TenderDekho Logo
Active GEM

BHEL Procurement Visakhapatnam Andhra Pradesh 2026 Electrical Equipment Tender with 25% Quantity Option Clause

Bid Publish Date

14-Nov-2026, 12:27 pm

Bid End Date

27-Nov-2026, 5:00 pm

Generate Docs

Progress

Issue14-Nov-2026, 12:27 pm
Corrigendum24-Nov-2026
AwardPending

Tender Overview

Bharat Heavy Electricals Limited (BHEL) invites bids under the Department of Heavy Industry for a Visakhapatnam, Andhra Pradesh procurement project. The tender comprises 83 BOQ items, though itemwise specifics are not disclosed in the available data. A key differentiator is the option clause allowing a ±25% variation in bid quantity at contracted rates, impacting delivery planning and cost. The delivery schedule links to the last original delivery date with proportional extension rules, ensuring supply flexibility. An ATC document is referenced as part of the tender terms, and the precise product category remains to be clarified in the official bid documents.

Technical Specifications & Requirements

  • No explicit technical specifications are provided in the summary; the BOQ contains 83 items but item details are not disclosed in this dataset.
  • The tender explicitly incorporates a 25% quantity variation option, enabling the purchaser to modify order quantity during and after contract award at the same contracted rates.
  • The delivery period mechanics require calculation: (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum of 30 days, and possible extension within the original delivery period.
  • An uploaded ATC document is part of the tender package and should be reviewed for compliance, terms, and any brand or OEM requirements that may be stated there.

Terms, Conditions & Eligibility

  • The tender includes an option clause for quantity variation up to ±25% at contracted rates, beginning from the last date of the original delivery order and extending through the contract duration.
  • Delivery timeframes are computed using a proportional formula, with a minimum 30-day extension, and potential extension up to the original delivery period.
  • An ATC document is available for bidders to view, which may outline specific compliance and submission requirements; no explicit EMD amount or eligibility thresholds are stated in the provided data.

Key Specifications

  • 83 total BOQ items identified in tender data

  • Quantity variation option up to ±25% at contracted rates

  • Delivery period calculated as (Increased quantity ÷ Original quantity) × Original delivery period with minimum 30 days

  • Delivery extensions permissible within the original delivery period

  • ATC document referenced for detailed terms

Terms & Conditions

  • Option Clause allows ±25% quantity variation at contracted rates

  • Delivery period rules include minimum 30-day extension and proportional time calculation

  • ATC document must be reviewed for compliance and submission requirements

Important Clauses

Delivery Terms

Delivery period starts from last date of original delivery order; extended time calculated by (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days.

Quantity Variation

Purchaser may increase or decrease quantity up to 25% during contract and currency of contract at contracted rates.

ATC Document

An Uploaded ATC document is part of the bid terms and may include mandatory compliance requirements.

Bidder Eligibility

  • Demonstrated capability to supply 83-item BOQ packages (as per tender scope)

  • Compliance with ATC terms and any brand/OEM specifications

  • Financial stability evidenced by latest financial statements

Advertisement

Tender Data

Bid Details

Quantity

74815

Category

190018400000_CS HX BOLTplus2NUTS _ M8X35LG _ IS1367 CL

Bid Type

Two Packet Bid

Bid Validity

180 (Days)

Bid Type

Service

Evaluation

Item wise evaluation

Inspection Required

No

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

No

MII Purchase Preference

Yes

MII Preference Band

L1+20%

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

No

Payment Timelines

Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

Delivery Details

Max Delivery Days

84

Delivery Locations

1

Delivery Cities

Visakhapatanam

Delivery Pincodes

530012

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Mohammad Shabir530012,Bharat Heavy Electricals Limited Heavy Plates and Vessels Plant (A Government of India Enterprise) Visakhapatnam 530012 (AP), India.VisakhapatanamAndhra Pradesh53001210084-

Authority Records

MINISTRY OF HEAVY INDUSTRIESHEAVY INDUSTRY DEPARTMENT

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 5

GeM-Bidding-10167252.pdf

Main Document

BOQ Document

BOQ

BOQ Document

BOQ

Buyer uploaded ATC document

ATC

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Authority & Contact

Office Name

10380038-heavy Plates & Vessels Plant

Grievance Contact

[email protected]

