TenderDekho Logo
GEM

Konkan Railway Corporation Limited BFB Steady Arm Assembly & Catenary Clamp Tender Goa 2026 ETI/OHE P/2390 P/1120

Bid Publish Date

22-Jan-2026, 4:34 pm

Bid End Date

02-Feb-2026, 3:00 pm

Progress

Issue22-Jan-2026, 4:34 pm
AwardPending
Explore all 4 tabs to view complete tender details

Quantity

529

Category

Contact wire PG Clamp Small

Bid Type

Single Packet Bid

Key Highlights

  • Specific brand/OEM alignment required: components per RI/ETI and RDSO drawings
  • RDSO ETI/OHE standards referenced: ETI/OHE/P/2390, ETI/OHE/P/1120, ETI/OHE/P/2402, RE/33/P/1, ETI/OHE/P/3232
  • Quantities with explicit items and units: 50 BFB Steady Arm Assemblies, 70 Catenary Wire Ending Clamps, 15 12 Hole Tubular Stay Adjusters, 25 Double Suspension Clamps, 4 Mast Guy Rod Fittings
  • Scope: supply-only, including all parts per data sheets and drawings
  • Delivery option for quantity variation up to ±25% and extended periods with minimum 30 days
  • GST handling as per actuals with potential reimbursement; bidder bears applicability
  • Data Sheet upload mandatory; mismatch can trigger rejection
  • Invoices to be raised in consignee name with consignee GSTIN
  • Approval from KRCL for supplier performance and compliance with at least RI/OHE specifications
  • Technical data cross-check against Data Sheet is mandatory for bid acceptance

Categories 22

Tender Overview

Organization: Konkan Railway Corporation Limited (KRCL) seeks supply of railway electrification assemblies in SOUTH GOA, GOA. Items include: BFB Steady Arm Assembly, Catenary Wire Ending Clamp, 12 Hole Tubular Stay Adjuster, Double Suspension Clamp with lockplate, and Mast Guy Rod Fitting (Welded Steel), with reference to RDSO ETI/OHE/P/2390, ETI/OHE/P/1120, ETI/OHE/P/2402, and RE/33/P/1 drawings. Quantities: 50 Steady Arm Assemblies, 70 Wire End Clamps, 15 Stay Adjusters, 25 Double Suspension Clamps, 4 Mast Guy Rod Fittings. Scope is supply-only, at vendor’s risk, under option to modify quantities up to ±25%. This bid targets KRCL rail electrification components, requiring adherence to RDSO specs and ETI/OHE guidelines.

Technical Specifications & Requirements

  • Items and formats: BFB Steady Arm Assembly (per ETI/OHE/P/2390), Catenary Wire Ending Clamp (ETI/OHE/P/1120), 12 Hole Tubular Stay Adjuster (RI 2402 per ETI/OHE/P/2402), Double Suspension Clamp complete assembly with lockplate fasteners (RE/33/P/1 or latest), Mast Guy Rod Fitting (galvanized steel per ETI/OHE/P/3232 Rev C and ID 3232).
  • Quantities: 50, 70, 15, 25, 4 respectively; all items must be supplied as complete assemblies with all parts per specifications.
  • Quality/Compliance: Bid must compile Data Sheet matching product specifications; non-conformities may lead to rejection. Vendor should confirm ATC-enclosed specifications.
  • Delivery/Scope: Scope of supply includes all costs; delivery terms align with KRCL option clause for quantity variance up to 25% and extended timelines with minimum 30 days.
  • Brand/Engineering: Drawings and RI/ETI references indicate OEM/approved vendor alignment for cantilever and traction system components.

Terms, Conditions & Eligibility

  • EMD/Deposit: Not explicitly stated (bidders should review ATC for actual deposit terms).
  • Delivery Timeline: Delivery commences after order; extension formulas apply with minimum 30 days; option quantity adjustments up to 25% during contract.
  • GST/Tax: GST responsibility with rate-based reimbursement as per actuals or lower applicable rates.
  • Documentation: Data Sheet upload mandatory; ensure GST, PAN, experience certificates, and OEM authorizations as applicable.
  • Payment Terms: Invoices should be in consignee name with GSTIN of consignee; specific payment schedule not provided in ATC.
  • Quality/Conformity: Data Sheet alignment is critical; mismatch can lead to bid rejection. KRCL reserves right to verify specifications offline.

