Bid Publish Date
14-Jul-2025, 5:34 pm
Bid End Date
31-Jul-2025, 12:00 pm
Value
₹25,11,242
Location
Progress
RAQuantity
337
Category
M4061010167
Bid Type
Two Packet Bid
Ntpc Sail Power Company Ltd announces a tender for M4061010167, M4061010177, M4061010158, M4061010278, M4061010279, M4061010275, M4061010296, M4048150007, M4048150008, M4061010194, M4061010141, M4068010003, M4068010009, M4068010023, M4060050001, M4068010021, M4061010171, M4061010164, M4061010092, M4061010093, M4068010001, M4068010014, M4068010015, M4061010107, M4061010350, M4068010125, M4068010008, M4061010142 in DURG, CHHATTISGARH. Quantity: 337. Submission Deadline: 31-07-2025 12: 00: 00. Last date to apply is approaching fast!
Main Document
BOQ
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) |
|---|---|---|---|---|---|---|
| 1 | M4061010167 | XRP883 GRINDING ROLL LOCK NUT | 21 | ea | con4nspclbhilai | 180 |
| 2 | M4061010177 | XRP883 SEAL WEAR RING OF AS PER DRG NO | 12 | ea | con4nspclbhilai | 180 |
| 3 | M4061010158 | XRP883 JOURNAL HEAD AIR SEAL RING | 5 | ea | con4nspclbhilai | 180 |
| 4 | M4061010278 | XRP883 SCRAPER HOLDER LINER OF BOWL MILL | 28 | ea | con4nspclbhilai | 180 |
| 5 | M4061010279 | XRP883 LINER FOR SCRAPER BRACKET | 10 | ea | con4nspclbhilai | 180 |
| 6 | M4061010275 | XRP883 SCRAPER ASSEMBLY BOWL MILL XRP883 | 4 | set | con4nspclbhilai | 180 |
| 7 | M4061010296 | XRP883 RESTICTION RING SEGMENT SEPARATO | 26 | ea | con4nspclbhilai | 180 |
| 8 | M4048150007 | HAG NDE SHAFT BMD 133 | 2 | ea | con4nspclbhilai | 180 |
| 9 | M4048150008 | HAG DE SHAFT BMD 134 | 2 | ea | con4nspclbhilai | 180 |
| 10 | M4061010194 | XRP883 UPPER BEARING HOUSING GUARD OF RJ | 21 | ea | con4nspclbhilai | 180 |
| 11 | M4061010141 | XRP883 BUSH FOR SPRING ASSY | 11 | ea | con4nspclbhilai | 180 |
| 12 | M4068010003 | FLANGE FOR HEAD PULLEY BEARING HOUSING | 2 | ea | con4nspclbhilai | 180 |
| 13 | M4068010009 | IDLER HOUSING FOR GRAVIMETRIC FEEDER | 32 | ea | con4nspclbhilai | 180 |
| 14 | M4068010023 | FEEDER GEAR BOX COUPLING | 2 | ea | con4nspclbhilai | 180 |
| 15 | M4060050001 | MRS CAST IRON BEND | 42 | ea | con4nspclbhilai | 180 |
| 16 | M4068010021 | GRAVIMETRIC FEEDER DISCHARGE CHUTE | 2 | ea | con4nspclbhilai | 180 |
| 17 | M4061010171 | XRP883 CLAMPING RING SET 1 SET 4 NOS | 6 | set | con4nspclbhilai | 180 |
| 18 | M4061010164 | XRP883 LOCK NUT OF MAIN SHAFT | 3 | ea | con4nspclbhilai | 180 |
| 19 | M4061010092 | XRP883 SHIM FOR JOURNAL BEARING HOUSING | 5 | set | con4nspclbhilai | 180 |
| 20 | M4061010093 | XRP883 SHIM FOR AIR SEAL RING UPPER | 2 | set | con4nspclbhilai | 180 |
| 21 | M4068010001 | TAKE UP UNIT R C FEEDER | 6 | ea | con4nspclbhilai | 180 |
| 22 | M4068010014 | SIDE SKIRT COAL FEEDER RIGHT SIDE | 2 | ea | con4nspclbhilai | 180 |
| 23 | M4068010015 | SIDE SKIRT COAL FEEDER LEFT SIDE | 2 | ea | con4nspclbhilai | 180 |
| 24 | M4061010107 | XRP883 BODY LINER 2 | 12 | ea | con4nspclbhilai | 180 |
| 25 | M4061010350 | XRP883 OUTLET PLATE LINER MILL DISCHARGE | 12 | ea | con4nspclbhilai | 180 |
| 26 | M4068010125 | ROLLER WITH NUT ASSY FOR I L GATE | 50 | set | con4nspclbhilai | 180 |
| 27 | M4068010008 | INLET SPAN ROLLER FOR GRAVIMETRIC FEEDER | 12 | ea | con4nspclbhilai | 180 |
| 28 | M4061010142 | XRP883 SPACER FOR ROLLER JOURNAL ASSY | 3 | ea | con4nspclbhilai | 180 |
Extended Deadline
31-Jul-2025, 12:00 pm
Opening Date
31-Jul-2025, 12:30 pm
Extended Deadline
30-Jul-2025, 12:00 pm
Opening Date
30-Jul-2025, 12:30 pm
Start
26-Aug-2025, 5:00 pm
End
28-Aug-2025, 5:00 pm
Duration: 48 hours
Reverse Auction Document
✅ RA concluded. Check financial results for final rankings.
| S.No | Seller | Item | Date | Status |
|---|---|---|---|---|
| 1 | ********** Under PMA | - | 23-07-2025 12:15:19 | Evaluated |
| 2 | ********** Under PMA | - | 19-07-2025 17:04:15 | Evaluated |
| 3 | ********** Under PMA | - | 30-07-2025 17:50:56 | Evaluated |
| 4 | ********** Under PMA | - | 24-07-2025 17:40:18 | Evaluated |
| 5 | ********** Under PMA | - | 24-07-2025 17:12:29 | Evaluated |
| 6 | ********** Under PMA | - | 18-07-2025 18:59:18 | Evaluated |
| 7 | ********** Under PMA | - | 25-07-2025 11:14:04 | Evaluated |
| 8 | ********** Under PMA | - | 23-07-2025 14:46:39 | Evaluated |
| 9 | ********** Under PMA | - | 24-07-2025 16:50:49 | Evaluated |
| 10 | ********** Under PMA | - | 23-07-2025 18:48:00 | Evaluated |
| 11 | ********** Under PMA | - | 22-07-2025 14:22:43 | Evaluated |
Please sign in or create an account to view contract details and download result documents.
Sign up now to access all documents
Main Document
BOQ
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS