Bid Publish Date
03-Oct-2026, 10:40 am
Bid End Date
20-Oct-2026, 2:00 pm
Location
Progress
Organization: Rourkela Steel Plant (SAIL) seeks supply of gear coupling items (ZINA 5, PT. 845, ZIZS 3.5-250, PT. 845.99) via GeM. Estimated value and quantity are not disclosed; scope covers Only supply of Goods. The tender allows a 25% quantity variation during placement and within the contract period at contracted rates. Pre- or post-dispatch inspection options are defined, with inspection at AT RSP STORES for acceptance. Registration for potential bidders is via the vendor portal at www.sail tenders.co.in, and LTE-registered suppliers will be considered. This procurement emphasizes supplier readiness, GST handling, and ad hoc quantity adjustments within the stated limits.
EMD amount: Not disclosed; provide bid security as per GeM/SAIL norms
Delivery: 25% quantity variation allowed; delivery time extended proportionally
Inspection: Post-receipt inspection at RSP Stores; ATC may specify pre-dispatch
GST: Bidder to determine GST; reimbursement per actuals or lower rate
GST must be uploaded with invoice; payment terms aligned with GeM/Sail standard practices; GST payment confirmation required
Delivery starts after order; extended delivery time based on increased quantity as per clause; minimum 30 days
Not explicitly defined; adherence to delivery terms and option clause is required; LD terms may be as per GeM/SAIL norms
LTE-issued offers only
Vendor registration via www.sailtenders.co.in
Experience in supplying gear coupling components or similar mechanical couplings
Quantity
4
Category
GEAR COUPLING, ZINA 5, PT. 845
Bid Type
Two Packet Bid
Bid Validity
60 (Days)
Bid Type
Service
Evaluation
Item wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
GEAR COUPLING, ZINA 5, PT. 845 , GEAR COUPLING, ZIZS 3.5-250, PT. 845.99
Payment Timelines
Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
200
Delivery Locations
1
Delivery Cities
Sundargarh
Delivery Pincodes
769011
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Pramod Kumar Biswal | 769011,Office of GM I/c Stores & Inspection, Rourkela Steel Plant, Rourkela | Sundargarh | Odisha | 769011 | 2 | 200 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
20-Oct-2026, 8:30 am
Opening Date
21-Oct-2026, 8:30 am
Discover companies most likely to bid on this tender
GST registration certificate
PAN card
Experience certificates (similar gear coupling supplies)
Financial statements (audited, if applicable)
Bid security/EMD as per GeM/SAIL norms (exact amount not disclosed)
Technical bid documents (compliance with ATC)
OEM authorizations or dealer authorization (if applicable)
GST invoice scan template and GST portal payment screenshot
Vendor registration confirmation from www.sailtenders.co.in
Key insights about ODISHA tender market
Bidders must be LTE-registered and upload GST invoice scans plus GST payment proof. Registration is via www.sailtenders.co.in. Ensure gear coupling items meet the ZINA 5 and ZIZS 3.5-250 specifications; comply with the 25% quantity variation clause and provide necessary certificates per ATC.
Submit GST registration, PAN, experience certificates for similar supply, financial statements, OEM/Dealer authorization, technical bid documents, EMD, and GST invoice scan with GST portal payment screenshot; ensure compliance with ATC and Bid Document.
If quantity increases by up to 25%, the delivery period extends proportionally: (increased quantity/original quantity) × original delivery period, with a minimum extension of 30 days; original delivery period must not be shorter than 30 days for extension feasibility.
Post-receipt inspection is conducted at the consignee site (AT RSP STORES). Pre-dispatch inspection is only required if specified in ATC; otherwise, acceptance is based on post-delivery verification.
GST reimbursement follows actuals or applicable rate, whichever is lower, capped to the quoted GST percentage. Bidders must upload GST invoice and GST portal payment confirmation in GeM.
Only LTE-issued offers are considered. Eligible bidders must complete vendor registration on www.sailtenders.co.in and demonstrate relevant gear coupling supply experience and financial stability per Terms and ATC.
Scope is limited to the supply of goods only; no service or installation components are specified. Ensure all gear coupling items (ZINA 5, ZIZS 3.5-250) are supplied, with post-delivery inspection compliance.
Post-receipt inspection at the consignee site validates quantity and quality before acceptance; pre-dispatch inspection is not mandatory unless ATC requires it. Ensure readiness to accommodate inspection criteria at RSP Stores.