TenderDekho Logo
GEM

Government Tender Published for Simulation panel for Differential protection of Transformer1,Simulation panel for Differential prot in THANE, MAHARASHTRA

Bid Publish Date

04-Jul-2025, 6:43 pm

Bid End Date

22-Jul-2025, 7:00 pm

EMD

₹1,10,000

Value

₹1,10,73,750

Progress

Issue04-Jul-2025, 6:43 pm
AwardPending
Explore all 4 tabs to view complete tender details

Quantity

141

Category

Single Phase Transformer 1 KVA 1

Bid Type

Two Packet Bid

Categories 42

Directorate Of Technical Education invites bids for Simulation panel for Differential protection of Transformer1, Simulation panel for Differential protection of Transformer2, Simulation panel for in THANE, MAHARASHTRA. Quantity: 141. Submission Deadline: 22-07-2025 19: 00: 00. Submit your proposal before the deadline.

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

Yes

Item Category

Simulation panel for Differential protection of Transformer1 , Simulation panel for Differential protection of Transformer2 , Simulation panel for

Authority Records

HIGHER AND TECHNICAL EDUCATION DEPARTMENTDIRECTORATE OF TECHNICAL EDUCATION

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 5

GeM-Bidding-8023533.pdf

Main Document

Other Documents

OTHER

BOQ Document

BOQ

BOQ Document

BOQ

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Past Similar Tenders (Historical Results)

5 found

SUPPLY, FIXING & PROGRAMMING OF NUMERICAL 3-POLE DIFFERENTIAL TRANSFORMER PROTECTION RELAY

Yantra India Limited

Posted: 13 November 2024
Closed: 4 December 2024
GEM

Transformer Overall Differential Protection Relay-MiCOM P543,MiCOM P743-Peripheral Unit,PU relay Ty

Damodar Valley Corporation

BOKARO, JHARKHAND

Posted: 7 February 2025
Closed: 5 March 2025
GEM

Invitation to Bid - 05/SE(TECH)/JZ/2025-26 in LUCKNOW, UTTAR PRADESH

Madhyanchal Vidyut Vitran Nigam Ltd

LUCKNOW, UTTAR PRADESH

Posted: 2 February 2026
Closed: 20 February 2026
EPROCURE

Invitation to Bid - Supply and Retrofitting of New Differential Protection Relay of 40MVA Transformer-III Panels at 132 KV Sub-Station Naugarh Under Electricity Transmission Division-II, Basti H.Q. at Siddharthnagar in BASTI, UTTAR PRADESH

UP Power Transmission Corp.Ltd (Operation)

BASTI, UTTAR PRADESH

Posted: 16 February 2026
Closed: 6 March 2026
EPROCURE

Government Tender Published for Supply of various De-Centralised materials for protection of Transformer under ETD, Fatehpur in FATEHPUR, UTTAR PRADESH

