Progress
Hindustan Aeronautics Limited (Department of Defence Production) in BANGALORE, KARNATAKA is inviting bids for a Mechanical Seal for Airborne Application. The procurement includes a staggered delivery plan: first lot of 20 units delivered within the standard lead time, and a second lot of 20 units after a 1-year gap. Bidders must provide an OEM CoC and clearly indicate delivery lead times in the compliance sheet. The tender allows an option to increase quantity by up to 25% at contracted rates during or after the contract, with delivery time adjustments based on the extended quantity. GST handling is on the bidder’s responsibility with reimbursement at actuals or applicable lower rates. Submission requirements include GSTIN, PAN, cancelled cheque, and EFT mandate. The tender emphasizes upload of a duly signed compliance sheet and adherence to the OEM terms. Location-based context and staggered delivery structure are key differentiators in this HAL procurement.
Product: Mechanical Seal for airborne application
Quantity: 20 units (first lot); 20 units (second lot)
Delivery: standard lead time for first lot; second lot after 1-year gap
OEM CoC required
Compliance sheet must be filled and signed
GST handling by bidder; GST invoice via GeM portal
Delivery in two lots with specified timeframes
Option to increase quantity up to 25% at contracted rates
Mandatory OEM CoC and signed compliance sheet
GST compliance and portal invoicing responsibilities
Two-batch delivery: 1st lot 20 units within standard lead time; 2nd lot 20 units after a 1-year gap.
purchaser may increase quantity up to 25% at contracted rates during or after contract period.
Bidder bears GST; reimbursement based on actuals or lower applicable rate; GST invoice must be uploaded on GeM with payment confirmation.
OEM authorization or CoC for mechanical seals used in airborne applications
Ability to deliver in two staggered lots with documented lead times
Compliance with GST, PAN, and EFT mandate submission
Financial capability to handle staged deliveries and potential quantity variations
Quantity
40
Bid Type
Single Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
Yes
Tech Clarification Time
2 Days
EMD Required
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
Yes
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
MECHANICAL SEAL FOR AIRBORNE APPLICATION
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
20
Delivery Locations
1
Delivery Cities
BANGALORE CITY
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | BANGALORE CITY | BANGALORE CITY | - | - | - | 20 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
PAN Card copy
GSTIN copy
Cancelled cheque copy
EFT mandate certified by bank
OEM CoC (Original Equipment Manufacturer Certificate)
Duly signed compliance sheet
Delivery lead time stated in compliance sheet
Bank details with supporting documents
Key insights about KARNATAKA tender market
Bidders must submit PAN, GSTIN, cancelled cheque, EFT mandate, OEM CoC, and a signed compliance sheet. Include delivery lead times for two lots: 20 units now and 20 units after a 1-year gap. Ensure GST is handled by the bidder with GST invoice uploaded on GeM.
Required documents include PAN card copy, GSTIN, cancelled cheque, EFT mandate, OEM CoC, and a duly signed compliance sheet with stated delivery lead times. Also provide bank details and ensure GST invoicing via GeM portal.
Delivery is in two lots: first lot of 20 units within standard lead time; second lot of 20 units with a 1-year gap. The option to increase quantity up to 25% at contracted rates applies during the contract period.
An OEM CoC is required; there is no explicit IS/ISO standard listed in data, but OEM certification and compliance sheet are mandatory for qualification and delivery readiness.
GST is bidder’s responsibility; reimbursement will be as per actuals or the lower applicable rate. A GST invoice and GeM payment confirmation must be uploaded.
If exercised, additional time equals (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum of 30 days; extended time may be up to the original delivery period.
The compliance sheet must be duly filled, signed, and uploaded with the bid. OEM CoC must accompany the bid submission to validate eligibility and ensure delivery readiness.
First lot: 20 units within standard lead time. Second lot: 20 units with a 1-year gap from the first lot delivery. This schedule governs contract performance and payment milestones.