Bid Publish Date
29-Oct-2026, 7:09 pm
Bid End Date
09-Nov-2026, 8:00 pm
Location
Progress
The procuring organization is Gondia District Panchayats under the Department Of Panchayati Raj for a Solar Power Plant (Roof Top) ONGRID System, Single Phase in Gondia, Maharashtra (441601). The tender references an on-site solar rooftop project with unspecified start/end dates and no BOQ items. A key differentiator is the explicit 25% quantity option clause allowing ±25% adjustments at contract award and during currency, at contracted rates. This indicates flexible scope and staged procurement, contingent on performance and budget. The opportunity targets local deployment of roof-top solar capacity under government solar programs, with delivery timelines tied to the extended delivery period logic. Bidders should prepare for a procurement process that accommodates scope variation while maintaining price stability. Unique aspects include the option-based quantity adjustments and the ONGRID, single-phase configuration, which implies interfacing with existing grid infrastructure and potential net-metering considerations.
There are no specific technical specifications published in the tender data. The stated category is Solar Power Plant (Roof Top) for ONGRID System, Single Phase (Q3), which implies requirements around solar modules, inverters, mounting structures, and grid-tie compatibility, but no exact models, capacities, voltages, or standards are listed. In the absence of detailed BOQ items (total items: 0), bidders should anticipate compliance with general solar PV installation norms, electrical safety standards, and local Maharashtra grid interconnection guidelines. The buyer’s clause suggests preparation for variable scope and phased delivery, with price protection under contract terms. Vendors should be ready to submit project plans, installation diagrams, and grid-connection proposals aligned to ONGRID operations.
Key terms include an option clause allowing ±25% quantity variation at contract time and during currency, with delivery timelines calculated as: (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days. This imposes schedule flexibility and necessitates contingency planning. The lack of explicit EMD and value data requires bidders to verify standard bid security practices with the procuring entity. Eligibility should cover experience in solar rooftop installations, compliance with electrical safety norms, and ability to coordinate with distribution networks for ONGRID integration. Bidders must also ensure readiness to adapt to extended delivery periods and price protections as per contract escalations.
Product/service: Solar Power Plant (Roof Top) ONGRID System, Single Phase
Quantity: not specified (BOQ items: 0)
Estimated value: not disclosed
Delivery terms: option to increase/decrease quantity up to 25% during contract
Standards/Certification: not specified; bidders to align with standard rooftop solar norms
Warranty/AMC: not specified; bidders should propose standard solar warranty
Option Clause: ±25% quantity variation at contract and during currency
Delivery: calculated extension with minimum 30 days and extended delivery window
BOQ: 0 items; no detailed specification provided
Payment/EMD: not specified in data; bidders to confirm with issuing agency
Purchaser may adjust quantity by ±25% at contract award and during currency; delivery period extends proportionally with a 30-day minimum.
Delivery timeline depends on original period and additional time calculation; extended period may commence from the last date of extended delivery period.
Not specified in provided data; bidders should seek clarification during bid submission.
Experience in rooftop solar installations for ONGRID/grid-tied systems
Technical capability to design and deploy single-phase rooftop PV solutions
Financial capacity to handle variable scope and delivery timelines
Quantity
1
Bid Type
Two Packet Bid
Bid Validity
15 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Solar Power Plant (Roof Top) for ONGRID System, Single Phase (Q3)
Max Delivery Days
15
Delivery Locations
1
Delivery Cities
Gondia
Delivery Pincodes
441911
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Indraraj Dasaram Basene | 441911,Gram Panchayat Atri P .s Tiroda Dist Gondia | Gondia | Maharashtra | 441911 | 1 | 15 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST registration certificate
Permanent account number (PAN) card
Company/organization tax clearance or financial statements
Experience certificates for prior rooftop solar installations
Technical bid documents and installation plan
OEM authorization (if applicable) for solar modules/inverters
EMD submission document (as per local norms)
Key insights about MAHARASHTRA tender market
Bidders should verify eligibility criteria, submit GST and PAN, provide prior rooftop solar installation experience, and furnish technical plans. The tender permits a 25% quantity variation, and delivery timelines depend on the original period plus calculated extensions. Ensure OEM authorizations if applicable and confirm EMD requirements with the procuring agency.
Required documents include GST certificate, PAN card, financial statements, and experience certificates for rooftop solar work. Also attach technical bid documents, installation plan, OEM authorizations if needed, and EMD submission as per local bid security norms; ensure all documents are current and properly notarized.
Specific models and capacities are not listed. Bidders should prepare for single-phase grid-tied design, including safe mounting, wiring, inverter compatibility, and grid interconnection accordance with local Maharashtra norms. Submit installation diagrams, wiring schematics, and compliance statements with bid.
Delivery period starts after the original delivery order date; extended time is calculated as (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum of 30 days. Ensure readiness to mobilize and complete within the extended period if quantity is adjusted.
EMD details are not specified in the data. Bidders should confirm the exact EMD amount or percentage with the tender issuing authority and prepare a bank guarantee or online submission as per government procurement norms to avoid disqualification.
While explicit standards are not listed, prepare to align with common rooftop PV norms, electrical safety standards, and grid interconnection guidelines for Maharashtra. Include warranty proposals, testing procedures, and compliance certificates from recognized bodies as part of technical bid.
The 25% quantity variation allows price adjustments within the contracted rate for additional or reduced quantities. Bidders should ensure price stability for fluctuating scope and present unit rates that accommodate potential upscaling or downscaling during contract validity.
Eligibility includes demonstrated rooftop solar installation experience, financial stability evidenced by statements, GST and PAN compliance, and the ability to supply and install grid-tied solar systems in single-phase configurations. OEM support and installation capability should be clearly documented.