicable rate; GST portal payment screenshot must be uploaded on GeM.
Only OEM/OES or their authorized dealers/channel partners with bid-specific authorization are eligible; material dimensions and tolerances must align with SKF specifications.
The purchaser may increase or decrease quantity up to 25% at contracted rates; delivery time adjusts according to the extended delivery period formula with a minimum 30 days.
Yes, items must be packed to protect during transit, and inspection by MM(Inspection), RSP at RSP stores requires fitment and guarantee certificates and specification compliance.