Purvanchal Vidyut Vitran Nigam Limited Varanasi

FATEHPUR, UTTAR PRADESH

Posted: 30 April 2026
Closed: 15 May 2026
EPROCURE

Bill of Quantities (BOQ) 73 Items Sign in for GEM prices

#1

Simulation panel for Differential protection of Transformer1

Simulation panel for Differential protection of Transformer1

1 pieces Delivery: 45 days
#2

Simulation panel for Differential protection of Transformer2

Simulation panel for Differential protection of Transformer2

1 pieces Delivery: 45 days
#3

Simulation panel for Differential protection of Transformer3

Simulation panel for Differential protection of Transformer3

1 pieces Delivery: 45 days
#4

Simulation panel for Differential protection of Transformer4

Simulation panel for Differential protection of Transformer4

1 pieces Delivery: 45 days
#5

Simulation panel for Differential protection of Transformer5

Simulation panel for Differential protection of Transformer5

1 pieces Delivery: 45 days
#6

Simulation panel for Differential protection of Transformer6

Simulation panel for Differential protection of Transformer6

1 pieces Delivery: 45 days
#7

Simulation panel for Differential protection of Transformer7

Simulation panel for Differential protection of Transformer7

1 pieces Delivery: 45 days
#8

Simulation panel for Differential protection of Transformer8

Simulation panel for Differential protection of Transformer8

1 pieces Delivery: 45 days
#9

Simulation panel for Differential protection of Transformer9

Simulation panel for Differential protection of Transformer9

1 pieces Delivery: 45 days
#10

Single Phase Transformer 1 KVA 1

Single Phase Transformer 1 KVA 1

6 pieces Delivery: 45 days
#11

Single Phase Transformer 1 KVA 2

Single Phase Transformer 1 KVA 2

4 pieces Delivery: 45 days
#12

Single Phase Transformer 1 KVA 3

Single Phase Transformer 1 KVA 3

2 pieces Delivery: 45 days
#13

Single Phase Transformer 1 KVA 4

Single Phase Transformer 1 KVA 4

4 pieces Delivery: 45 days
#14

Single phase Universal motor 1

Single phase Universal motor 1

1 pieces Delivery: 45 days
#15

Single phase Universal motor 2

Single phase Universal motor 2

2 pieces Delivery: 45 days
#16

Switchgear Testing Kit 1

Switchgear Testing Kit 1

1 pieces Delivery: 45 days
#17

Switchgear Testing Kit 2

Switchgear Testing Kit 2

1 pieces Delivery: 45 days
#18

Switchgear Testing Kit 3

Switchgear Testing Kit 3

1 pieces Delivery: 45 days
#19

Three Phase Induction Motor Protection Simulation Unit 1

Three Phase Induction Motor Protection Simulation Unit 1

1 pieces Delivery: 45 days
#20

Three Phase Induction Motor Protection Simulation Unit 2

Three Phase Induction Motor Protection Simulation Unit 2

1 pieces Delivery: 45 days
#21

Three Phase Induction Motor Protection Simulation Unit 3

Three Phase Induction Motor Protection Simulation Unit 3

1 pieces Delivery: 45 days
#22

Three Phase Induction Motor Protection Simulation Unit 4

Three Phase Induction Motor Protection Simulation Unit 4

2 pieces Delivery: 45 days
#23

Three phase Power Factor Meter 1

Three phase Power Factor Meter 1

1 pieces Delivery: 45 days
#24

Three phase Power Factor Meter 2

Three phase Power Factor Meter 2

2 pieces Delivery: 45 days
#25

Three phase Power Factor Meter 3

Three phase Power Factor Meter 3

2 pieces Delivery: 45 days
#26

Three phase Power Factor Meter 4

Three phase Power Factor Meter 4

1 pieces Delivery: 45 days
#27

Three phase Power Factor Meter 5

Three phase Power Factor Meter 5

1 pieces Delivery: 45 days