Corrigendum Updates

1 Update
#1

Update

24-Nov-2026

Extended Deadline

27-Nov-2026, 11:30 am

Opening Date

28-Nov-2026, 11:30 am

Bill of Quantities (BOQ) 83 Items Sign in for GEM prices

#1

414080001600_PUN WASHER_M16 _IS2016_A

PUN WASHER_M16 _IS2016_A

100 no Delivery: 84 days
#2

413040001600_NUT _M16 _CL4_IS1363P3

NUT _M16 _CL4_IS1363P3

145 no Delivery: 84 days
#3

189300014127_M16_JACK SCREW_SS304_135Lg_APD

M16_JACK SCREW_SS304_135Lg_APD

50 no Delivery: 84 days
#4

189300016074_BOLT M16x60_IS1363 CL4.6

BOLT M16x60_IS1363 CL4.6

50 no Delivery: 84 days
#5

190017650000_HX BLTplusN M16x2 Px110LG_ IS1367CL

HX BLTplusN M16x2 Px110LG_ IS1367CL

50 no Delivery: 84 days
#6

190018400000_CS HX BOLTplus2NUTS _ M8X35LG _ IS1367 CL

CS HX BOLTplus2NUTS _ M8X35LG _ IS1367 CL

50 no Delivery: 84 days
#7

190019360000_CS HX NUTS IS1367CL6 M24

CS HX NUTS IS1367CL6 M24

50 no Delivery: 84 days
#8

190022110000_GI NUTS IS1367 CL4.0 M16

GI NUTS IS1367 CL4.0 M16

50 no Delivery: 84 days
#9

190026860000_CS SNAP HD REVITS DIA 20X25_IS 1829

CS SNAP HD REVITS DIA 20X25_IS 1829

50 no Delivery: 84 days
#10

190028540000_STUD plus2NUTS M24X150LG SA193GrB7 194Gr2H

STUD plus2NUTS M24X150LG SA193GrB7 194Gr2H

50 no Delivery: 84 days
#11

190253220000_Splus2HXN_M24x3Px155LGSA193GrB7 194Gr2H

Splus2HXN_M24x3Px155LGSA193GrB7 194Gr2H

50 no Delivery: 84 days
#12

190253230000_Splus2HXN_M20x2.5Px140LGSA193GrB7 194Gr2H

Splus2HXN_M20x2.5Px140LGSA193GrB7 194Gr2H

50 no Delivery: 84 days
#13

190254090000_CS Washer for M24 bolt25 ST _ IS2016

CS Washer for M24 bolt25 ST _ IS2016

50 no Delivery: 84 days
#14

190254170000_Hex Lock Nut_ M24 x 3P_IS1367Cl4

Hex Lock Nut_ M24 x 3P_IS1367Cl4

50 no Delivery: 84 days
#15

190255850000_HEX LOCK NUT_M24X3P_ CS

HEX LOCK NUT_M24X3P_ CS

50 no Delivery: 84 days
#16

190258130000_BoltM20x100L_IS3757 CL8.8

BoltM20x100L_IS3757 CL8.8

50 no Delivery: 84 days
#17

411061607000_PRE STUD BOLT A T425_550 M16X70 BPS41106

PRE STUD BOLT A T425_550 M16X70 BPS41106

50 no Delivery: 84 days
#18

411062011000_PRE STUDBOLT A T425_550 M20X110 BPS41106

PRE STUDBOLT A T425_550 M20X110 BPS41106

50 no Delivery: 84 days
#19

411062014000_DE STUD_M20x140 _B16_DGPT

DE STUD_M20x140 _B16_DGPT

50 no Delivery: 84 days
#20

411171609000_FT STUD_M16x90 _B7

FT STUD_M16x90 _B7

25 no Delivery: 84 days
#21

411172012000_FT STUD_M20x120 _B7

FT STUD_M20x120 _B7

25 no Delivery: 84 days
#22

412010402000_CHS HD SCRU_M4x20 _4.8_IS1366

CHS HD SCRU_M4x20 _4.8_IS1366

10,000 no Delivery: 84 days
#23

412101205000_SLOT GRB SCRU C M12X50_22H IS2388

SLOT GRB SCRU C M12X50_22H IS2388

50 no Delivery: 84 days
#24

412211209000_BOLT_M12x90 _4.6_IS1363P1

BOLT_M12x90 _4.6_IS1363P1

500 no Delivery: 84 days
#25

412211294000_HEX HD SCREW M12X40_4.6 IS1363 P_2 CAD

HEX HD SCREW M12X40_4.6 IS1363 P_2 CAD

720 no Delivery: 84 days
#26

412211606000_BOLT_M16x60 _4.6_IS1363P1

BOLT_M16x60 _4.6_IS1363P1

100 no Delivery: 84 days
