TenderDekho Logo
Closed GEM

South East Central Railway Air Circulator Fans Tender Conforming To IS 2997 (Q2) 2026

Bid Publish Date

17-Sep-2026, 11:31 am

Bid End Date

22-Sep-2026, 12:00 pm

Progress

Issue17-Sep-2026, 11:31 am
Award09-Oct-2026, 1:43 am

Key Highlights

  • • IS 2997 (Q2) compliant air circulator fans specification
  • • Option clause enabling ±25% quantity variation during/after contract
  • • Post-receipt inspection at consignee site by OEM GC & TC
  • • Supply-only scope; no service/installation included in scope

Tender Overview

The procuring entity is South East Central Railway, a division of Indian Railways, seeking the supply of Air Circulator Type Electric Fans with Regulator (V2) conforming to IS 2997 (Q2). The contract scope is limited to the supply of goods with no BOQ items listed, and the award may allow up to 25% quantity variation during and after contract formation. Post-receipt inspection is conducted by the consignee on OEMs GC & TC; pre-dispatch inspection is not indicated. This tender emphasizes conformity to IS 2997 (Q2) and OEM accountability for quality, with delivery terms adaptable to fluctuating quantities. This highlights a procurement focused on standardized cooling equipment for railway facilities and ensures inspection at the consignee site aligns with OEM documentation.

Technical Specifications & Requirements

  • Product name/category: Air Circulator Type Electric Fan with Regulator (V2)
  • Standard: IS 2997 (Q2) compliance
  • Quantity scope: 0 listed in BOQ; percentage-based quantity variation up to 25% during/after contract
  • Inspection: Post-receipt inspection at consignee site; inspection by OEM GC & TC as determined; pre-dispatch inspection not mandated in ATC
  • Delivery terms: Flexible delivery period linked to order dates; option clause allows extended time based on quantity changes, minimum 30 days
  • Scope of supply: Only supply of goods; no services included
  • Quality control: OEM accountability for GC & TC; conformity to IS 2997 (Q2) is mandatory

Terms, Conditions & Eligibility

  • Option clause: Purchaser may increase/decrease quantity by up to 25%; same rates apply; extended delivery period calculated per clause with a minimum of 30 days
  • Scope of supply: Only supply; no installation or commissioning charges indicated
  • Inspection: Post-receipt inspection by consignee on OEM GC & TC; pre-dispatch not specified
  • Delivery: Commencement tied to last date of original DO; extension rules apply with calculated timeframes
  • Documentation: Standard OEM documentation and IS 2997 (Q2) compliance evidence required

Key Specifications

  • Air Circulator Type Electric Fan with Regulator (V2) conforming to IS 2997 (Q2)

  • Quantity: 0 items in BOQ; bidder must anticipate up to +25% variation

  • Inspection: post-receipt by consignee; OEM GC & TC verification

  • Delivery: as per option clause; minimum 30 days extension if applicable

  • Scope: supply of goods only; no installation

Terms & Conditions

  • 25% quantity variation rights during/after contract

  • Post-receipt inspection by consignee on OEM GC & TC

  • IS 2997 (Q2) compliance mandatory

Important Clauses

Delivery Terms

Delivery commences from last date of original delivery order; extended time for option quantities; minimum 30 days

Inspection

Post-receipt inspection at consignee site; OEM GC & TC verification; pre-dispatch inspection not specified

Scope of Supply

Only supply of goods; no installation/commissioning included

Bidder Eligibility

  • Experience in supplying IS 2997 (Q2) compliant fans

  • Financial capacity to handle 25% quantity variation

  • OEM authorization to supply Air Circulator Type Electric Fans

Advertisement

Authority & Contact

Department

Indian Railways

Office Name

Hq New General Manager Secr

Grievance Contact

[email protected]

