TenderDekho Logo
Closed GEM

Indian Army Leh UPS & Power Room Systems Tender 40 KVA UPS ATS Operators 2026

Bid Publish Date

02-Apr-2026, 6:17 pm

Bid End Date

14-Apr-2026, 3:00 pm

EMD

₹2,09,971

Value

₹69,99,029

Progress

RA
Issue02-Apr-2026, 6:17 pm
Reverse AuctionCompleted
AwardCompleted
Explore all 4 tabs to view complete tender details

Quantity

1917

Category

40 Kva Ups To Be Supplied With 01 X Bty Banks Each To Provide 1.5-Hour Backup Battery 150AH 12v X 32 Nos

Bid Type

Two Packet Bid

Key Highlights

  • Brand/OEM requirements: OEM-certified installation personnel or OEM-authorized resellers required
  • Technical standards: Explicit IS/IEC standards not listed; Data Sheet alignment mandatory
  • Penalties: Delivery window extension rules via option clause; minimum 30 days extension logic
  • Warranty/AMC: Service support contact and escalation matrix required; dedicated service line
  • Delivery clauses: 25% quantity variation allowed during contract and currency; delivery from last order date
  • Spare parts & training: Spares kit, tool kits, and operator training included

Categories 81

Tender Overview

Organization: Indian Army (Department of Military Affairs) in Leh, Jammu & Kashmir 194101 seeks procurement and commissioning of a comprehensive power room solution. Item scope includes a 40 KVA UPS with 01 x Bty Banks and 1.5-hour backup at 150AH 12V for 32 units, 3-source ATS with 5 x 3-phase balanced outputs, Dual Source UPS ATS Panel (40 KVA), Active Harmonic Filter for 100 KVA, Automatic Phase Sequence Corrector 100 KVA, and Digital Earthing System. Includes cables, SCADA software, HVAC, environmental monitoring, installation charges, spares, trays, ducts, and integration with power generation room. Estimated contract value: ₹69,99,029; EMD: ₹2,09,971. Key differentiator: end-to-end power control system with integration, monitoring, and commissioning by OEM-certified staff. Unique aspect: inclusion of SCADA and environmental sensors for power management.

Technical Specifications & Requirements

  • Product scope: 40 KVA UPS with 1.5-hour battery backup, 150AH 12V per string for 32 units; 3-source ATS; 5 x 3-phase output distribution; Dual Source UPS ATS Panel; 100 KVA Active Harmonic Filter; 100 KVA Automatic Phase Sequence Corrector; Digital Earthing System; HVAC & Environmental Monitoring System; LT panel and fire/safety cabling.
  • Standards & compliance: Not explicitly specified; Data Sheet to be uploaded; installation by OEM-certified personnel; data sheet alignment with offered configurations.
  • Delivery scope: Supply, installation, testing, commissioning, operator training, and statutory clearances if any; integration in power room; use of aluminium and copper cabling as listed; SCADA integration with control unit.
  • Special features: Central heating, ventilation, air conditioning, antistatic flooring, and cable trays; 170–470 V range components; earth distribution bar with 10 terminals; dedicated service support and escalation matrix required.

Terms, Conditions & Eligibility

  • EMD: ₹2,09,971; provide via online or bank guarantee per bid terms.
  • Delivery terms: Option clause allows up to ±25% quantity variation; delivery period calculated from last delivery order date with minimum 30 days.
  • Installation & commissioning: Must be performed by OEM or OEM-certified resources or authorized reseller; data sheets to match offered specs.
  • Documentation: PAN, GSTIN, cancelled cheque, EFT mandate; data sheets for offered products; GST applicable per actuals with capping at quoted rate.
  • Warranty & service: Dedicated service support line and escalation matrix; availability of service centers; scope includes training and commissioning charges.
  • Contract scope: Supply, installation, testing, commissioning, operator training, and statutory clearances if required; references to OEM support and data sheet alignment.

Key Specifications

  • 40 KVA UPS with 1.5-hour backup at 150AH 12V, 32 strings

  • 3-source ATS with 5 x 3-phase output distribution

  • Dual Source UPS ATS Panel 40 KVA

  • Active Harmonic Filter for 100 KVA load

  • 100 KVA Automatic Phase Sequence Corrector

  • Digital Earthing System for Power Management

  • Aluminium 3.5 core 135 sqmm armoured; Aluminium 2 core 50 sqmm UA; Copper 6 sqmm flame; Copper 35 sqmm flame resistant

  • SCADA Supervisory Control and Data Acquisition Software with Controller Unit

  • HVAC System, Environmental Monitoring System with ambient sensors

Terms & Conditions

  • EMD amount and payment terms: ₹2,09,971 EMD; GST as per actuals with cap

  • Delivery extension: option clause permits 25% quantity variation during contract

  • Installation by OEM-certified staff; data sheets must match offered specs

Important Clauses

Payment Terms

GST as per actuals with cap; EMD enclosed; payment terms aligned to delivery milestones