#27

412212008000_BOLT_M20x80 _4.6_IS1363P1

BOLT_M20x80 _4.6_IS1363P1

100 no Delivery: 84 days
#28

412221002000_HEX HD SCRU_M10x20 _4.6_IS1363P2

HEX HD SCRU_M10x20 _4.6_IS1363P2

300 no Delivery: 84 days
#29

412221002500_HEX HD SCRU_M10x25 _4.6_IS1363P2

HEX HD SCRU_M10x25 _4.6_IS1363P2

300 no Delivery: 84 days
#30

412330401300_TAPSCREW_ST 4.2X13C Drg4_28_700_00627 00

TAPSCREW_ST 4.2X13C Drg4_28_700_00627 00

26,600 no Delivery: 84 days
#31

412330401900_TAPSCREW_ST4.2X19C Drg 4_28_700_00627 00

TAPSCREW_ST4.2X19C Drg 4_28_700_00627 00

22,000 no Delivery: 84 days
#32

412371606000_BOLT_M16x60 _8.8_IS1364P1

BOLT_M16x60 _8.8_IS1364P1

50 no Delivery: 84 days
#33

413010002000_NUT _M20 _CL6_IS1364P3

NUT _M20 _CL6_IS1364P3

50 no Delivery: 84 days
#34

413010002400_NUT _M24 _CL6_IS1364P3 BPS 41301

NUT _M24 _CL6_IS1364P3 BPS 41301

50 no Delivery: 84 days
#35

413040000800_NUT _M 8 _CL4_IS1363P3

NUT _M 8 _CL4_IS1363P3

175 no Delivery: 84 days
#36

413040001000_NUT _M10 _CL4_IS1363P3

NUT _M10 _CL4_IS1363P3

340 no Delivery: 84 days
#37

413040001200_NUT _M12 _CL4_IS1363P3

NUT _M12 _CL4_IS1363P3

420 no Delivery: 84 days
#38

413040002000_NUT _M20 _2P CL4_IS1363P3

NUT _M20 _2P CL4_IS1363P3

80 no Delivery: 84 days
#39

413040091200_HEX NUT M12_4 IS1363 P_3 CAD 10_12 MIC

HEX NUT M12_4 IS1363 P_3 CAD 10_12 MIC

720 no Delivery: 84 days
#40

413044007200_HEX NUT M72X4_14H IS3138

HEX NUT M72X4_14H IS3138

10 no Delivery: 84 days
#41

413190001600_NUT _M16 _2H

NUT _M16 _2H

50 no Delivery: 84 days
#42

413190002000_NUT _M20 _2H

NUT _M20 _2H

50 no Delivery: 84 days
#43

413200000400_NUT _M 4 _CL8_IS1364P3

NUT _M 4 _CL8_IS1364P3

50 no Delivery: 84 days
#44

413240001600_NUT _M16 _GR7

NUT _M16 _GR7

150 no Delivery: 84 days
#45

413240002000_NUT _M20 _GR7

NUT _M20 _GR7

150 no Delivery: 84 days
#46

413240002400_NUT _M24 _GR7

NUT _M24 _GR7

50 no Delivery: 84 days
#47

414080000800_PUN WASHER_M 8 _IS2016_A

PUN WASHER_M 8 _IS2016_A

50 no Delivery: 84 days
#48

414080001000_PUN WASHER_M10 _IS2016_A

PUN WASHER_M10 _IS2016_A

700 no Delivery: 84 days
#49

414080001200_PUN WASHER_M12 _IS2016_A

PUN WASHER_M12 _IS2016_A

200 no Delivery: 84 days
#50

414080002000_PUN WASHER_M20 _IS2016_A

PUN WASHER_M20 _IS2016_A

200 no Delivery: 84 days
#51

414080002400_PUN WASHER_M24 _IS2016_A

PUN WASHER_M24 _IS2016_A

50 no Delivery: 84 days
#52

414080091200_PUNCHED WASHER A14 ID IS 2016_CAD

PUNCHED WASHER A14 ID IS 2016_CAD

1,500 no Delivery: 84 days
#53

414090000800_TAPER WASHER 9.5 IS5372 for Bolt M8

TAPER WASHER 9.5 IS5372 for Bolt M8

100 no Delivery: 84 days
#54

414090001000_TAPER WASHER 11 IS5372

TAPER WASHER 11 IS5372

50 no Delivery: 84 days
#55

414090001200_TAPER WASHER 14 IS5372

TAPER WASHER 14 IS5372

50 no Delivery: 84 days
#56

414090001600_TAPER WASHER 18 IS5372 for Bolt M16

TAPER WASHER 18 IS5372 for Bolt M16

50 no Delivery: 84 days
#57

414090002000_TAPER WASHER 22 IS5372

