TenderDekho Logo
Active GEM

Procurement Opportunity: A 001,A 002,A 003,A 004,A 005,A 006,A 007,A 008,A 009,A 010,A 011,A 012,A 013,A 014,A 015,A 016,A 0 in SOUTH WEST DELHI, DELHI

Bid Publish Date

16-Oct-2026, 1:00 pm

Bid End Date

06-Nov-2026, 1:00 pm

EMD

₹23,00,000

Value

₹4,60,00,000

Progress

Issue16-Oct-2026, 1:00 pm
AwardPending

Bharat Petroleum Corporation Ltd has released a public tender for A 001, A 002, A 003, A 004, A 005, A 006, A 007, A 008, A 009, A 010, A 011, A 012, A 013, A 014, A 015, A 016, A 017, A 018, A 019, A 020, A 021, A 022, A 023, A 024, A 025, A 026, A 027, A 028, A 029, A 030, A 031, A 032, A 033, A 034, A 035, A 036, A 037, A 038, A 039, A 040, A 041, A 042, A 043, A 044, A 045, A 046, A 047, A 048, A 049, A 050, A 051, A 052, A 053, A 054, A 055, A 056, A 057, A 058, A 059, A 060, A 061, A 062, A 063, A 064, A 065, A 066, A 067, A 068, A 069, A 070, A 071, A 072, A 073, A 074, A 075, VA 001, VA 002, VA 003, VA 004, MCS 001, RTF 001, INST 001, CBL 001 in SOUTH WEST DELHI, DELHI. Quantity: 8159. Submission Deadline: 06-11-2026 13: 00: 00. Download documents and apply online.

Advertisement

Tender Data

Bid Details

Quantity

8159

Category

A 001

Bid Type

Two Packet Bid

Bid Validity

90 (Days)

Bid Type

Service

Evaluation

Total value wise evaluation

Inspection Required

No

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

Yes

MII Purchase Preference

Yes

MII Preference Band

L1+20%

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Min. Avg. Annual Turnover

140

OEM Avg. Turnover

140

Past Performance

30 %

Warranty Period

5 days

Experience Required

3 Year (s)

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

No

Item Category

A 001 , A 002 , A 003 , A 004 , A 005 , A 006 , A 007 , A 008 , A 009 , A 010 , A 011 , A 012 , A 013 , A 014 , A 015 , A 016 , A 017 , A 018 , A 019 , A 020 , A 021 , A 022 , A 023 , A 024 , A 025 , A 026 , A 027 , A 028 , A 029 , A 030 , A 031 , A 032 , A 033 , A 034 , A 035 , A 036 , A 037 , A 038 , A 039 , A 040 , A 041 , A 042 , A 043 , A 044 , A 045 , A 046 , A 047 , A 048 , A 049 , A 050 , A 051 , A 052 , A 053 , A 054 , A 055 , A 056 , A 057 , A 058 , A 059 , A 060 , A 061 , A 062 , A 063 , A 064 , A 065 , A 066 , A 067 , A 068 , A 069 , A 070 , A 071 , A 072 , A 073 , A 074 , A 075 , VA 001 , VA 002 , VA 003 , VA 004 , MCS 001 , RTF 001 , INST 001 , CBL 001

Advisory Bank

YES Bank Limited

ePBG Percentage

5%

ePBG Duration (Months)

32

Payment Timelines

Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

Delivery Details

Max Delivery Days

75

Delivery Locations

1

Delivery Cities

New Delhi

Delivery Pincodes

110061

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Arjun Chakraborty110061,BHARAT PETROLEUM CORPORATION LIMITED, BIJWASAN INSTALLATION, NEAR DWARKA SECTOR 21 UNDERPASS, NEW DELHI - 110061New DelhiDelhi110061175-