#28

Three phase Synchronous Motor coupled with DC shunt generator setup 1

Three phase Synchronous Motor coupled with DC shunt generator setup 1

1 pieces Delivery: 45 days
#29

Three phase Synchronous Motor coupled with DC shunt generator setup 2

Three phase Synchronous Motor coupled with DC shunt generator setup 2

1 pieces Delivery: 45 days
#30

Three phase Synchronous Motor coupled with DC shunt generator setup 3

Three phase Synchronous Motor coupled with DC shunt generator setup 3

1 pieces Delivery: 45 days
#31

Three phase Synchronous Motor coupled with DC shunt generator setup 4

Three phase Synchronous Motor coupled with DC shunt generator setup 4

1 pieces Delivery: 45 days
#32

Three phase Transformer 5kVA 1

Three phase Transformer 5kVA 1

4 pieces Delivery: 45 days
#33

Three phase Transformer 5kVA 2

Three phase Transformer 5kVA 2

1 pieces Delivery: 45 days
#34

Three phase Transformer 5kVA 3

Three phase Transformer 5kVA 3

1 pieces Delivery: 45 days
#35

Three phase Transformer 5kVA 4

Three phase Transformer 5kVA 4

2 pieces Delivery: 45 days
#36

Three phase Transformer 5kVA 5

Three phase Transformer 5kVA 5

2 pieces Delivery: 45 days
#37

Three phase Transformer 5kVA 6

Three phase Transformer 5kVA 6

2 pieces Delivery: 45 days
#38

THREE PHASE VERIABLE RESISTIVE LOAD 1

THREE PHASE VERIABLE RESISTIVE LOAD 1

2 pieces Delivery: 45 days
#39

THREE PHASE VERIABLE RESISTIVE LOAD 2

THREE PHASE VERIABLE RESISTIVE LOAD 2

1 pieces Delivery: 45 days
#40

THREE PHASE VERIABLE RESISTIVE LOAD 3

THREE PHASE VERIABLE RESISTIVE LOAD 3

2 pieces Delivery: 45 days
#41

Three point starter for DC motor 230 volts, 10 amps 1

Three point starter for DC motor 230 volts, 10 amps 1

3 pieces Delivery: 45 days
#42

Three point starter for DC motor 230 volts, 10 amps 2

Three point starter for DC motor 230 volts, 10 amps 2

1 pieces Delivery: 45 days
#43

Transformer Workbench 1

Transformer Workbench 1

1 pieces Delivery: 45 days
#44

Transformer Workbench 2

Transformer Workbench 2

1 pieces Delivery: 45 days
#45

Transformer Workbench 3

Transformer Workbench 3

1 pieces Delivery: 45 days
#46

Transmission line protection simulation kit 1

Transmission line protection simulation kit 1

1 pieces Delivery: 45 days
#47

Transmission line protection simulation kit 2

Transmission line protection simulation kit 2

1 pieces Delivery: 45 days
#48

Transmission line protection simulation kit 3

Transmission line protection simulation kit 3

1 pieces Delivery: 45 days
#49

Transmission line protection simulation kit 4

Transmission line protection simulation kit 4

1 pieces Delivery: 45 days
#50

Transmission line simulator 1

Transmission line simulator 1

1 pieces Delivery: 45 days
#51

Transmission line simulator 2

Transmission line simulator 2

1 pieces Delivery: 45 days
#52

Transmission line simulator 3

Transmission line simulator 3

1 pieces Delivery: 45 days
#53

Undrground cable fault locator 1

Undrground cable fault locator 1

1 pieces Delivery: 45 days
#54

Undrground cable fault locator 2

Undrground cable fault locator 2

1 pieces Delivery: 45 days
#55

Undrground cable fault locator 3

Undrground cable fault locator 3

1 pieces Delivery: 45 days
#56

Venturi flow measurement setup 1

Venturi flow measurement setup 1

1 pieces Delivery: 45 days
#57

Venturi flow measurement setup 2

Venturi flow measurement setup 2

1 pieces Delivery: 45 days
#58

Venturi flow measurement setup 3

Venturi flow measurement setup 3

