Bid Publish Date
04-Aug-2026, 9:28 am
Bid End Date
17-Aug-2026, 12:00 pm
Location
Progress
Product/service names: IT hardware upgradation for Distributed Control System (DCS)
Estimated value: Not disclosed
EMD: Not disclosed
Experience: ABB India Limited exclusive vendor per ATC
Delivery: Based on original delivery order; extended by formula with minimum 30 days
Standards/Certification: Not specified in tender data
Warranty/AMC: Not specified
Option Clause: quantity may vary ±25% at contract placement and during currency
Single-source tender: ABB India Limited only; MSE PP-MII not applicable
Delivery timelines tied to last date of original delivery order with calculated extensions
BOQ items: none listed; no itemized quantities provided
ATC/Specific terms: GeM terms apply; OEM authorization required
EMD amount not disclosed; payment terms not specified in tender data
Delivery period commence from last date of original delivery order; additional time = (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days
No LD/penalty details provided in the tender data
Only ABB India Limited is eligible as per ATC
Single-tender scenario; no MSE PP-MII preference
GeM submission with OEM authorization for ABB
| Rank | Seller | Price | Item |
|---|---|---|---|
| L1 | ABB INDIA LIMITED Under PMA | Item Categories : IT hardware upgradation of Distributed Control System (DCS) at IOCL, LBP Mumbai |
Please sign in or create an account to view contract details and download result documents.
Quantity
1
Bid Type
Single Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
4 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
No
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
IT hardware upgradation of Distributed Control System (DCS) at IOCL, LBP Mumbai
Advisory Bank
ICICI
ePBG Percentage
5%
ePBG Duration (Months)
24
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
120
Delivery Locations
1
Delivery Cities
Mumbai Suburban
Delivery Pincodes
400074
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Mahendra Pratap Singh | 400074,Indian Oil Corporation Limited Lube Blending Plant Trombay Near Tata Power Plant Gawanpada | Mumbai Suburban | Maharashtra | 400074 | 1 | 120 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
17-Aug-2026, 6:30 am
Opening Date
17-Aug-2026, 7:00 am
Extended Deadline
14-Aug-2026, 6:30 am
Opening Date
14-Aug-2026, 7:00 am
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates showing relevant DCS/IT hardware upgrades
Financial statements for the past 2–3 years
EMD/Security deposit documentation (amount not specified in tender data)
Technical bid documents and conformity certificates
OEM authorization/partner agreement for ABB India Limited
Any existing ISI/ISO certifications relevant to DCS hardware (if applicable)
Key insights about MAHARASHTRA tender market
Bidders must be ABB India Limited and submit OEM authorization through GeM. The tender specifies a single-source arrangement; prepare standard GeM bid documents, vendor qualification, and typical compliance certificates. Ensure delivery terms align with the original delivery order and be ready for quantity adjustments up to 25%.
Submit GST certificate, PAN, experience certificates in DCS/IT hardware upgrades, financial statements, EMD documentation, technical bid, OEM authorization, and any relevant certifications. Since BOQ is not listed, provide proof of capability to upgrade IOCL LBP Mumbai DCS per ABB standards.
Delivery begins from the last date of the original delivery order. If quantity is increased, the extension period is calculated as (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum extension of 30 days; the purchaser may extend up to the original delivery period.
The tender data does not disclose an EMD amount. Bidders should verify GeM tender terms or contact IOCL Marketing Division for the exact EMD submission requirements and payment method before final submission.
The provided data does not specify mandatory standards. Bidders should prepare OEM authorization for ABB, and include any relevant IT hardware standards or system integration certificates typical for DCS upgrades, while awaiting explicit IS/ISO/industry standard directives from IOCL.
The Purchaser may modify quantity by up to 25% at contract placement and again during the currency at contracted rates. Delivery extensions are driven by a formula with a minimum 30 days, ensuring flexibility for variations in ABB-procured DCS hardware.