TenderDekho Logo
Closed GEM

Bharat Heavy Electricals Limited (BHEL) Clamping Structure Tender Bhopal Madhya Pradesh 2026

Bid Publish Date

14-Nov-2026, 4:49 pm

Bid End Date

24-Nov-2026, 5:00 pm

Progress

Issue14-Nov-2026, 4:49 pm
AwardPending

Tender Overview

Bharat Heavy Electricals Limited (BHEL), operating under the Government procurement framework in Bhopal, Madhya Pradesh (462001), invites bids for ITEM# 1) CLAMPING STRUCTURE and ITEM# 2) CLAMPING STRUCTURE. The tender process includes GST considerations and inspection regimes at multiple stages, with final acceptance at BHEL, BHOPAL. Although the estimated value and EMD are not disclosed, the procurement emphasizes rigorous pre-dispatch and source inspections, and the need for material test certificates, ensuring compliance with contract drawings. The bid terms highlight supplier readiness for on-site and at-seller premises checks, and the requirement to upload GST invoices via the GeM portal. A unique emphasis is placed on inspection accountability and timely readiness for testing, with seven days allocated for inspection readiness after notification. This opportunity targets manufacturers or suppliers capable of delivering precision clamping structures under stringent quality controls.

Technical Specifications & Requirements

  • Product category: Clamping structures (ITEM# 1 and ITEM# 2)
  • Location: Bhopal, Madhya Pradesh
  • Inspection regime: Pre-dispatch inspection at seller premises or by nominated external agency; source inspection by buyer at supplier site; post-receipt inspection at consignee site; final inspection at BHEL, BHOPAL
  • Testing & certificates: Material Test Certificate mandatory; certificates must be uploaded to bid; ensure compliance with contract drawings
  • GST handling: GST payable per actuals or applicable rates (whichever is lower) with GST invoice uploaded on GeM
  • Delivery & acceptance: Final acceptance post TC & GC review; delays in inspection may be regularised without LD
  • ATC/Corrigendum compliance: All required certificates/documents must be uploaded; non-compliance risks rejection

Terms, Conditions & Eligibility

  • GST: Bidder to ensure GST applicability; GST invoice and portal payment confirmation required
  • Inspection charges: External agency/lab charges borne by Buyer; in-house testing facilities provided by Seller free of cost
  • Material Test Certificate: Must be submitted with bid
  • Delivery timeline: Specified in contract drawings; final acceptance at BHEL, BHOPAL
  • Documentation: Upload all required certificates/documents as per bid—ATC and Corrigendum applicable
  • Penalties: Liquidated Damages to be defined in contract terms; inspection timelines may affect delivery without LDs if delays are buyer-caused
  • BOQ: No items listed in BOQ; indicates focused specification on clamping structures and related inspections

Key Specifications

    • Product/service names: Clamping structures (ITEM# 1 and ITEM# 2)
    • Location: Bhopal, Madhya Pradesh
    • Inspection: Pre-dispatch at seller premises or nominated external agency; source inspection by buyer; post-receipt inspection at consignee site; final inspection at BHEL, BHOPAL
    • Testing/Quality: Material Test Certificate (MTC) mandatory
    • GST: GST invoicing via GeM; GST payable per actuals or applicable lower rate
    • Delivery/Acceptance: Final acceptance after TC & GC review; seven-day readiness period for inspection; LD not applicable if buyer delays

Terms & Conditions

  • GST payable per actuals or lower rate; invoice upload on GeM

  • Pre-dispatch/source/post-receipt inspections by specified agencies

  • Material Test Certificate mandatory; non-submission may lead to rejection

Important Clauses

Payment Terms

GST reimbursement as per actuals or applicable lower rate; invoice must be uploaded with GST confirmation on GeM

Delivery Schedule

Delivery and final acceptance contingent on TC & GC review at BHEL, BHOPAL; 7-day inspection readiness period

Penalties/Liquidated Damages

LD provisions apply for delays unless delays are attributable to the buyer; specific percentage not disclosed

Bidder Eligibility

  • Eligibility to supply clamping structures and pass inspection regimes

  • Compliance with GST invoicing and GeM portal submission

  • Ability to provide Material Test Certificate and other required documents

Advertisement

Tender Data

Bid Details

Quantity

4

Category

ITEM# 1) CLAMPING STRUCTURE

Bid Type

Two Packet Bid

Bid Validity

120 (Days)

Bid Type

Service

Evaluation

Item wise evaluation

Inspection Required

No

RA Qualification Rule

H1-Highest Priced Bid Elimination

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

No

MII Purchase Preference

Yes

MII Preference Band

L1+20%

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

Yes

Item Category

ITEM# 1) CLAMPING STRUCTURE , ITEM# 2) CLAMPING STRUCTURE

Payment Timelines

Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

Delivery Details

Max Delivery Days

2

Delivery Locations

1

Delivery Cities

Bhopal

Delivery Pincodes

462022

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Niket Agrawal462022,BHARAT HEAVY ELECTRICAL LTD, PIPLANIBhopalMadhya Pradesh462022-2-

Authority Records

MINISTRY OF HEAVY INDUSTRIESHEAVY INDUSTRY DEPARTMENT

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 7

GeM-Bidding-10168391.pdf

Main Document

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Buyer uploaded ATC document

ATC

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Categories 2

Required Documents

1

GST registration certificate

2

PAN card

3

Material Test Certificate

4

Company/Bidder VAT/GST certificate

5

Experience certificates (if any) related to clamping structures

6

Technical bid documents showing compliance with contract drawings

7

OEM authorizations or approvals (if applicable)

8

PCB/Corporate financial statements (as required)

Frequently Asked Questions

Key insights about MADHYA PRADESH tender market

How to bid on clamping structure tender in Bhopal with GST?

Bidders must ensure GST registration, upload GST invoice and payment confirmation on GeM, and submit all required certificates including Material Test Certificate. The contract requires final acceptance after TC/GC review by BHEL, BHOPAL, with pre-dispatch and source inspections as applicable.

What documents are required for clamping structure procurement in BHEL?

Submit GST registration, PAN, Material Test Certificate, company financials, experience certificates for similar clamps, OEM authorizations if applicable, and all bid documents showing conformity to contract drawings. Ensure GeM portal uploads accompany submission.

What are the inspection stages for the BHEL clamping tender?

Inspection includes pre-dispatch at seller premises or external agency, source inspection by the buyer at supplier site, post-receipt inspection at the consignee site, and final inspection at BHEL, BHOPAL after TC/GC review.

What is the delivery acceptance process for the BHEL tender?

Delivery is accepted only after final TC & GC review at BHEL, BHOPAL; readiness for inspection is required within seven days of notice, and delays due to buyer-caused scheduling may be regularised without LD.

What is the role of the Material Test Certificate in this bid?

The Material Test Certificate is mandatory; its submission accompanies the bid to demonstrate compliance with contract drawings and quality standards for the clamping structures.

Which standards or certifications are required for the clamps?

While explicit standards are not listed, bidders must provide Material Test Certificates and ensure compliance with contract drawings; any OEM authorizations should be included if applicable for the clamping structures.

How is GST handled for this GeM tender in Madhya Pradesh?

GST is reimbursed based on actuals or the lower applicable rate, subject to the quoted GST percentage cap; the vendor must upload GST invoices and payment confirmation on the GeM portal.

What happens if inspection is delayed by the buyer?

If inspection is delayed beyond seven days after notification, the delay is regularised without Liquidated Damages, and the seller should continue to prepare for inspection per the process.