The Central Agricultural University Imphal Manipur (Department of Agricultural Research and Education) issues a procurement for a comprehensive wireless network and security installation package in East Sikkim, 737101. The scope includes Wireless Access Points supporting WiFi6 with channel bandwidth options, 8-port PoE switches, CAT 6 copper cabling, camera installation, cable laying, server rack 6U fully wired, and related back-box components. Estimated value is ₹400,000 with an option to adjust quantities by up to 25%, at contracted rates. A 12‑month on-site service commitment is required, with dedicated service support and a toll-free escalation matrix. Bidders must establish or demonstrate a functional local service center and provide documentary evidence of availability prior to payment release. Unique bid conditions allow adjustable delivery timelines based on quantity changes and extended delivery periods. Location details emphasize East Sikkim, Sikkim 737101. This procurement emphasizes compliant security networking equipment alongside installation and commissioning.
Wireless Access Point supporting WiFi6 with channels 2.4 GHz 20/40 MHz and 5 GHz (noted in title as Channel Bandwidth options)
8-port PoE switch (Smart managed, 80 W total) required
CAT6 copper cabling for network backbone and camera installation
Back box and Keystone wall plates as part of patch panels
RJ-46 O box and thus required hardware for connectivity
Server rack 6U fully loaded with cable manager
Cabling laying, racking, and installation for CCTV cameras
Up to 25% quantity variation allowed at bid/contracted rates
12 months on-site service and support with a dedicated service centre
Delivery schedule depends on original vs extended delivery period with minimum 30 days
Payment to be released after submission of evidence of functional service centre and completion of installation as per ATC; no explicit milestone values provided.
Option clause allows delivery extension; extra time = (additional quantity / original quantity) × original delivery period, minimum 30 days.
12 months on-site service; LD not specified in data; ATC may include penalties for service lapse or delayed installation.
Not in liquidation or court receivership; not bankrupt
Functional service centre to be established within 30 days if not existing
Dedicated toll-free support line and escalation matrix must be provided
Quantity
471
Category
RJ 46 O BOX KEYSTONE EACE PLATE BACK BOX
Bid Type
Two Packet Bid
Bid Validity
30 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Min. Avg. Annual Turnover
1
Past Performance
40 %
Experience Required
3 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
WIRELESS ACCESS POINT wIFI6 Channel Bandwidth 2.4G 20 and 40 MHZ x4 SG 20 40 80 and 160 MHZ x4 , RJ 46 O BOX KEYSTONE EACE PLATE BACK BOX , 8 PORT POE SWITCH SMART MANAGED 80 WATT , CAT 6 CABLE COPPER , INSTALLATION AND ONFKGURATION OF CAMERAS LAYING OF CABLES CAT 6 , CASHING AND CAPPING , SERVER RACK 6U FULUY LOADED WITH CABLE MANAGER
Max Delivery Days
15
Delivery Locations
1
Delivery Cities
East District
Delivery Pincodes
737134
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Sarah Sangay Lepcha | 737134,College of Horticulture, Bermiok, South Sikkim | East District | Sikkim | 737134 | 8 | 15 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
WIRELESS ACCESS POINT wIFI6 Channel Bandwidth 2.4G 20 and 40 MHZ x4 SG 20 40 80 and 160 MHZ x4
WIRELESS ACCESS POINT wIFI6 Channel Bandwidth 2.4G 20 and 40 MHZ x4 SG 20 40 80 and 160 MHZ x4
RJ 46 O BOX KEYSTONE EACE PLATE BACK BOX
RJ 46 O BOX KEYSTONE EACE PLATE BACK BOX
8 PORT POE SWITCH SMART MANAGED 80 WATT
8 PORT POE SWITCH SMART MANAGED 80 WATT
CAT 6 CABLE COPPER
CAT-6 CABLE COPPER
INSTALLATION AND ONFKGURATION OF CAMERAS LAYING OF CABLES CAT 6
INSTALLATION & (ONFKGURATION OF CAMERAS LAYING OF CABLES CAT 6
CASHING AND CAPPING
CASHING AND CAPPING
SERVER RACK 6U FULUY LOADED WITH CABLE MANAGER
SERVER RACK 6U FULUY LOADED WITH CABLE MANAGER
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | WIRELESS ACCESS POINT wIFI6 Channel Bandwidth 2.4G 20 and 40 MHZ x4 SG 20 40 80 and 160 MHZ x4 | WIRELESS ACCESS POINT wIFI6 Channel Bandwidth 2.4G 20 and 40 MHZ x4 SG 20 40 80 and 160 MHZ x4 | 8 | pieces | cohsanjita | 15 | |
| 2 | RJ 46 O BOX KEYSTONE EACE PLATE BACK BOX | RJ 46 O BOX KEYSTONE EACE PLATE BACK BOX | 8 | pieces | cohsanjita | 15 | |
| 3 | 8 PORT POE SWITCH SMART MANAGED 80 WATT | 8 PORT POE SWITCH SMART MANAGED 80 WATT | 2 | pieces | cohsanjita | 15 | |
| 4 | CAT 6 CABLE COPPER | CAT-6 CABLE COPPER | 400 | pieces | cohsanjita | 15 | |
| 5 | INSTALLATION AND ONFKGURATION OF CAMERAS LAYING OF CABLES CAT 6 | INSTALLATION & (ONFKGURATION OF CAMERAS LAYING OF CABLES CAT 6 | 1 | pieces | cohsanjita | 15 | |
| 6 | CASHING AND CAPPING | CASHING AND CAPPING | 50 | pieces | cohsanjita | 15 | |
| 7 | SERVER RACK 6U FULUY LOADED WITH CABLE MANAGER | SERVER RACK 6U FULUY LOADED WITH CABLE MANAGER | 2 | pieces | cohsanjita | 15 |
Discover companies most likely to bid on this tender
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates for similar projects
Financial statements demonstrating financial stability
EMD/Security deposit documentation (as applicable)
Technical bid documents showing compliance with WiFi6, PoE, CAT6, camera installation
OEM authorizations or channel partner certificates (if applicable)
Proof of functional service centre establishment or plan to establish within 30 days
Key insights about SIKKIM tender market
Bidders should submit GST, PAN, experience certificates, financials, and EMD documents along with OEM authorizations. Ensure 12 months on-site service commitment and a functional service centre in the state. The bid allows up to 25% quantity variation and requires installation and commissioning of WiFi6 APs, PoE switches, and CAT6 cabling.
Required documents include GST certificate, PAN, past project experience certificates for similar installs, financial statements demonstrating stability, EMD documentation, OEM authorizations if applicable, and evidence of a functional service centre or plan to establish within 30 days of award.
The bid specifies WiFi6-capable access points supporting 2.4 GHz and 5 GHz channels, with 20/40 MHz bandwidth on 2.4 GHz and multi-band configuration on 5 GHz, integrated with an 8-port PoE switch and CAT6 cabling for full installation.
Delivery extensions follow this formula: (additional quantity/original quantity) × original delivery period, with a minimum of 30 days. The purchaser may extend the period for the extended quantity up to the original delivery period.
The ATC mandates 12 months of on-site service and support post-installation, with dedicated service contact details and an escalation matrix to resolve issues during the warranty period.
While not fully detailed, the ATC specifies 12 months of on-site service; penalties or liquidated damages would be defined in the main contract. Bidders should prepare to meet installation timelines and maintain service continuity.