Key Specifications

  • BFB Steady Arm Assembly: per RDSO ETI/OHE/P/2390, Nos 50

  • Catenary Wire Ending Clamp: per ETI/OHE/P/1120, Nos 70

  • 12 Hole Tubular Stay Adjuster: RI 2402 per ETI/OHE/P/2402, Nos 15

  • Double Suspension Clamp: per RDSO drawing RE/33/P/1, Nos 25

  • Mast Guy Rod Fitting (Welded): galvanized steel per ETI/OHE/P/3232 Rev C, Nos 4

Terms & Conditions

  • Delivery quantity may adjust ±25% with extended delivery timeline as per option clause

  • GST to be borne by bidder; reimbursement as per actuals or lowest applicable rate

  • Data Sheet alignment critical; mismatches can cause bid rejection

Important Clauses

Payment Terms

Invoices must be in consignee name with GSTIN; payment terms not explicitly fixed in ATC and to be clarified in offer.

Delivery Schedule

Delivery starts after order; extended delivery time formula applies: (Increased quantity ÷ Original quantity) × Original delivery period, min 30 days.

Penalties/Liquidated Damages

Not explicitly described in ATC; KRCL retains right to reject non-conforming data and apply penalties as per standard policy.

Bidder Eligibility

  • Experience in supplying railway electrification components per RDSO standards

  • Ability to meet Data Sheet verification with OEM/approved vendor status

  • GST registration and compliant invoicing with consignee GSTIN

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

No

Item Category

BFB Steady Arm Assembly , Catenary wire Ending clamp , 12 Hole Tubeler Stay Adjuster , Double Suspension clamp complete assembly with lockplate fasteners , Mast Guy Rod Fitting Welded Steel , Contact wire PG Clamp Small , Contact Wire PG Clamp Large , Parallel groove clamp set , Parallel Groove clamp , Double Contact wire Parallel clamp

Authority Records

MINISTRY OF RAILWAYS

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 5

GeM-Bidding-8872963.pdf

Main Document

BOQ Document

BOQ

BOQ Document

BOQ

BOQ Document

BOQ

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Bill of Quantities (BOQ) 10 Items Sign in for GEM prices

#1

BFB Steady Arm Assembly

BFB Steady Arm Assembly comprising all the parts material and all as per RDSO specifications ETI OHE P 2390 for Railway Electrification use

50 nos Delivery: 21 days
#2

Catenary wire Ending clamp

Catenary wire Ending clamp comprising all the parts material and all as per RDSO specifications ETI OHE P 1120 for Railway electrification use

70 nos Delivery: 21 days
#3

12 Hole Tubeler Stay Adjuster

12 Hole Tubeler Stay Adjuster comprising of material specification and all as per RI number 2402 mentioned in RDSO specifications ETI OHE P 2402 for Railway electrification use

15 nos Delivery: 21 days
#4

Double Suspension clamp complete assembly with lockplate fasteners

Double Suspension clamp complete assembly with lockplate fasteners as per RDSO drwng no RE 33 P 1170 or latest all parts from part number 1 to 9 used in Cantilever assembly of Traction system from an approved vendor

25 nos Delivery: 21 days
#5

Mast Guy Rod Fitting Welded Steel

Mast Guy Rod Fitting Welded Steel Galvanized as per RDSOs Drawing No ETI OHE P 3232 Rev C and ID no 3232 or latest from Approved Vendors used in Traction for Railway Electrification

10 nos Delivery: 21 days
#6

Contact wire PG Clamp Small

Contact wire PG Clamp Small with RI No 1041 2 As per Drawing No ETI OHE P 1040 2 MOD E or latest from the approved vendor used for Railway Electrification