TAPER WASHER 22 IS5372

10 no Delivery: 84 days
#58

414090002400_TAPER WASHER 26 IS5372

TAPER WASHER 26 IS5372

30 no Delivery: 84 days
#59

418010300800_SNAP HD RIVET 3X8 GR 1 IS2998

SNAP HD RIVET 3X8 GR 1 IS2998

4,800 no Delivery: 84 days
#60

418011001000_SNAP HD RIVET 10X10MM GR1 IS2998

SNAP HD RIVET 10X10MM GR1 IS2998

100 no Delivery: 84 days
#61

418011050100_RIVET 5X10

RIVET 5X10

100 no Delivery: 84 days
#62

190254670000_STDplus2HX NUT M24x3Px140L A193GRB16 194GR7

STDplus2HX NUT M24x3Px140L A193GRB16 194GR7

20 no Delivery: 84 days
#63

190014570000_Splus2N M16x2.0 Px110LG SA193GrB7 194Gr2H

Splus2N M16x2.0 Px110LG SA193GrB7 194Gr2H

50 no Delivery: 84 days
#64

190012870000_Splus2HXN_M20x2.5Px120LG SA193GrB7 194Gr2H

Splus2HXN_M20x2.5Px120LG SA193GrB7 194Gr2H

50 no Delivery: 84 days
#65

412211004500_BOLT_M10x45 _4.6_IS1363P1

BOLT_M10x45 _4.6_IS1363P1

250 no Delivery: 84 days
#66

412221202500_HEX HD SCRU_M12x25 _4.6_IS1363_P2

HEX HD SCRU_M12x25 _4.6_IS1363_P2

450 no Delivery: 84 days
#67

412221203000_HEX HD SCRU_M12x30 _4.6_IS1363P2

HEX HD SCRU_M12x30 _4.6_IS1363P2

70 no Delivery: 84 days
#68

412221204000_HEX HD SCRU_M12x40 _4.6_IS1363P2

HEX HD SCRU_M12x40 _4.6_IS1363P2

50 no Delivery: 84 days
#69

413040000600_NUT _M 6 _CL4_IS1363P3

NUT _M 6 _CL4_IS1363P3

100 no Delivery: 84 days
#70

413040003000_NUT _M30 _CL4_IS1363_P3

NUT _M30 _CL4_IS1363_P3

25 no Delivery: 84 days
#71

413043004800_HEX NUT M48X3_14H IS3138

HEX NUT M48X3_14H IS3138

25 no Delivery: 84 days
#72

414080000600_PUN WASHER_M 6 _IS2016_A

PUN WASHER_M 6 _IS2016_A

100 no Delivery: 84 days
#73

414080003000_PUN WASHER_M30 _IS2016_A

PUN WASHER_M30 _IS2016_A

20 no Delivery: 84 days
#74

414080004800_PUNCHED WASHER A 52 ID_ IS2016

PUNCHED WASHER A 52 ID_ IS2016

20 no Delivery: 84 days
#75

416010400600_HAM DRV SCRU_2.90x6.4 _IS7519_No4

HAM DRV SCRU_2.90x6.4 _IS7519_No4

300 no Delivery: 84 days
#76

416010801200_SCRU NO 8X12.5 IS7519

SCRU NO 8X12.5 IS7519

25 no Delivery: 84 days
#77

413020001000_THIN NUT_M10 _CL5_IS1364P4

THIN NUT_M10 _CL5_IS1364P4

50 no Delivery: 84 days
#78

413250001200_DOMED CAP NUT GR A_T425 M12 BPS 41325

DOMED CAP NUT GR A_T425 M12 BPS 41325

550 no Delivery: 84 days
#79

156473110000_CS PUNCHED WASHERS M16_ IS 2016

CS PUNCHED WASHERS M16_ IS 2016

50 no Delivery: 84 days
#80

190017560000_HX BLTplusN M16x2.0 Px40LG IS1367CL4.6 4

HX BLTplusN M16x2.0 Px40LG IS1367CL4.6 4

50 no Delivery: 84 days
#81

412231625000_FDN BOLT M16X250_4.6 IS5624 type A LAT

FDN BOLT M16X250_4.6 IS5624 type A LAT

50 no Delivery: 84 days
#82

412232432000_FDN BOLT M24X320_4.6 IS5624 TY A

FDN BOLT M24X320_4.6 IS5624 TY A

60 no Delivery: 84 days
#83

412251209000_EYE BOLT_M12x90 _CL8.8

EYE BOLT_M12x90 _CL8.8

250 no Delivery: 84 days

Categories 7

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Required Documents

1

GST registration certificate

2

Permanent Account Number (PAN) card

3