1 pieces Delivery: 45 days
#59

Wattmeter 0.5 1A, 150 300V Low Power factor

Wattmeter 0.5 1A, 150 300V Low Power factor

6 pieces Delivery: 45 days
#60

Wattmeter 10 20 A ,150 300 600V Unity Power factor 1

Wattmeter 10 20 A ,150 300 600V Unity Power factor 1

4 pieces Delivery: 45 days
#61

Wattmeter 10 20 A ,150 300 600V Unity Power factor 2

Wattmeter 10 20 A ,150 300 600V Unity Power factor 2

4 pieces Delivery: 45 days
#62

Wattmeter 10 20 A ,150 300 600V Unity Power factor 3

Wattmeter 10 20 A ,150 300 600V Unity Power factor 3

2 pieces Delivery: 45 days
#63

Wattmeter 10 20 A ,150 300 600V Unity Power factor 4

Wattmeter 10 20 A ,150 300 600V Unity Power factor 4

3 pieces Delivery: 45 days
#64

Wattmeter 10 20 A ,150 300 600V Unity Power factor 5

Wattmeter 10 20 A ,150 300 600V Unity Power factor 5

2 pieces Delivery: 45 days
#65

Wattmeter 10 20 A ,150 300 600V Unity Power factor 6

Wattmeter 10 20 A ,150 300 600V Unity Power factor 6

2 pieces Delivery: 45 days
#66

Wattmeter 2.5 5A , 150 300V Unity Power factor 1

Wattmeter 2.5 5A , 150 300V Unity Power factor 1

7 pieces Delivery: 45 days
#67

Wattmeter 2.5 5A , 150 300V Unity Power factor 2

Wattmeter 2.5 5A , 150 300V Unity Power factor 2

3 pieces Delivery: 45 days
#68

Wattmeter 2.5 5A , 150 300V Unity Power factor 3

Wattmeter 2.5 5A , 150 300V Unity Power factor 3

4 pieces Delivery: 45 days
#69

Wattmeter 2.5 5A , 150 300V Unity Power factor 4

Wattmeter 2.5 5A , 150 300V Unity Power factor 4

2 pieces Delivery: 45 days
#70

Wattmeter 5 10 A ,150 300 600V Unity Power factor 1

Wattmeter 5 10 A ,150 300 600V Unity Power factor 1

2 pieces Delivery: 45 days
#71

Wattmeter 5 10 A ,150 300 600V Unity Power factor 2

Wattmeter 5 10 A ,150 300 600V Unity Power factor 2

8 pieces Delivery: 45 days
#72

Wattmeter 5 10 A ,150 300 600V Unity Power factor 3

Wattmeter 5 10 A ,150 300 600V Unity Power factor 3

5 pieces Delivery: 45 days
#73

Wattmeter 5 10 A ,150 300 600V Unity Power factor 4

Wattmeter 5 10 A ,150 300 600V Unity Power factor 4

3 pieces Delivery: 45 days

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Required Documents

1

Experience Criteria

2

Past Performance

3

Bidder Turnover

4

Certificate (Requested in

Similar Tenders

5 found

Transformer Differential Protection Relay

Delhi Metro Rail Corporation Limited

📍 NORTH EAST DELHI, DELHI

EMD: ₹1.0 L
⏰ Deadline: 2 weeks left
🛒 Type: Goods
View GEM
Urgent

33 kV Protection Panel for Transformer

Power Grid Corporation Of India Limited

📍 UDHAM SINGH NAGAR, UTTARAKHAND

EMD: ₹26,000
⏰ Deadline: 5 days left
🛒 Type: Goods
View GEM
Urgent

33 kV CONTROL & RELAY PANEL FOR SINGLE TRANSFORMER (WITHOUT DIFFRENTIAL PROTECTION),33 kV CONTROL &

Uttar Pradesh Power Corporation Limited (uppcl)

📍 AGRA, UTTAR PRADESH

EMD: ₹4.8 L
⏰ Deadline: 2 days left
🛒 Type: Goods
View GEM
Urgent

Design, Supply, erection, testing and commissioning of Transformer Protection Relay panel with Numerical Relays, in place of existing Alston make Transformer Protection relay panel pertaining to Stage-I, Dr. NTTPS

📍 ANDHRA PRADESH

⏰ Deadline: 2 days left
🛒 Type: Goods
View EPROCURE-ANDHRA_PRADESH
Urgent

Procurement Opportunity: Work of Protection Related Works of Distribution Transformers under Business Plan 2026-27 in the Area of EUDD-11 KV Line, South-Madhavpuram, Meerut. in MEERUT, UTTAR PRADESH

Paschimanchal Vidyut Vitran Nigam Ltd.

📍 MEERUT, UTTAR PRADESH

EMD: ₹1.4 L
Est: ₹1.4 Cr
⏰ Deadline: 3 days left
🛒 Type: Works
View EPROCURE