135 nos Delivery: 21 days
#7

Contact Wire PG Clamp Large

Contact Wire PG Clamp Large with RI no 1031 2 as per RDSO Drawing No ETI OHE P 1030 2 or latest from approved Vendors used in Railway Electrification

100 nos Delivery: 21 days
#8

Parallel groove clamp set

Parallel groove clamp set RI no 1051 3 complete with fastener as per dwg no ETI OHE P 1050 3 Rev A or latest RDSO spec no TI SPC OHE Fittings 0130 10 13 Rev 1 or latest

40 nos Delivery: 21 days
#9

Parallel Groove clamp

Parallel Groove clamp with RI no 1041 3 complete with fasteners as per dwg no ETI OHE P 1040 3 Rev B or latest

30 nos Delivery: 21 days
#10

Double Contact wire Parallel clamp

Double Contact wire Parallel clamp RI no 6171 complete with fasteners as per RDSO dwg no ETI OHE P 6170 Rev C or latest

54 nos Delivery: 21 days

Required Documents

1

GST registration certificate

2

Permanent Account Number (PAN) card

3

Experience certificates for similar railway electrification supply

4

Financial statements (latest audited or certified)

5

EMD/Security deposit documents (as per ATC terms)

6

Technical bid documents and Data Sheet for each item

7

OEM authorization (if applicable) for listed components

8

Manufacturer/Vendor approvals aligned with RDSO drawings RE/33/P/1, ETI/OHE/P/2390, P/1120, P/2402, P/3232

Financial Results

Rank Seller Price Item
L1
******   Under PMA
Item Categories : BFB Steady Arm Assembly,Catenary wire Ending clamp,12 Hole Tubeler Stay Adjuster,Double Suspension
L2
******   Under PMA
Item Categories : BFB Steady Arm Assembly,Catenary wire Ending clamp,12 Hole Tubeler Stay Adjuster,Double Suspension

Frequently Asked Questions

Key insights about GOA tender market

How to bid for KRCL Goa railway electrification components tender in 2026?

Submit Data Sheets for each item, provide OEM authorizations if required, and ensure GSTIN is valid. Include PAN, experience certificates, financial statements, and EMD as per ATC. Quantities are 50 Steady Arms, 70 End Clamps, 15 Stay Adjusters, 25 Suspension Clamps, 4 Mast Rod Fittings.

What documents are required for KRCL BFB Arm and Clamp tender in Goa?

Required documents include GST certificate, PAN, experience certificates for railway supply, financial statements, EMD documents, Data Sheets, OEM authorizations, and proof of compliance with RI/ETI/OHE specifications referenced in ATC.

What standards must be met for the catenary clamps in this KRCL tender?

Clamps must conform to RDSO ETI/OHE/P/1120 and RE/33/P/1 drawings, with data sheet alignment. Suppliers should provide validated Data Sheets and OEM compliance, with galvanized steel Mast Rod fittings per ETI/OHE/P/3232 Rev C.

When is delivery expected after order for KRCL Goa tender?

Delivery period follows the option clause; base delivery schedule, with minimum 30 days for any expanded quantity. If quantity increases by up to 25%, adjust delivery time proportionally according to the formula stated in ATC.

What is the payment arrangement for KRCL railway equipment supply?

Invoices must be issued in the consignee name with the consignee GSTIN. GST reimbursement follows actuals or the lower applicable rate as per the tender ATC; exact payment milestones are not specified in the ATC.

What are the essential data sheet requirements for KRCL bids in Goa?

Each item requires a Data Sheet uploaded with the bid, matching parameters to ETI/OHE/RI specifications. Any unexplained mismatch can lead to bid rejection; ensure itemwise conformity with ETI references before submission.

What quantity flexibility provisions exist in the KRCL AtC for this tender?

The purchaser reserves the right to increase or decrease quantity up to 25% at contract placement and during currency at contracted rates; additional time is computed as (increased quantity/original quantity) × original delivery period with a minimum 30 days.