Experience certificates for similar procurement

4

Financial statements (annual reports or audited statements)

5

EMD/Security deposit documentation (if required per ATC)

6

Technical bid documents illustrating compliance with ATC

7

OEM authorizations or dealership certificates (if applicable)

Frequently Asked Questions

Key insights about ANDHRA PRADESH tender market

How to bid for the BHEL Visakhapatnam electrical equipment tender 2026 with quantity option

Bidders should review the ATC and prepare submissions for GST, PAN, experience, and financial documents. Ensure compliance with the 25% quantity variation clause and demonstrate ability to scale delivery within the calculated period. Include OEM authorizations if required and submit technical bid alongside financial bid.

What documents are required for BHEL procurement bid in Visakhapatnam 2026

Submit GST certificate, PAN card, experience certificates for similar work, latest financial statements, and EMD documentation if specified in ATC. Include technical bid documents and OEM authorizations where applicable. Ensure all documents reflect current validity and align with ATC guidelines.

What are the delivery terms for the BHEL tender in Visakhapatnam

Delivery starts from the last date of the original order; if quantities increase, time extends by (Increased quantity ÷ Original quantity) × Original period, minimum 30 days. The purchaser may extend delivery within the original period; ensure schedule alignment with BOM and ATC.

What standards or certifications are required for BHEL Visakhapatnam bid

The ATC document may specify certifications; bidders should verify if ISI, ISO, or OEM standards are mandated. Prepare documentation proving compliance with any specified standards and attach relevant certificates to the technical bid.

How is the EMD amount handled for the BHEL tender 2026

EMD requirements are not explicitly disclosed in the available data; bidders should consult the ATC document for exact EMD amount, payment method, and submission process to ensure compliance with procurement norms.

What is the scope of the 83-item BOQ in this tender

The BOQ lists 83 items, though item-level details are not disclosed here. Bidders must obtain the official BOQ from the tender portal or ATC to prepare item-wise pricing, delivery schedules, and technical conformity for each category.

Where to find the official ATC terms for the Visakhapatnam tender

The ATC document is uploaded with the tender; bidders should access the ATC link in the portal listing to view mandatory terms, eligibility criteria, submission formats, and any brand or supplier constraints.

How to ensure compliance with delivery extensions in this BHEL tender

Plan for a contingency schedule that aligns with the proportional delivery extension formula and maintains buffer against minimum 30 days. Coordinate with the procurement plan and confirm capacity to scale output within contracted rates.