Delivery Schedule

Option for 25% quantity variation; minimum 30 days extension; delivery starts after original order date

Penalties/Liquidated Damages

Delivery/installation penalties governed by option clause; LD terms not explicitly stated in data

Bidder Eligibility

  • No liquidation or bankruptcy proceedings against bidder

  • OEM-certified installation capability or OEM-authorized reseller requirement

  • Data sheet alignment with offered configuration and BOM

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

Yes

Item Category

40 Kva Ups To Be Supplied With 01 X Bty Banks Each To Provide 1.5-Hour Backup Battery 150AH 12v X 32 Nos , Automatic Transfer Switch ATS 3 source with 5 Nos of 3 phase balanced output power distr for instln of power supply equipment configuration of power control systems , Dual Source UPS ATS Panel 40 KVA , Active Harmonic Filter for 100 KVA load , Automatic Phase Sequence Corrector 100 KVA , Digital Earthing System for Power Management. , Aluminium 3.5 Core 135 sqmm Aluminium Cable armoured , Aluminium 2 Core 50 sqmm UA Cable , Copper Cable 6 Sqmm flame , Copper Cable 35 Sqmm flame resistant , Controller Unit and Professional SCADA Supervisory Control and Data Acquisition Software , AC Protection Module 1 plus 1 Hot Wire 40 KVA , 60 KVA Digital Static Voltage Regulator. 170 to 470 , Integration of Power Generation Room including Spares Tool Kits and Cable Trays Ducts etc Only for Power Room Area , High low Voltage Disconnector Three Phase , Earth distribution bar CU 200 x 100 x 3 mm with 10 terminals , Central Heating, Ventilation and Air conditioning HVAC System , Environmental Monitoring System with ambient sensors for temp and humidity. , LT PANAL , Antistatic Mat Floor , Installation and Commissioning Charges

Authority Records

MINISTRY OF DEFENCEMILITARY AFFAIRS DEPARTMENT

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 5

GeM-Bidding-9150197.pdf

Main Document

BOQ Document

BOQ

BOQ Document

BOQ

Buyer uploaded ATC document

ATC

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Bill of Quantities (BOQ) 21 Items Sign in for GEM prices

#1

40 Kva Ups To Be Supplied With 01 X Bty Banks Each To Provide 1.5-Hour Backup Battery 150AH 12v X 32 Nos

40 Kva Ups To Be Supplied With 01 X Bty Banks Each To Provide 1.5-Hour Backup Battery 150AH 12v X 32 Nos

2 nos Delivery: 90 days
#2

Automatic Transfer Switch ATS 3 source with 5 Nos of 3 phase balanced output power distr for instln of power supply equipment configuration of power control systems

Automatic Transfer Switch ATS 3 source with 5 Nos of 3 phase balanced output power distr for instln of power supply equipment configuration of power control systems

1 nos Delivery: 90 days
#3

Dual Source UPS ATS Panel 40 KVA

Dual Source UPS ATS Panel 40 KVA

1 nos Delivery: 90 days
#4

Active Harmonic Filter for 100 KVA load

Active Harmonic Filter for 100 KVA load

1 nos Delivery: 90 days
#5

Automatic Phase Sequence Corrector 100 KVA

Automatic Phase Sequence Corrector 100 KVA

1 nos Delivery: 90 days
#6

Digital Earthing System for Power Management.

Digital Earthing System for Power Management.

1 nos Delivery: 90 days
#7

Aluminium 3.5 Core 135 sqmm Aluminium Cable armoured

Aluminium 3.5 Core 135 sqmm Aluminium Cable armoured

150 meters Delivery: 90 days
#8

Aluminium 2 Core 50 sqmm UA Cable

Aluminium 2 Core 50 sqmm UA Cable

150 meters Delivery: 90 days
#9

Copper Cable 6 Sqmm flame

Copper Cable 6 Sqmm flame

250 meters Delivery: 90 days
#10

Copper Cable 35 Sqmm flame resistant

Copper Cable 35 Sqmm flame resistant

150 meters Delivery: 90 days
#11

Controller Unit and Professional SCADA Supervisory Control and Data Acquisition Software

Controller Unit & Professional SCADA Supervisory Control and Data Acquisition Software

1 nos Delivery: 90 days
#12

AC Protection Module 1 plus 1 Hot Wire 40 KVA

AC Protection Module 1 plus 1 Hot Wire 40 KVA

1 nos Delivery: 90 days
#13

60 KVA Digital Static Voltage Regulator. 170 to 470

60 KVA Digital Static Voltage Regulator. 170 to 470

1 nos Delivery: 90 days
#14

Integration of Power Generation Room including Spares Tool Kits and Cable Trays Ducts etc Only for Power Room Area

Integration of Power Generation Room including Spares Tool Kits and Cable Trays Ducts etc Only for Power Room Area

1 nos Delivery: 90 days
#15

High low Voltage Disconnector Three Phase

High low Voltage Disconnector Three Phase.