Authority Records

MINISTRY OF PETROLEUM AND NATURAL GASBHARAT PETROLEUM CORPORATION LTD

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 5

GeM-Bidding-10046137.pdf

Main Document

Other Documents

OTHER

BOQ Document

BOQ

BOQ Document

BOQ

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Authority & Contact

Bill of Quantities (BOQ) 83 Items Sign in for GEM prices

#1

A 001

A 001 Actuator only 1 TANK FARM 1 TK01 INLET 10inch MOV

1 ea Delivery: 75 days
#2

A 002

A 002 Actuator only 2 TANK FARM 1 TK01 OUTLET 8inch MOV

1 ea Delivery: 75 days
#3

A 003

A 003 Actuator only 3 TANK FARM 1 TK01 RECIRCULATION 6inch MOV

1 ea Delivery: 75 days
#4

A 004

A 004 Actuator only 4 TANK FARM 1 TK02 INLET 10inch MOV

1 ea Delivery: 75 days
#5

A 005

A 005 Actuator only 5 TANK FARM 1 TK02 OUTLET 8inch MOV

1 ea Delivery: 75 days
#6

A 006

A 006 Actuator only 6 TANK FARM 1 TK02 RECIRCULATION 6inch MOV

1 ea Delivery: 75 days
#7

A 007

A 007 Actuator only 7 TANK FARM 1 TK03 INLET 10inch MOV

1 ea Delivery: 75 days
#8

A 008

A 008 Actuator only 8 TANK FARM 1 TK03 OUTLET 8inch MOV

1 ea Delivery: 75 days
#9

A 009

A 009 Actuator only 9 TANK FARM 1 TK03 RECIRCULATION 6inch MOV

1 ea Delivery: 75 days
#10

A 010

A 010 Actuator only 10 TANK FARM 1 TK11 INLET 10inch MOV

1 ea Delivery: 75 days
#11

A 011

A 011 Actuator only 11 TANK FARM 1 TK11 OUTLET 8inch MOV

1 ea Delivery: 75 days
#12

A 012

A 012 Actuator only 12 TANK FARM 1 TK11 RECIRCULATION 8inch MOV

1 ea Delivery: 75 days
#13

A 013

A 013 Actuator only 13 TANK FARM 2 TK27 INLET 8inch MOV

1 ea Delivery: 75 days
#14

A 014

A 014 Actuator only 14 TANK FARM 2 TK27 OUTLET 8inch MOV

1 ea Delivery: 75 days
#15

A 015

A 015 Actuator only 15 TANK FARM 2 TK28 INLET 8inch MOV

1 ea Delivery: 75 days
#16

A 016

A 016 Actuator only 16 TANK FARM 2 TK28 OUTLET 8inch MOV

1 ea Delivery: 75 days
#17

A 017

A 017 Actuator only 17 TANK FARM 2 TK33 INLET 10inch DBBV

1 ea Delivery: 75 days
#18

A 018

A 018 Actuator only 18 TANK FARM 2 TK33 OUTLET 10inch DBBV

1 ea Delivery: 75 days
#19

A 019

A 019 Actuator only 19 TANK FARM 2 TK34 INLET 8inch MOV

1 ea Delivery: 75 days
#20

A 020

A 020 Actuator only 20 TANK FARM 2 TK34 OUTLET 8inch MOV

1 ea Delivery: 75 days
#21

A 021

A 021 Actuator only 21 TANK FARM 2 TK21 RECIRCULATION 6inch MOV

1 ea Delivery: 75 days
#22

A 022

A 022 Actuator only 22 TANK FARM 2 TK22 RECIRCULATION 6inch MOV

1 ea Delivery: 75 days
#23

A 023

A 023 Actuator only 23 TANK FARM 2 TK23 RECIRCULATION 6inch MOV

1 ea Delivery: 75 days
#24

A 024

A 024 Actuator only 24 TANK FARM 2 TK24 RECIRCULATION 6inch MOV

1 ea Delivery: 75 days
#25

A 025

A 025 Actuator only 25 TANK FARM 4 TK04 INLET 10inch MOV

1 ea Delivery: 75 days
#26

A 026

A 026 Actuator only 26 TANK FARM 4 TK04 OUTLET 8inch MOV

1 ea Delivery: 75 days
#27

A 027

A 027 Actuator only 27 TANK FARM 4 TK04 RECIRCULATION 6inch MOV

1 ea Delivery: 75 days
#28

A 028

A 028 Actuator only 28 TANK FARM 4 TK05 INLET 10inch MOV

1 ea Delivery: 75 days
#29

A 029

A 029 Actuator only 29 TANK FARM 4 TK05 OUTLET 8inch MOV

