Bid Publish Date
20-Oct-2026, 1:32 pm
Bid End Date
28-Oct-2026, 4:00 pm
Location
Progress
Power Grid Corporation Of India Limited invites bids for HITACHI make PLCC System ETL-600 spares for delivery in Aligarh, Uttar Pradesh. The procurement scope references specific spares for the ETL-600 PLCC system, with no BOQ quantity disclosed. The tender emphasizes bid flexibility through an option clause allowing up to 25% quantity variation at contracted rates, and delivery timing linked to the original delivery schedule with a minimum 30-day extension rule. This opportunity targets suppliers with HITACHI-compatible PLCC components and strong supply chain readiness for critical electrical infrastructure spares. The unique aspect is the explicit quantity option mechanism and reliance on original delivery terms to govern extensions.
Option Clause allows ±25% quantity change at contract placement and during currency
Delivery period starts from the last date of the original delivery order
Minimum 30 days extension for extended delivery periods, proportional to quantity change
Delivery timing tied to original delivery order; optional extensions calculated as (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days
Not specified in available data; bidders should seek clarification during bid process
Not specified in available data; verify terms at bid stage
Demonstrated HITACHI PLCC spare supply experience
OEM authorization or proven capability to source HITACHI ETL-600 spares
Financial statements showing stability and capacity for procurement
GST and PAN compliance; corporate registration in India
Ability to meet delivery timelines with scalable logistics
Quantity
1
Bid Type
Single Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
No
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
Yes (Arbitration clause document) as per DoE OM No.F.1/2/2024-PPD dated 03.06.2024 Arbitration should not be routinely included in contracts
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
I1217 Spares of HITACHI make PLCC System ETL-600
Payment Timelines
Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
91
Delivery Locations
1
Delivery Cities
Aligarh
Delivery Pincodes
202141
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Dharm Chandra Prajapati | 202141,POWER GRID CORPORATION OF INDIA LTD, 765/400 kV GIS Sub Station, Village: Keelpur, Tahsil Khair, Dist.- Aligarh, Uttar Pradesh 202141 | Aligarh | Uttar Pradesh | 202141 | 1 | 91 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates demonstrating HITACHI PLCC spare supply capability
Financial statements (latest audited)
EMD/Security deposit documentation (as applicable by purchaser)
OEM authorizations or HITACHI supply capability letter
Technical bid documents demonstrating PLCC ETL-600 compatibility
Any prior project references for ETL-600 or similar PLCC system spares
Key insights about UTTAR PRADESH tender market
Bidders should register on GEM, prepare OEM authorization, demonstrate HITACHI ETL-600 spare supply capability, include GST, PAN, financials, and experience certificates. Ensure alignment with the option clause allowing ±25% quantity changes and confirm delivery terms tied to the original delivery order.
Submit GST registration, PAN, company incorporation, audited financial statements, HITACHI OEM authorization, experience certificates for similar PLCC spares, and technical compliance documents proving ETL-600 compatibility. Include any previous project references in electrical infrastructure.
Delivery starts from the last date of the original delivery order; extended time is (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum of 30 days. Maintain supply readiness for potential 25% quantity adjustments.
Exact standards are not listed; bidders should ensure HITACHI PLCC ETL-600 compatibility and confirm any internal company quality procedures. Request clarification on any required IS or OEM specifications during bid submission.
The tender data does not disclose the EMD amount. Bidders should monitor GEM updates or contact the purchasing authority for the exact EMD value and payment mode before submission.
Obtain official HITACHI spare part numbers, cross-reference with ETL-600 bill of materials, and secure OEM certification or supplier authorization. Include mappings of part numbers to system configurations in the technical bid.
The end date is not provided in the current data. Bidders should check the GEM portal for updated deadlines, ensuring submission of all required documents and technical bids before the stated closing date.
Payment terms are not specified in the available information. Clarify whether advances, milestones, or post-delivery payment apply during bid submission and request a formal schedule from the purchaser.