1 nos Delivery: 90 days
#16

Earth distribution bar CU 200 x 100 x 3 mm with 10 terminals

Earth distribution bar CU 200 x 100 x 3 mm with 10 terminals

1 nos Delivery: 90 days
#17

Central Heating, Ventilation and Air conditioning HVAC System

Central Heating, Ventilation and Air conditioning HVAC System

1 nos Delivery: 90 days
#18

Environmental Monitoring System with ambient sensors for temp and humidity.

Environmental Monitoring System with ambient sensors for temp and humidity.

1 nos Delivery: 90 days
#19

LT PANAL

LT PANAL

1 nos Delivery: 90 days
#20

Antistatic Mat Floor

Antistatic Mat Floor

1,200 square feet Delivery: 90 days
#21

Installation and Commissioning Charges

Installation and Commissioning Charges

1 job Delivery: 90 days

Required Documents

1

PAN Card copy

2

GSTIN copy

3

Cancelled cheque copy

4

EFT mandate copy certified by bank

5

Product data sheets for all offered items

6

OEM authorization or OEM-certified installation proof

7

Bidder/company financial statements and current solvency may be requested

Reverse Auction Schedule

Completed

Start

07-Jun-2026, 8:00 pm

End

09-Jun-2026, 8:00 pm

Duration: 48 hours

Reverse Auction Document

✅ RA concluded. Check financial results for final rankings.

Reverse Auction Results Final Prices

These are the final prices after the reverse auction event. Prices may be lower than initial bids.

Rank Seller Final Price Item
L1SYOLOGIC SOLUTIONS(MII)   Under PMA Winner ₹69,91,777Item Categories : 40 Kva Ups To Be Supplied With 01 X Bty Banks Each To Provide 1.5-Hour Backup Battery 150AH 12v X 3
L2Alliance Digisolutions (MII)   Under PMA₹71,49,388Item Categories : 40 Kva Ups To Be Supplied With 01 X Bty Banks Each To Provide 1.5-Hour Backup Battery 150AH 12v X 3
L3REAL PC COM PRIVATE LIMITED (MSE,MII)   Under PMA₹71,79,529Item Categories : 40 Kva Ups To Be Supplied With 01 X Bty Banks Each To Provide 1.5-Hour Backup Battery 150AH 12v X 3

🎉 L1 Winner

SYOLOGIC SOLUTIONS(MII)   Under PMA

Final Price: ₹69,91,777

Frequently Asked Questions

Key insights about JAMMU AND KASHMIR tender market

How to bid for the Leh UPS power room tender in 2026?

Bidders must submit PAN, GSTIN, cancelled cheque, EFT mandate, and product data sheets with their bid. Ensure OEM certification for installation, and provide data sheets matching offered specifications for the 40 KVA UPS, ATS, harmonic filter, and SCADA. Include EMD ₹2,09,971 and agree to option clause up to 25% quantity variation.

What documents are required for the Indian Army power equipment bid 2026?

Submit PAN, GSTIN, cancelled cheque, EFT mandate; vendor code creation documents; data sheets for offered equipment; OEM authorization or OEM-certified installation proof; financial statements; and proof of service support availability with escalation matrix.

What are the technical specifications for the 40 KVA UPS package in Leh?

Package includes 40 KVA UPS with 1.5-hour backup using 150AH 12V per string for 32 units, 3-source ATS, 5 x 3-phase output, 100 KVA harmonic filter, 100 KVA phase sequence corrector, digital earthing, and SCADA control with controller unit; cabling includes 135 sqmm aluminium and copper conductors as listed.

What are the delivery and extension terms for the Army tender?

Delivery may be extended by up to 25% of original quantity; additional time computed as (increased quantity/original quantity) × original delivery days, minimum 30 days; extension may apply during currency of contract as per option clause.

What are the EMD and payment terms for this procurement?

EMD is ₹2,09,971; GST will be reimbursed at actuals or capped to the quoted rate; payment linked to delivery milestones and inspection, with terms to be specified in the formal contract; ensure EFT mandate is submitted with bid.

Which OEM requirements are mandatory for installation and testing?

Installation, commissioning, testing, and training must be carried out by OEM-certified resources or OEM-authorized resellers; data sheet must align with offered configuration; service support channels and escalation matrix must be provided.

What is included in the scope of supply for the Leh power project?

Scope includes supply, installation, testing, commissioning, operator training, spares kit, cable trays, ducts, integration with power generation room, HVAC, and environmental monitoring sensors; includes statutory clearances if applicable.

What is the estimated contract value and EMD amount for bidders?

Estimated value is ₹69,99,029; EMD required is ₹2,09,971; bidders should ensure data sheet alignment and OEM certifications to qualify; provide data sheets for all offered items during submission.