1 ea Delivery: 75 days
#30

A 030

A 030 Actuator only 30 TANK FARM 4 TK05 RECIRCULATION 6inch MOV

1 ea Delivery: 75 days
#31

A 031

A 031 Actuator only 31 TANK FARM 4 TK06 INLET 10inch MOV

1 ea Delivery: 75 days
#32

A 032

A 032 Actuator only 32 TANK FARM 4 TK06 OUTLET 8inch MOV

1 ea Delivery: 75 days
#33

A 033

A 033 Actuator only 33 TANK FARM 4 TK07 INLET 10inch MOV

1 ea Delivery: 75 days
#34

A 034

A 034 Actuator only 34 TANK FARM 4 TK07 OUTLET 8inch DBBV

1 ea Delivery: 75 days
#35

A 035

A 035 Actuator only 35 TANK FARM 4 TK08 INLET 10inch DBBV

1 ea Delivery: 75 days
#36

A 036

A 036 Actuator only 36 TANK FARM 4 TK08 OUTLET 8inch DBBV

1 ea Delivery: 75 days
#37

A 037

A 037 Actuator only 37 TANK FARM 4 TK09 INLET 10inch DBBV

1 ea Delivery: 75 days
#38

A 038

A 038 Actuator only 38 TANK FARM 4 TK09 OUTLET 8inch DBBV

1 ea Delivery: 75 days
#39

A 039

A 039 Actuator only 39 TANK FARM 4 TK10 INLET 12inch DBBV

1 ea Delivery: 75 days
#40

A 040

A 040 Actuator only 40 TANK FARM 4 TK10 OUTLET 10inch DBBV

1 ea Delivery: 75 days
#41

A 041

A 041 Actuator only 41 TANK FARM 4 TK20 INLET 6inch MOV

1 ea Delivery: 75 days
#42

A 042

A 042 Actuator only 42 TANK FARM 4 TK20 OUTLET 6inch MOV

1 ea Delivery: 75 days
#43

A 043

A 043 Actuator only 43 TLF GANTRY HEADER SKO 6inch MOV

1 ea Delivery: 75 days
#44

A 044

A 044 Actuator only 44 TLF GANTRY HEADER MTO 6inch MOV

1 ea Delivery: 75 days
#45

A 045

A 045 Actuator only 45 TLF GANTRY HEADER MS 12inch MOV

1 ea Delivery: 75 days
#46

A 046

A 046 Actuator only 46 TLF GANTRY HEADER HSD 12inch MOV

1 ea Delivery: 75 days
#47

A 047

A 047 Actuator only 47 TLF GANTRY HEADER S97 8inch MOV

1 ea Delivery: 75 days
#48

A 048

A 048 Actuator only 48 TLF GANTRY HEADER ETH 4inch MOV

1 ea Delivery: 75 days
#49

A 049

A 049 Actuator only 49 TLF GANTRY HEADER ATF 8inch MOV

1 ea Delivery: 75 days
#50

A 050

A 050 Actuator only 50 UNDER GROUND TANK FARM AREA TK12 INLET 6inch MOV

1 ea Delivery: 75 days
#51

A 051

A 051 Actuator only 51 UNDER GROUND TANK FARM AREA TK12 OUTLET 6inch MOV

1 ea Delivery: 75 days
#52

A 052

A 052 Actuator only 52 UNDER GROUND TANK FARM AREA TK13 INLET 4inch MOV

1 ea Delivery: 75 days
#53

A 053

A 053 Actuator only 53 UNDER GROUND TANK FARM AREA TK13 OUTLET 4inch MOV

1 ea Delivery: 75 days
#54

A 054

A 054 Actuator only 54 UNDER GROUND TANK FARM AREA TK14 INLET 6inch MOV

1 ea Delivery: 75 days
#55

A 055

A 055 Actuator only 55 UNDER GROUND TANK FARM AREA TK14 OUTLET 6inch MOV

1 ea Delivery: 75 days
#56

A 056

A 056 Actuator only 56 UNDER GROUND TANK FARM AREA TK15 INLET 6inch MOV

1 ea Delivery: 75 days
#57

A 057

A 057 Actuator only 57 UNDER GROUND TANK FARM AREA TK15 OUTLET 4inch MOV

1 ea Delivery: 75 days
#58

A 058

A 058 Actuator only 58 UNDER GROUND TANK FARM AREA TK16 INLET 6inch MOV

1 ea Delivery: 75 days
#59

A 059

A 059 Actuator only 59 UNDER GROUND TANK FARM AREA TK16 OUTLET 6inch MOV

1 ea Delivery: 75 days
#60

A 060

A 060 Actuator only 60 UNDER GROUND TANK FARM AREA TK17 INLET 4inch MOV

1 ea Delivery: 75 days
#61

A 061

