Progress
The Procuring Organization is the Commissionerate Of Technical Education (Gujarat) inviting bids for the procurement of Signage Board (V4) – Q3 in Ahmedabad, Gujarat. The scope covers Supply, Installation, Testing and Commissioning of the signage goods with option to increase quantity by up to 25%, at contracted rates. Bidders must meet the minimum turnover requirement (three-year average) and provide evidence via audited balance sheets or CA certificate. A dedicated service helpline is required. The tender emphasizes sample approval post-award, with a five-day window for submission and a five-day turnaround for buyer modification. Unique procurement nuances include price adjustments for extended delivery and a defined delivery period tied to the original schedule.
Signage Board (V4) – Q3 category with no BOQ items; exact specs not provided
Scope includes Supply, Installation, Testing and Commissioning of signage goods
Delivery quantity options allow up to 25% increase at contracted rates
Delivery period adjustments based on original delivery period with minimum 30 days
Advance sample approval required within 5 days of award; 5-day response window for modifications
Dedicated toll-free support requirement for ongoing service
25% quantity variation permitted during contract; delivery time adjusts accordingly
Turnover requirement: minimum average annual turnover for last 3 years as per bid
Advance sample approval process: 5 samples within 5 days; buyer modification timeline
Mandatory service support contact details; certificates must be uploaded with bid
Purchaser may increase/decrease quantity by up to 25% and adjust delivery period using a calculated formula with a minimum of 30 days
Successful bidder must supply 5 advance samples within 5 days; buyer to approve or list modifications within 5 days; delays shift delivery schedule
Bidder/OEM must provide a dedicated or toll-free service support line
Minimum average turnover as specified in the bid documentation for the last 3 financial years
Demonstrated capability for Supply, Installation, Testing and Commissioning of signage goods
Submission of audited financials or CA certificate verifying turnover
Quantity
500
Bid Type
Two Packet Bid
Bid Validity
90 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+20%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
Yes
Bid Splitting Applied
No
OEM Avg. Turnover
3
Past Performance
50 %
Experience Required
3 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
Signage Board (V4) (Q3)
Advisory Bank
State Bank of India
ePBG Percentage
5%
ePBG Duration (Months)
6
Max Delivery Days
15
Delivery Locations
1
Delivery Cities
Ahmadabad
Delivery Pincodes
380015
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Mahendra Yashavantrao Patil | 380015,L D College of Engineering Ahmedabad Navrangpura Opposite Gujarat University | Ahmadabad | Gujarat | 380015 | 500 | 15 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
CATALOG Specification
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
GST registration certificate
Permanent Account Number (PAN) card
Audited financial statements for the last 3 financial years or CA certificate showing turnover
Certificate(s) proving turnover compliance as per bid document
Proof of service support (dedicated/toll-free number) for the OEM/bidder
Technical bid documents and any OEM authorizations
Advance sample submission documents (within 5 days of award) and confirmation of approval/required modifications
| Category | Specification | Requirement |
|---|---|---|
| STANDARDS | Type of Signage Board | Non-illuminated Signage Board |
| STANDARDS | Lighting Option in Signage Board | Without Lighting |
| STANDARDS | Material of Signage Board | Sunboard / Foam Sheet |
| STANDARDS | Thickness of Signage board Material | 5 mm |
| STANDARDS | Frame Material | NA (In case of No frame) |
| STANDARDS | Mounting Type | Hanging Type |
| STANDARDS | Length of the Signage Board (in Feet) | 2 feet to 4 feet |
| STANDARDS | Width of the Signage Board (in Feet) | 1 feet to 3 feet |
Key insights about GUJARAT tender market
Bidders must submit GST, PAN, turnover evidence for last 3 years, and required certificates. Ensure Supply-Installation-Testing-Commissioning scope is clear, with the option clause allowing 25% quantity variation. Provide dedicated service support contact and advance sample within 5 days of award; non-submission risks rejection.
Submit GST registration, PAN, audited financials or CA turnover certificate for last 3 years, service support proof, technical bid documents, OEM authorizations if applicable, and advance sample submission within 5 days of award.
Delivery follows the original delivery period; with up to 25% quantity variation, the extended time is calculated as (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days, and may extend to the original period with option clause.
The tender requires submission of certificates per ATC; specific ISI/ISO standards are not listed in the provided data. Ensure all certificates are uploaded and confirm any OEM authorizations as part of the technical bid.
Submit 5 advance samples within 5 days of award. Buyer will approve or specify modifications within 5 days. Bulk supply must follow the approved samples; delays by the buyer shift deadlines without LD in the interim.
Bidders must show a minimum average annual turnover for the last three years as stated in the bid document, supported by audited balance sheets or CA certificates; in case of new entities, turnover is calculated from the date of constitution.
Scope includes Supply, Installation, Testing and Commissioning of signage boards (V4) – Q3; quantity variation permitted up to 25% and service support must be available via a dedicated/toll-free line.
If the buyer delays approval of advance samples, the delivery period is adjusted accordingly; the initial calculation of extended time is preserved, but LDs or penalties are contingent on schedule changes.