Financial Results

Rank Seller Price Item
L1
DARUBRAHMA ASSOCIATES   Under PMA
Item Categories : Air Circulator Type Electric Fan and Regulator (V2) Conforming To IS 2997
L2
BROSIS TECHNOLOGY   Under PMA
Item Categories : Air Circulator Type Electric Fan and Regulator (V2) Conforming To IS 2997
L3
OUR BUSINESS MACHINE   Under PMA
Item Categories : Air Circulator Type Electric Fan and Regulator (V2) Conforming To IS 2997
L4
M.N.Agencies   Under PMA
Item Categories : Air Circulator Type Electric Fan and Regulator (V2) Conforming To IS 2997
L5
CONTINENTAL ELECTRIC & TRADING CO   Under PMA
Item Categories : Air Circulator Type Electric Fan and Regulator (V2) Conforming To IS 2997
L6
Amarya International   Under PMA
Item Categories : Air Circulator Type Electric Fan and Regulator (V2) Conforming To IS 2997

Contract / Result Documents 1

Please sign in or create an account to view contract details and download result documents.

Tender Data

Bid Details

Quantity

15

Bid Type

Single Packet Bid

Bid Validity

30 (Days)

Bid Type

Service

Evaluation

Total value wise evaluation

Inspection Required

No

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

No

MII Purchase Preference

No

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

No

Item Category

Air Circulator Type Electric Fan and Regulator (V2) Conforming To IS 2997 (Q2)

Delivery Details

Max Delivery Days

15

Delivery Locations

1

Delivery Cities

Nagpur

Delivery Pincodes

440001

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Div Ranjan Yadav440001,Electrical Workshop in front of Sai Mandir near Gurudwara Kamptee Road .NagpurMaharashtra4400011515-

Authority Records

MINISTRY OF RAILWAYS

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 4

GeM-Bidding-9905219.pdf

Main Document

Other Documents

OTHER

Other Documents

OTHER

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Advertisement

Categories 7

Required Documents

1

GST registration certificate

2

Permanent Account Number (PAN) card

3

Experience certificates for similar supply

4

Financial statements showing turnover

5

EMD documents (as applicable by tender terms)

6

Technical compliance certificates evidencing IS 2997 (Q2) conformity

7

OEM authorization/specimen GC & TC from the original equipment manufacturer

Frequently Asked Questions

Key insights about MAHARASHTRA tender market

How to bid on the Air Circulator fans tender in Railways 2026

To bid, submit GST, PAN, experience certificates, financials, EMD, and technical compliance documents proving IS 2997 (Q2) conformity. Include OEM authorization and GC/TC, plus evidence of previous IS 2997-compliant fan supply. Ensure you can honor up to 25% quantity variation.

What documents are required for Railway fan tender submission 2026

Required documents include GST certificate, PAN, company financial statements, experience certificates for similar supplies, EMD proof, OEM authorization, and IS 2997 (Q2) compliance certificates. Prepare OEM GC & TC and post-receipt inspection readiness for consignee verification.

What standards must Air Circulator fans meet for this tender

Bidders must supply IS 2997 (Q2) compliant Air Circulator Type Electric Fans with regulator V2. Provide IS 2997 (Q2) test reports or approved OEM documentation. Non-compliant units are ineligible for acceptance during post-receipt inspection.

What is the payment approach for Railway fan procurement 2026

Payment terms specify supply-only scope; if applicable, reference to standard Railway terms should be confirmed in ATC. Ensure pricing accounts for potential quantity variation up to 25% at contracted rates, with inspection outcomes guiding release of payments post-acceptance.

What is the delivery timeline for the Railways Air Circulator tender

Delivery timing is tied to the last date of the original delivery order; if quantities increase, the extended period is calculated as (increased quantity/original quantity) × original delivery period, with a minimum of 30 days and possible extension to the original delivery timeframe.

Who conducts post-receipt inspection for the fan supply

Post-receipt inspection is conducted by the consignee site, based on OEM GC & TC. Pre-dispatch inspection is not specified in the ATC, so bidders should prepare rigorous post-delivery QA evidence and OEM documentation.

Advertisement