Tender Overview
Bharat Heavy Electricals Limited in BANGALORE, KARNATAKA invites bids for a 3 Ton Diesel Fork Lift. Though no BOQ items are listed, the tender mandates an EMD of ₹40,000 and requires submission of a Data Sheet to verify technical parameters. Key qualifiers include compatibility with BHEL’s existing inventory and alignment to approved drawings. The buyer reserves a 25% quantity variation, applicable during or after contract award, at contracted rates. Successful bidders must obtain Detailed Design Drawings approval within 7 days of contract award, with modification lists communicated within the same period. GST handling is on bidder’s responsibility with reimbursement limited to actuals or the prevailing rate, whichever is lower, up to quoted GST percentage. This procurement emphasizes drawing alignment, data sheet validation, and seamless system compatibility to minimize integration risks.
Technical Specifications & Requirements
- Product: 3 Ton Diesel Fork Lift
- Data Sheet must be uploaded and match offered specifications
- Compatibility with the buyer’s existing inventory; must include necessary hardware/software for compatibility at no extra cost
- Detailed Design Drawings required: approval within 7 days of award; if delayed, delivery period is adjusted excluding LD for Buyer-approved delay
- GST caption: bidder bears GST impact; reimbursement per actuals or applicable rate, not exceeding quoted GST
- Data integrity: any mismatch may lead to bid rejection; supplier must ensure ISI/ISO alignment if specified elsewhere
Terms, Conditions & Eligibility
- EMD: ₹40,000
- Quantity variation: up to 25% during/after contract at contracted rates
- Delivery timeline adjustment: based on drawing approval delay; LD not charged for buyer-caused delay
- Documentation: PAN, GSTIN, cancelled cheque, EFT mandate copy required for vendor code creation; GST compliance on quote
- Data Sheet & Compatibility: mandatory; mismatch leads to rejection; provide OEM data and compatibility details
- GST handling: bidder bears GST; reimbursement aligned to actuals or lower of actual vs quoted GST
- Drawings: approval within 7 days; modifications list issued within 7 days if revisions needed