Bid Publish Date
21-Sep-2026, 10:33 am
Bid End Date
10-Oct-2026, 12:00 pm
Location
Progress
Goa Shipyard Limited, under the Department Of Defence Production, seeks procurement of a portable heavy duty angle grinder rated at 2400 watts. The tender references a potential quantity adjustment up to 50% of the bid quantity at contract award and during the currency of the contract, with pricing at contracted rates. Delivery timelines hinge on the last date of the original delivery order; extension rules apply if options are exercised. The scope emphasizes standard equipment rather than bespoke models and is positioned within defence production supply chains in India. Unique terms include explicit option and delivery-time calculations tied to original delivery quantities.
Product/service: Portable heavy duty angle grinder
Power rating: 2400 watts
Quantity flexibility: up to 50% increase/decrease
Delivery extension: minimum 30 days, formula-based calculation
Delivery trigger: from last date of original delivery order
BOQ status: No items listed; scope likely stand-alone procurement
ATC document: Provided by buyer for bidders to view
Delivery quantity may change by up to 50% and priced at contracted rates
Delivery period begins after the original delivery order date
Minimum extended delivery period is 30 days per option clause
ATC document exists; bidders should review for compliance
No BOQ items specified; evaluate potential stand-alone grinder procurement
Not specified in available data; refer to ATC for terms
Delivery starts from the last date of the original delivery order; extension formula applies with minimum 30 days
Not described in data; ATC may include penalties in final contract
Eligibility not explicitly detailed; bidders should review ATC document for criteria
Experience in supplying portable power tools preferred
Compliance with defence production procurement practices
Quantity
2
Bid Type
Two Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
Portable heavy duty angle grinder, 2400 watts
Payment Timelines
Payments shall be made to the Seller within 21 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
30
Delivery Locations
1
Delivery Cities
SOUTH GOA
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | SOUTH GOA | SOUTH GOA | - | - | 2 | 30 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates for similar portable grinders
Financial statements (as required by ATC/Terms)
EMD instrument (amount not disclosed) or alternative security as per ATC
Technical bid documents and compliance statements
OEM authorization letters (if applicable)
ATC view/download reference materials
Bid players should review the ATC document, ensure compliance with the 50% quantity option, and prepare documents including GST, PAN, and OEM authorizations. Confirm delivery terms based on the original delivery order’s last date and understand the 30-day minimum extension rule. Ensure the grinder is 2400W and portable heavy duty.
Prepare GST certificate, PAN card, experience certificates for similar grinders, financial statements, EMD or security as per ATC, technical bid documents, and OEM authorizations if applicable. Include the ATC viewable document reference and ensure 2400W grinder specifications are clear.
Delivery begins from the last date of the original delivery order; quantity may be increased/decreased up to 50% at contracted rates. If extended, apply the formula: (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum extension of 30 days.
The tender data does not specify explicit standards; bidders should reference the ATC for any required certifications and ensure compliance with 2400W portable grinders and any defence procurement prerequisites.
Delivery deadlines are determined by the original delivery order date; any option-based extension follows the percentage-based calculation with a minimum 30 days extension, ensuring timely compliance with contract terms.
The EMD amount is not disclosed in the provided tender data; bidders should verify the ATC document to confirm the exact EMD or security requirements and submit accordingly.
Review the ATC document linked with the tender; ensure ability to supply portable 2400W angle grinders, demonstrate relevant experience in defence production supply chains, and provide necessary financial and legal documents such as GST, PAN, and OEM authorizations.
The purchaser may adjust quantity by up to 50% of the bid quantity at contract award and during the contract currency, at contracted rates. This is governed by the option clause and requires alignment with original/extended delivery periods.