A 061 Actuator only 61 UNDER GROUND TANK FARM AREA TK17 OUTLET 6inch MOV

1 ea Delivery: 75 days
#62

A 062

A 062 Actuator only 62 UNDER GROUND TANK FARM AREA TK 18 INLET 4inch MOV

1 ea Delivery: 75 days
#63

A 063

A 063 Actuator only 63 UNDER GROUND TANK FARM AREA TK 18 OUTLET 4inch MOV

1 ea Delivery: 75 days
#64

A 064

A 064 Actuator only 64 UNDER GROUND TANK FARM AREA TK19 INLET 4inch MOV

1 ea Delivery: 75 days
#65

A 065

A 065 Actuator only 65 UNDER GROUND TANK FARM AREA TK19 OUTLET 6inch MOV

1 ea Delivery: 75 days
#66

A 066

A 066 Actuator only 66 UNDER GROUND TANK FARM AREA TK25 INLET 6inch MOV

1 ea Delivery: 75 days
#67

A 067

A 067 Actuator only 67 UNDER GROUND TANK FARM AREA TK25 OUTLET 6inch MOV

1 ea Delivery: 75 days
#68

A 068

A 068 Actuator only 68 UNDER GROUND TANK FARM AREA TK26 INLET 6inch MOV

1 ea Delivery: 75 days
#69

A 069

A 069 Actuator only 69 UNDER GROUND TANK FARM AREA TK26 OUTLET 6inch MOV

1 ea Delivery: 75 days
#70

A 070

A 070 Actuator only 70 UNDER GROUND TANK FARM AREA TK31 INLET 4inch MOV

1 ea Delivery: 75 days
#71

A 071

A 071 Actuator only 71 UNDER GROUND TANK FARM AREA TK31 OUTLET 4inch MOV

1 ea Delivery: 75 days
#72

A 072

A 072 Actuator only 72 UNDER GROUND TANK FARM AREA TK32 INLET 4inch MOV

1 ea Delivery: 75 days
#73

A 073

A 073 Actuator only 73 UNDER GROUND TANK FARM AREA TK32 OUTLET 4inch MOV

1 ea Delivery: 75 days
#74

A 074

A 074 Actuator only 74 PH PUMP HOUSE 1 PUMP 11 ETHANOL 6inch MOV

1 ea Delivery: 75 days
#75

A 075

A 075 Actuator only 75 PH PUMP HOUSE 1 PUMP 12 ETHANOL 6inch MOV

1 ea Delivery: 75 days
#76

VA 001

VA 001 Valve with actuator 1 TANK FARM 3 TK21 INLET 10inch MOV

1 ea Delivery: 75 days
#77

VA 002

VA 002 Valve with actuator 2 TANK FARM 3 TK22 INLET 10inch MOV

1 ea Delivery: 75 days
#78

VA 003

VA 003 Valve with actuator 3 TANK FARM 3 TK23 INLET 10inch MOV

1 ea Delivery: 75 days
#79

VA 004

VA 004 Valve with actuator 4 TANK FARM 3 TK24 INLET 10inch MOV

1 ea Delivery: 75 days
#80

MCS 001

MCS 001 Redundant MCS upgradation new cost 1 Control Room CR

1 ea Delivery: 75 days
#81

RTF 001

RTF 001 Actuator retrofitiing inclusive of supply of all gaskets bolts and nuts using non sparking tools cable glanding termination configuration and commissioning 75 LS

75 ls Delivery: 120 days
#82

INST 001

INST 001 Old MOV dismantling new MOV installation cabling and commissioning inclusive of supply of all gaskets bolts and nuts using non sparking tools 4 LS

4 ls Delivery: 120 days
#83

CBL 001

CBL 001 MOV signal cable supply 8000 M

8,000 m Delivery: 75 days

Categories 38

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Required Documents

1

Experience Criteria

2

Past Performance

3

Bidder Turnover

4

Certificate (Requested in ATC)

5

OEM Authorization Certificate

6

OEM Annual Turnover

7

Additional Doc 1 (Requested in ATC)

8

Compliance of BoQ specification and supporting document *In case any bidder is seeking exemption from Experience / Turnover Criteria

9

the supporting documents to prove his eligibility for exemption must be uploaded for evaluation by the buyer

Advertisement