TC9751030013,TC9751030021,TC9751030030,dummy1,dummy2
Bharat Heavy Electricals Limited (bhel)
MEDAK, TELANGANA
Progress
Quantity
10
Category
TC9758042017
Bid Type
Two Packet Bid
Bharat Heavy Electricals Limited (BHEL), under the Department of Heavy Industry, invites bids for an electrical equipment procurement order under a GEM tender in India. The BOQ comprises 5 items with quantities not specified, and the estimated contract value is not disclosed. A notable feature is the buyer's right to vary quantity by up to 25% of bid/contracted quantities, including during the currency of the contract. The delivery schedule references a calculated extension approach, starting from the last date of the original delivery order, with a minimum extension of 30 days. This procurement emphasizes adaptable quantity handling and extended delivery time provisions, reflecting the project’s flexible supply requirements.
Option Clause enabling quantity variation up to 25% during contract
Delivery extension calculated with minimum 30 days
BOQ items listed as 5 entries with unspecified quantities
Delivery period can be extended based on the formula (Additional quantity ÷ Original quantity) × Original delivery period with a 30-day minimum.
Purchaser may adjust quantity by up to 25% at contract placement and during the currency of the contract at contracted rates.
Must meet general GEM eligibility criteria for government procurement
Experience in electrical equipment procurement recommended
Financial standing to fulfill potential 25% quantity adjustments
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Bharat Heavy Electricals Limited (bhel)
MEDAK, TELANGANA
Bharat Heavy Electricals Limited (bhel)
MEDAK, TELANGANA
Bharat Heavy Electricals Limited (bhel)
MEDAK, TELANGANA
Bharat Heavy Electricals Limited (bhel)
MEDAK, TELANGANA
Bharat Heavy Electricals Limited (bhel)
MEDAK, TELANGANA
Tender Results
Loading results...
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) |
|---|---|---|---|---|---|---|
| 1 | TC9758042017 | RADIAL BALL BEARING | 6 | pieces | hpep_tc_con_001 | 60 |
| 2 | dummy1 | dummy 1 | 1 | pieces | hpep_tc_con_001 | 15 |
| 3 | dummy2 | dummy 2 | 1 | pieces | hpep_tc_con_001 | 15 |
| 4 | dummy3 | dummy 3 | 1 | pieces | hpep_tc_con_001 | 15 |
| 5 | dummy4 | dummy 4 | 1 | pieces | hpep_tc_con_001 | 15 |
Discover companies most likely to bid on this tender
GST registration certificate
PAN card
Experience certificates (relevant to electrical equipment procurement)
Financial statements (last 2-3 years)
EMD/Security deposit documents as per ATC
Technical bid documents
OEM authorizations (if applicable)
Any specific BIDDER SUBMISSION documents listed in ATC
Key insights about TELANGANA tender market
Bidders must submit all required BIDDER SUBMISSION documents per ATC, provide GST and PAN, and demonstrate relevant electrical equipment experience. Ensure compliance with the option clause allowing up to 25% quantity variation and understand the delivery-extension formula initiating after the original delivery date with a minimum 30 days.
Required documents include GST registration, PAN, 2–3 years of financial statements, experience certificates for electrical procurement, EMD documents per ATC, technical bid, and OEM authorizations if applicable. Refer to ATC for any organization-specific forms and seals, and submit as per GEM guidelines.
Delivery extensions follow the formula: Additional time = (Additional quantity ÷ Original quantity) × Original delivery period, with a minimum of 30 days. Extensions may occur during the contract currency, up to the original delivery period, depending on quantity changes.
The purchaser may adjust bid/contracted quantities by up to 25% at contract placement and during contract currency at the contracted rates, affecting delivery timelines and material planning for suppliers.
No item-specific technical specifications are provided in the available data; bidders should refer to the ATC and attach any standard electrical equipment qualifications, as well as ensure readiness for variable quantities across 5 BOQ items.
While the exact delivery period is not disclosed, the extension formula imposes a minimum 30-day extension for each quantity variation, ensuring suppliers plan for extended delivery windows after the original order date.
Payment terms are not disclosed in the available data; bidders should consult the ATC for payment milestones, advance payments, and post-delivery payments aligned with contract delivery and acceptance criteria.
The tender data does not specify standards; bidders should verify in ATC for any required certifications, OEM authorizations, and compliance with any general electrical equipment norms applicable to government procurements.
Sign up now to access all documents
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS