Bid Publish Date
03-Jun-2025, 10:18 am
Bid End Date
29-Jul-2025, 3:00 pm
Location
Progress
RAQuantity
62
Category
Gr-1-Sl No-1 - 65M3-HR VRT,CNTRFUGE,BILG CUM BALLAST PP
Bid Type
Two Packet Bid
A tender has been published for Garden Reach Ship Builders And Engineers Limited (grse) Gr-1-Sl No-1 - 65M3-HR VRT, CNTRFUGE, BILG CUM BALLAST PP, Gr-1-Sl No-2 - ON BOARD SPARE_BILGE CUM BALLAST PUMP, Gr-1-Sl No-3 - TOOLS FOR BILGE CUM BALLAST PUMP, Gr-1-Sl No-4 - DOCU FOR BILGE CUM BALLAST PUMP, Gr-1- Sl No-5 - INSTL AND COMM SPARES_BILGE CUM BALLAST PUMP, Gr-1-Sl No-6 - 1ST SUBMISSION_BD_BILGE CUM BALLAST PUMP, Gr-1-Sl No-7 - PRSERVTN_CONSUMBLE_BILG CUM BALLAST PUMP, Gr-1-Sl No-8 - TRAINING FOR BILGE CUM BALLAST PUMP, Gr-1-Sl No-9 - SERV ENGINEER FOR BILGE CUM BALLAST PUMP, Gr- 2-Sl No-1 - 15M3-HR VRT, CENTRIFUGAL, FW TRNSFR PUMP, Gr-2-Sl No-2 - ON BOARD SPARE FOR FRESH WATER PUMP, Gr-2-Sl No-3 - TOOLS FOR FRESH WATER PUMP, Gr-2-Sl No- 4 - DOCUMENTATION FOR FRESH WATER PUMP, Gr-2-Sl No- 5 - 1ST SUBMISION OF BD FOR FRESH WATER PUMP, Gr-2-Sl No-6 - INSTL AND COMM SPARES FOR FRESH WATER PUMP, Gr-2-Sl No-7 - PRESERVATION_CONSUMBLE_FRESH WATER PUMP, Gr-2-Sl No-8 - TRAINING FOR FRESH WATER PUMP, Gr-2-Sl No-9 - SERVICE ENGINEER FOR FRESH WATER PUMP, Gr-3-Sl No-1 - 150 M3-HR CENTRIFUGAL AUX. SW PUMP, Gr-3-Sl No-2 - ON BOARD SPARE_AUX. SW PUMP, Gr-3-Sl No-3 - TOOLS FOR AUX. SW PUMP, Gr-3-Sl No-4 - DOCUMENTATION FOR AUX. SW PUMP, Gr-3-Sl No-5 - INSTL AND COMM SPARES_AUX. SW PUMP, Gr-3-Sl No-6 - 1ST SUBMISSION_BD_AUX. SW PUMP, Gr-3-Sl No-7 - PRSERVTN_CONSUMBLE_AUX. SW PUMP, Gr-3-Sl No-8 - TRAINING FOR AUX. SW PUMP, Gr-3-Sl No-9 - SERV ENGINEER FOR AUX. SW PUMP, Gr-4-Sl No-1 - 110 M3-HR CENTRIFUGAL AUX. FW PUMP, Gr-4-Sl No-2 - ON BOARD SPARE_AUX. FW PUMP, Gr-4-Sl No-3 - TOOLS FOR AUX. FW PUMP, Gr-4-Sl No-4 - DOCUMENTATION FOR AUX. FW PUMP, Gr-4-Sl No-5 - INSTL AND COMM SPARES_AUX. FW PUMP, Gr-4-Sl No-6 - 1ST SUBMISSION_BD_AUX. FW PUMP, Gr-4-Sl No-7 - PRSERVTN_CONSUMBLE_AUX. FW PUMP, Gr-4-Sl No- 8 - TRAINING FOR AUX. FW PUMP, Gr-4-Sl No-9 - SERV ENGINEER FOR AUX. FW PUMP, Gr-5-Sl No-1 - 6 M3-HR CENTRIFUGAL SW PUMP FOR RSW PLAN, Gr-5-Sl No-2 - ON BOARD SPARE_SW PUMP FOR RSW PLANT, Gr-5-Sl No-3 - TOOLS FOR SW PUMP FOR RSW PLANT, Gr-5-Sl No-4 - DOCU FOR SW PUMP FOR RSW PLANT, Gr-5-Sl No-5 - INSTL AND COMM SPARES_SW PUMP FOR RSW PLANT, Gr-5-Sl No-6 - 1ST SUBMISSION_BD_SW PUMP FOR RSW PLANT, Gr-5-Sl No-7 - PRSERVTN_CONSUMBLE_SW PUMP FOR RSW PLANT, Gr-5-Sl No-8 - TRAINING FOR SW PUMP FOR RSW PLANT, Gr- 5-Sl No-9 - SERV ENGINEER FOR SW PUMP FOR RSW PLANT, Gr-6-Sl No-1 - 30 M3-HR ROTARY GEAR MDO TRANSFER PUMP, Gr-6-Sl No-2 - ON BOARD SPARE FOR MDO TRANSFER PUMP, Gr-6-Sl No-3 - TOOLS FOR MDO TRANSFER PUMP, Gr-6-Sl No-4 - DOCUMENTATION FOR MDO TRANSFER PUMP, Gr-6-Sl No-5 - INSTL AND COMM SPARES FOR MDO TRANSFR PUMP, Gr-6-Sl No-6 - 1ST SUBMISSION OF BD_MDO TRANSFER PUMP, Gr-6-Sl No-7 - PRESERVATION_CONSUMBLE_MDO TRANSFER PUMP, Gr-6- Sl No-8 - TRAINING FOR MDO TRANSFER PUMP, Gr-6-Sl No-9 - SERVICE ENGINEER FOR MDO TRANSFER PUMP in KOLKATA, WEST BENGAL. Quantity: 62 by. Submission Deadline: 29-07-2025 15: 00: 00. Check eligibility and apply.
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
Gr-1-Sl No-1 - 65M3-HR VRT,CNTRFUGE,BILG CUM BALLAST PP , Gr-1-Sl No-2 - ON BOARD SPARE_BILGE CUM BALLAST PUMP , Gr-1-Sl No-3 - TOOLS FOR BILGE CUM BALLAST PUMP , Gr-1-Sl No-4 - DOCU FOR BILGE CUM BALLAST PUMP , Gr-1- Sl No-5 - INSTL AND COMM SPARES_BILGE CUM BALLAST PUMP , Gr-1-Sl No-6 - 1ST SUBMISSION_BD_BILGE CUM BALLAST PUMP , Gr-1-Sl No-7 - PRSERVTN_CONSUMBLE_BILG CUM BALLAST PUMP , Gr-1-Sl No-8 - TRAINING FOR BILGE CUM BALLAST PUMP , Gr-1-Sl No-9 - SERV ENGINEER FOR BILGE CUM BALLAST PUMP , Gr- 2-Sl No-1 - 15M3-HR VRT, CENTRIFUGAL,FW TRNSFR PUMP , Gr-2-Sl No-2 - ON BOARD SPARE FOR FRESH WATER PUMP , Gr-2-Sl No-3 - TOOLS FOR FRESH WATER PUMP , Gr-2-Sl No- 4 - DOCUMENTATION FOR FRESH WATER PUMP , Gr-2-Sl No- 5 - 1ST SUBMISION OF BD FOR FRESH WATER PUMP , Gr-2-Sl No-6 - INSTL AND COMM SPARES FOR FRESH WATER PUMP , Gr-2-Sl No-7 - PRESERVATION_CONSUMBLE_FRESH WATER PUMP , Gr-2-Sl No-8 - TRAINING FOR FRESH WATER PUMP , Gr-2-Sl No-9 - SERVICE ENGINEER FOR FRESH WATER PUMP , Gr-3-Sl No-1 - 150 M3-HR CENTRIFUGAL AUX. SW PUMP , Gr-3-Sl No-2 - ON BOARD SPARE_AUX. SW PUMP , Gr-3-Sl No-3 - TOOLS FOR AUX. SW PUMP , Gr-3-Sl No-4 - DOCUMENTATION FOR AUX. SW PUMP , Gr-3-Sl No-5 - INSTL AND COMM SPARES_AUX. SW PUMP , Gr-3-Sl No-6 - 1ST SUBMISSION_BD_AUX. SW PUMP , Gr-3-Sl No-7 - PRSERVTN_CONSUMBLE_AUX. SW PUMP , Gr-3-Sl No-8 - TRAINING FOR AUX. SW PUMP , Gr-3-Sl No-9 - SERV ENGINEER FOR AUX. SW PUMP , Gr-4-Sl No-1 - 110 M3-HR CENTRIFUGAL AUX. FW PUMP , Gr-4-Sl No-2 - ON BOARD SPARE_AUX. FW PUMP , Gr-4-Sl No-3 - TOOLS FOR AUX. FW PUMP , Gr-4-Sl No-4 - DOCUMENTATION FOR AUX. FW PUMP , Gr-4-Sl No-5 - INSTL AND COMM SPARES_AUX. FW PUMP , Gr-4-Sl No-6 - 1ST SUBMISSION_BD_AUX. FW PUMP , Gr-4-Sl No-7 - PRSERVTN_CONSUMBLE_AUX. FW PUMP , Gr-4-Sl No- 8 - TRAINING FOR AUX. FW PUMP , Gr-4-Sl No-9 - SERV ENGINEER FOR AUX. FW PUMP , Gr-5-Sl No-1 - 6 M3-HR CENTRIFUGAL SW PUMP FOR RSW PLAN , Gr-5-Sl No-2 - ON BOARD SPARE_SW PUMP FOR RSW PLANT , Gr-5-Sl No-3 - TOOLS FOR SW PUMP FOR RSW PLANT , Gr-5-Sl No-4 - DOCU FOR SW PUMP FOR RSW PLANT , Gr-5-Sl No-5 - INSTL AND COMM SPARES_SW PUMP FOR RSW PLANT , Gr-5-Sl No-6 - 1ST SUBMISSION_BD_SW PUMP FOR RSW PLANT , Gr-5-Sl No-7 - PRSERVTN_CONSUMBLE_SW PUMP FOR RSW PLANT , Gr-5-Sl No-8 - TRAINING FOR SW PUMP FOR RSW PLANT , Gr- 5-Sl No-9 - SERV ENGINEER FOR SW PUMP FOR RSW PLANT , Gr-6-Sl No-1 - 30 M3-HR ROTARY GEAR MDO TRANSFER PUMP , Gr-6-Sl No-2 - ON BOARD SPARE FOR MDO TRANSFER PUMP , Gr-6-Sl No-3 - TOOLS FOR MDO TRANSFER PUMP , Gr-6-Sl No-4 - DOCUMENTATION FOR MDO TRANSFER PUMP , Gr-6-Sl No-5 - INSTL AND COMM SPARES FOR MDO TRANSFR PUMP , Gr-6-Sl No-6 - 1ST SUBMISSION OF BD_MDO TRANSFER PUMP , Gr-6-Sl No-7 - PRESERVATION_CONSUMBLE_MDO TRANSFER PUMP , Gr-6- Sl No-8 - TRAINING FOR MDO TRANSFER PUMP , Gr-6-Sl No-9 - SERVICE ENGINEER FOR MDO TRANSFER PUMP
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Gr-1-Sl No-1 - 65M3-HR VRT,CNTRFUGE,BILG CUM BALLAST PP
65M3/HR VRT,CNTRFUGE,BILG CUM BALLAST PP
Gr-1-Sl No-2 - ON BOARD SPARE_BILGE CUM BALLAST PUMP
ON BOARD SPARE_BILGE CUM BALLAST PUMP
Gr-1-Sl No-3 - TOOLS FOR BILGE CUM BALLAST PUMP
TOOLS FOR BILGE CUM BALLAST PUMP
Gr-1-Sl No-4 - DOCU FOR BILGE CUM BALLAST PUMP
DOCU FOR BILGE CUM BALLAST PUMP
Gr-1-Sl No-5 - INSTL AND COMM SPARES_BILGE CUM BALLAST PUMP
INSTL&COMM SPARES_BILGE CUM BALLAST PUMP
Gr-1-Sl No-6 - 1ST SUBMISSION_BD_BILGE CUM BALLAST PUMP
1ST SUBMISSION_BD_BILGE CUM BALLAST PUMP
Gr-1-Sl No-7 - PRSERVTN_CONSUMBLE_BILG CUM BALLAST PUMP
PRSERVTN_CONSUMBLE_BILG CUM BALLAST PUMP
Gr-1-Sl No-8 - TRAINING FOR BILGE CUM BALLAST PUMP
TRAINING FOR BILGE CUM BALLAST PUMP
Gr-1-Sl No-9 - SERV ENGINEER FOR BILGE CUM BALLAST PUMP
SERV ENGINEER FOR BILGE CUM BALLAST PUMP
Gr-2-Sl No-1 - 15M3-HR VRT, CENTRIFUGAL,FW TRNSFR PUMP
15M3/HR VRT, CENTRIFUGAL,FW TRNSFR PUMP
Gr-2-Sl No-2 - ON BOARD SPARE FOR FRESH WATER PUMP
ON BOARD SPARE FOR FRESH WATER PUMP
Gr-2-Sl No-3 - TOOLS FOR FRESH WATER PUMP
TOOLS FOR FRESH WATER PUMP
Gr-2-Sl No-4 - DOCUMENTATION FOR FRESH WATER PUMP
DOCUMENTATION FOR FRESH WATER PUMP
Gr-2-Sl No-5 - 1ST SUBMISION OF BD FOR FRESH WATER PUMP
1ST SUBMISION OF BD FOR FRESH WATER PUMP
Gr-2-Sl No-6 - INSTL AND COMM SPARES FOR FRESH WATER PUMP
INSTL & COMM SPARES FOR FRESH WATER PUMP
Gr-2-Sl No-7 - PRESERVATION_CONSUMBLE_FRESH WATER PUMP
PRESERVATION_CONSUMBLE_FRESH WATER PUMP
Gr-2-Sl No-8 - TRAINING FOR FRESH WATER PUMP
TRAINING FOR FRESH WATER PUMP
Gr-2-Sl No-9 - SERVICE ENGINEER FOR FRESH WATER PUMP
SERVICE ENGINEER FOR FRESH WATER PUMP
Gr-3-Sl No-1 - 150 M3-HR CENTRIFUGAL AUX. SW PUMP
150 M3/HR CENTRIFUGAL AUX. SW PUMP
Gr-3-Sl No-2 - ON BOARD SPARE_AUX. SW PUMP
ON BOARD SPARE_AUX. SW PUMP
Gr-3-Sl No-3 - TOOLS FOR AUX. SW PUMP
TOOLS FOR AUX. SW PUMP
Gr-3-Sl No-4 - DOCUMENTATION FOR AUX. SW PUMP
DOCUMENTATION FOR AUX. SW PUMP
Gr-3-Sl No-5 - INSTL AND COMM SPARES_AUX. SW PUMP
INSTL&COMM SPARES_AUX. SW PUMP
Gr-3-Sl No-6 - 1ST SUBMISSION_BD_AUX. SW PUMP
1ST SUBMISSION_BD_AUX. SW PUMP
Gr-3-Sl No-7 - PRSERVTN_CONSUMBLE_AUX. SW PUMP
PRSERVTN_CONSUMBLE_AUX. SW PUMP
Gr-3-Sl No-8 - TRAINING FOR AUX. SW PUMP
TRAINING FOR AUX. SW PUMP
Gr-3-Sl No-9 - SERV ENGINEER FOR AUX. SW PUMP
SERV ENGINEER FOR AUX. SW PUMP
Gr-4-Sl No-1 - 110 M3-HR CENTRIFUGAL AUX. FW PUMP
110 M3/HR CENTRIFUGAL AUX. FW PUMP
Gr-4-Sl No-2 - ON BOARD SPARE_AUX. FW PUMP
ON BOARD SPARE_AUX. FW PUMP
Gr-4-Sl No-3 - TOOLS FOR AUX. FW PUMP
TOOLS FOR AUX. FW PUMP
Gr-4-Sl No-4 - DOCUMENTATION FOR AUX. FW PUMP
DOCUMENTATION FOR AUX. FW PUMP
Gr-4-Sl No-5 - INSTL AND COMM SPARES_AUX. FW PUMP
INSTL&COMM SPARES_AUX. FW PUMP
Gr-4-Sl No-6 - 1ST SUBMISSION_BD_AUX. FW PUMP
1ST SUBMISSION_BD_AUX. FW PUMP
Gr-4-Sl No-7 - PRSERVTN_CONSUMBLE_AUX. FW PUMP
PRSERVTN_CONSUMBLE_AUX. FW PUMP
Gr-4-Sl No-8 - TRAINING FOR AUX. FW PUMP
TRAINING FOR AUX. FW PUMP
Gr-4-Sl No-9 - SERV ENGINEER FOR AUX. FW PUMP
SERV ENGINEER FOR AUX. FW PUMP
Gr-5-Sl No-1 - 6 M3-HR CENTRIFUGAL SW PUMP FOR RSW PLAN
6 M3/HR CENTRIFUGAL SW PUMP FOR RSW PLAN
Gr-5-Sl No-2 - ON BOARD SPARE_SW PUMP FOR RSW PLANT
ON BOARD SPARE_SW PUMP FOR RSW PLANT
Gr-5-Sl No-3 - TOOLS FOR SW PUMP FOR RSW PLANT
TOOLS FOR SW PUMP FOR RSW PLANT
Gr-5-Sl No-4 - DOCU FOR SW PUMP FOR RSW PLANT
DOCU FOR SW PUMP FOR RSW PLANT
Gr-5-Sl No-5 - INSTL AND COMM SPARES_SW PUMP FOR RSW PLANT
INSTL&COMM SPARES_SW PUMP FOR RSW PLANT
Gr-5-Sl No-6 - 1ST SUBMISSION_BD_SW PUMP FOR RSW PLANT
1ST SUBMISSION_BD_SW PUMP FOR RSW PLANT
Gr-5-Sl No-7 - PRSERVTN_CONSUMBLE_SW PUMP FOR RSW PLANT
PRSERVTN_CONSUMBLE_SW PUMP FOR RSW PLANT
Gr-5-Sl No-8 - TRAINING FOR SW PUMP FOR RSW PLANT
TRAINING FOR SW PUMP FOR RSW PLANT
Gr-5-Sl No-9 - SERV ENGINEER FOR SW PUMP FOR RSW PLANT
SERV ENGINEER FOR SW PUMP FOR RSW PLANT
Gr-6-Sl No-1 - 30 M3-HR ROTARY GEAR MDO TRANSFER PUMP
30 M3/HR ROTARY GEAR MDO TRANSFER PUMP
Gr-6-Sl No-2 - ON BOARD SPARE FOR MDO TRANSFER PUMP
ON BOARD SPARE FOR MDO TRANSFER PUMP
Gr-6-Sl No-3 - TOOLS FOR MDO TRANSFER PUMP
TOOLS FOR MDO TRANSFER PUMP
Gr-6-Sl No-4 - DOCUMENTATION FOR MDO TRANSFER PUMP
DOCUMENTATION FOR MDO TRANSFER PUMP
Gr-6-Sl No-5 - INSTL AND COMM SPARES FOR MDO TRANSFR PUMP
INSTL & COMM SPARES FOR MDO TRANSFR PUMP
Gr-6-Sl No-6 - 1ST SUBMISSION OF BD_MDO TRANSFER PUMP
1ST SUBMISSION OF BD_MDO TRANSFER PUMP
Gr-6-Sl No-7 - PRESERVATION_CONSUMBLE_MDO TRANSFER PUMP
PRESERVATION_CONSUMBLE_MDO TRANSFER PUMP
Gr-6-Sl No-8 - TRAINING FOR MDO TRANSFER PUMP
TRAINING FOR MDO TRANSFER PUMP
Gr-6-Sl No-9 - SERVICE ENGINEER FOR MDO TRANSFER PUMP
SERVICE ENGINEER FOR MDO TRANSFER PUMP
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | Gr-1-Sl No-1 - 65M3-HR VRT,CNTRFUGE,BILG CUM BALLAST PP | 65M3/HR VRT,CNTRFUGE,BILG CUM BALLAST PP | 4 | st | sharma.prabeenkumar | 124 | |
| 2 | Gr-1-Sl No-2 - ON BOARD SPARE_BILGE CUM BALLAST PUMP | ON BOARD SPARE_BILGE CUM BALLAST PUMP | 1 | st | sharma.prabeenkumar | 701 | |
| 3 | Gr-1-Sl No-3 - TOOLS FOR BILGE CUM BALLAST PUMP | TOOLS FOR BILGE CUM BALLAST PUMP | 1 | st | sharma.prabeenkumar | 701 | |
| 4 | Gr-1-Sl No-4 - DOCU FOR BILGE CUM BALLAST PUMP | DOCU FOR BILGE CUM BALLAST PUMP | 1 | st | sharma.prabeenkumar | 63 | |
| 5 | Gr-1-Sl No-5 - INSTL AND COMM SPARES_BILGE CUM BALLAST PUMP | INSTL&COMM SPARES_BILGE CUM BALLAST PUMP | 1 | st | sharma.prabeenkumar | 63 | |
| 6 | Gr-1-Sl No-6 - 1ST SUBMISSION_BD_BILGE CUM BALLAST PUMP | 1ST SUBMISSION_BD_BILGE CUM BALLAST PUMP | 1 | st | sharma.prabeenkumar | 30 | |
| 7 | Gr-1-Sl No-7 - PRSERVTN_CONSUMBLE_BILG CUM BALLAST PUMP | PRSERVTN_CONSUMBLE_BILG CUM BALLAST PUMP | 1 | ls | sharma.prabeenkumar | 794 | |
| 8 | Gr-1-Sl No-8 - TRAINING FOR BILGE CUM BALLAST PUMP | TRAINING FOR BILGE CUM BALLAST PUMP | 1 | ls | sharma.prabeenkumar | 732 | |
| 9 | Gr-1-Sl No-9 - SERV ENGINEER FOR BILGE CUM BALLAST PUMP | SERV ENGINEER FOR BILGE CUM BALLAST PUMP | 1 | ls | sharma.prabeenkumar | 66 | |
| 10 | Gr-2-Sl No-1 - 15M3-HR VRT, CENTRIFUGAL,FW TRNSFR PUMP | 15M3/HR VRT, CENTRIFUGAL,FW TRNSFR PUMP | 2 | st | sharma.prabeenkumar | 124 | |
| 11 | Gr-2-Sl No-2 - ON BOARD SPARE FOR FRESH WATER PUMP | ON BOARD SPARE FOR FRESH WATER PUMP | 1 | st | sharma.prabeenkumar | 701 | |
| 12 | Gr-2-Sl No-3 - TOOLS FOR FRESH WATER PUMP | TOOLS FOR FRESH WATER PUMP | 1 | st | sharma.prabeenkumar | 701 | |
| 13 | Gr-2-Sl No-4 - DOCUMENTATION FOR FRESH WATER PUMP | DOCUMENTATION FOR FRESH WATER PUMP | 1 | st | sharma.prabeenkumar | 63 | |
| 14 | Gr-2-Sl No-5 - 1ST SUBMISION OF BD FOR FRESH WATER PUMP | 1ST SUBMISION OF BD FOR FRESH WATER PUMP | 1 | st | sharma.prabeenkumar | 30 | |
| 15 | Gr-2-Sl No-6 - INSTL AND COMM SPARES FOR FRESH WATER PUMP | INSTL & COMM SPARES FOR FRESH WATER PUMP | 1 | st | sharma.prabeenkumar | 63 | |
| 16 | Gr-2-Sl No-7 - PRESERVATION_CONSUMBLE_FRESH WATER PUMP | PRESERVATION_CONSUMBLE_FRESH WATER PUMP | 1 | ls | sharma.prabeenkumar | 794 | |
| 17 | Gr-2-Sl No-8 - TRAINING FOR FRESH WATER PUMP | TRAINING FOR FRESH WATER PUMP | 1 | ls | sharma.prabeenkumar | 732 | |
| 18 | Gr-2-Sl No-9 - SERVICE ENGINEER FOR FRESH WATER PUMP | SERVICE ENGINEER FOR FRESH WATER PUMP | 1 | ls | sharma.prabeenkumar | 66 | |
| 19 | Gr-3-Sl No-1 - 150 M3-HR CENTRIFUGAL AUX. SW PUMP | 150 M3/HR CENTRIFUGAL AUX. SW PUMP | 3 | st | sharma.prabeenkumar | 124 | |
| 20 | Gr-3-Sl No-2 - ON BOARD SPARE_AUX. SW PUMP | ON BOARD SPARE_AUX. SW PUMP | 1 | st | sharma.prabeenkumar | 701 | |
| 21 | Gr-3-Sl No-3 - TOOLS FOR AUX. SW PUMP | TOOLS FOR AUX. SW PUMP | 1 | st | sharma.prabeenkumar | 701 | |
| 22 | Gr-3-Sl No-4 - DOCUMENTATION FOR AUX. SW PUMP | DOCUMENTATION FOR AUX. SW PUMP | 1 | st | sharma.prabeenkumar | 63 | |
| 23 | Gr-3-Sl No-5 - INSTL AND COMM SPARES_AUX. SW PUMP | INSTL&COMM SPARES_AUX. SW PUMP | 1 | st | sharma.prabeenkumar | 63 | |
| 24 | Gr-3-Sl No-6 - 1ST SUBMISSION_BD_AUX. SW PUMP | 1ST SUBMISSION_BD_AUX. SW PUMP | 1 | st | sharma.prabeenkumar | 30 | |
| 25 | Gr-3-Sl No-7 - PRSERVTN_CONSUMBLE_AUX. SW PUMP | PRSERVTN_CONSUMBLE_AUX. SW PUMP | 1 | ls | sharma.prabeenkumar | 794 | |
| 26 | Gr-3-Sl No-8 - TRAINING FOR AUX. SW PUMP | TRAINING FOR AUX. SW PUMP | 1 | ls | sharma.prabeenkumar | 732 | |
| 27 | Gr-3-Sl No-9 - SERV ENGINEER FOR AUX. SW PUMP | SERV ENGINEER FOR AUX. SW PUMP | 1 | ls | sharma.prabeenkumar | 66 | |
| 28 | Gr-4-Sl No-1 - 110 M3-HR CENTRIFUGAL AUX. FW PUMP | 110 M3/HR CENTRIFUGAL AUX. FW PUMP | 2 | st | sharma.prabeenkumar | 124 | |
| 29 | Gr-4-Sl No-2 - ON BOARD SPARE_AUX. FW PUMP | ON BOARD SPARE_AUX. FW PUMP | 1 | st | sharma.prabeenkumar | 701 | |
| 30 | Gr-4-Sl No-3 - TOOLS FOR AUX. FW PUMP | TOOLS FOR AUX. FW PUMP | 1 | st | sharma.prabeenkumar | 701 | |
| 31 | Gr-4-Sl No-4 - DOCUMENTATION FOR AUX. FW PUMP | DOCUMENTATION FOR AUX. FW PUMP | 1 | st | sharma.prabeenkumar | 63 | |
| 32 | Gr-4-Sl No-5 - INSTL AND COMM SPARES_AUX. FW PUMP | INSTL&COMM SPARES_AUX. FW PUMP | 1 | st | sharma.prabeenkumar | 63 | |
| 33 | Gr-4-Sl No-6 - 1ST SUBMISSION_BD_AUX. FW PUMP | 1ST SUBMISSION_BD_AUX. FW PUMP | 1 | st | sharma.prabeenkumar | 30 | |
| 34 | Gr-4-Sl No-7 - PRSERVTN_CONSUMBLE_AUX. FW PUMP | PRSERVTN_CONSUMBLE_AUX. FW PUMP | 1 | ls | sharma.prabeenkumar | 794 | |
| 35 | Gr-4-Sl No-8 - TRAINING FOR AUX. FW PUMP | TRAINING FOR AUX. FW PUMP | 1 | ls | sharma.prabeenkumar | 732 | |
| 36 | Gr-4-Sl No-9 - SERV ENGINEER FOR AUX. FW PUMP | SERV ENGINEER FOR AUX. FW PUMP | 1 | ls | sharma.prabeenkumar | 66 | |
| 37 | Gr-5-Sl No-1 - 6 M3-HR CENTRIFUGAL SW PUMP FOR RSW PLAN | 6 M3/HR CENTRIFUGAL SW PUMP FOR RSW PLAN | 1 | st | sharma.prabeenkumar | 124 | |
| 38 | Gr-5-Sl No-2 - ON BOARD SPARE_SW PUMP FOR RSW PLANT | ON BOARD SPARE_SW PUMP FOR RSW PLANT | 1 | st | sharma.prabeenkumar | 701 | |
| 39 | Gr-5-Sl No-3 - TOOLS FOR SW PUMP FOR RSW PLANT | TOOLS FOR SW PUMP FOR RSW PLANT | 1 | st | sharma.prabeenkumar | 701 | |
| 40 | Gr-5-Sl No-4 - DOCU FOR SW PUMP FOR RSW PLANT | DOCU FOR SW PUMP FOR RSW PLANT | 1 | st | sharma.prabeenkumar | 63 | |
| 41 | Gr-5-Sl No-5 - INSTL AND COMM SPARES_SW PUMP FOR RSW PLANT | INSTL&COMM SPARES_SW PUMP FOR RSW PLANT | 1 | st | sharma.prabeenkumar | 63 | |
| 42 | Gr-5-Sl No-6 - 1ST SUBMISSION_BD_SW PUMP FOR RSW PLANT | 1ST SUBMISSION_BD_SW PUMP FOR RSW PLANT | 1 | st | sharma.prabeenkumar | 30 | |
| 43 | Gr-5-Sl No-7 - PRSERVTN_CONSUMBLE_SW PUMP FOR RSW PLANT | PRSERVTN_CONSUMBLE_SW PUMP FOR RSW PLANT | 1 | ls | sharma.prabeenkumar | 794 | |
| 44 | Gr-5-Sl No-8 - TRAINING FOR SW PUMP FOR RSW PLANT | TRAINING FOR SW PUMP FOR RSW PLANT | 1 | ls | sharma.prabeenkumar | 732 | |
| 45 | Gr-5-Sl No-9 - SERV ENGINEER FOR SW PUMP FOR RSW PLANT | SERV ENGINEER FOR SW PUMP FOR RSW PLANT | 1 | ls | sharma.prabeenkumar | 66 | |
| 46 | Gr-6-Sl No-1 - 30 M3-HR ROTARY GEAR MDO TRANSFER PUMP | 30 M3/HR ROTARY GEAR MDO TRANSFER PUMP | 2 | st | sharma.prabeenkumar | 124 | |
| 47 | Gr-6-Sl No-2 - ON BOARD SPARE FOR MDO TRANSFER PUMP | ON BOARD SPARE FOR MDO TRANSFER PUMP | 1 | st | sharma.prabeenkumar | 701 | |
| 48 | Gr-6-Sl No-3 - TOOLS FOR MDO TRANSFER PUMP | TOOLS FOR MDO TRANSFER PUMP | 1 | st | sharma.prabeenkumar | 701 | |
| 49 | Gr-6-Sl No-4 - DOCUMENTATION FOR MDO TRANSFER PUMP | DOCUMENTATION FOR MDO TRANSFER PUMP | 1 | st | sharma.prabeenkumar | 63 | |
| 50 | Gr-6-Sl No-5 - INSTL AND COMM SPARES FOR MDO TRANSFR PUMP | INSTL & COMM SPARES FOR MDO TRANSFR PUMP | 1 | st | sharma.prabeenkumar | 63 | |
| 51 | Gr-6-Sl No-6 - 1ST SUBMISSION OF BD_MDO TRANSFER PUMP | 1ST SUBMISSION OF BD_MDO TRANSFER PUMP | 1 | st | sharma.prabeenkumar | 30 | |
| 52 | Gr-6-Sl No-7 - PRESERVATION_CONSUMBLE_MDO TRANSFER PUMP | PRESERVATION_CONSUMBLE_MDO TRANSFER PUMP | 1 | ls | sharma.prabeenkumar | 794 | |
| 53 | Gr-6-Sl No-8 - TRAINING FOR MDO TRANSFER PUMP | TRAINING FOR MDO TRANSFER PUMP | 1 | ls | sharma.prabeenkumar | 732 | |
| 54 | Gr-6-Sl No-9 - SERVICE ENGINEER FOR MDO TRANSFER PUMP | SERVICE ENGINEER FOR MDO TRANSFER PUMP | 1 | ls | sharma.prabeenkumar | 66 |
Certificate (Requested in ATC)
OEM Authorization Certificate
Compliance of BoQ specification and supporting document *In case any bidder is seeking exemption from Experience / Turnover Criteria
the supporting documents to prove his eligibility for exemption must be uploaded for evaluation by the buyer
Extended Deadline
29-Jul-2025, 3:00 pm
Opening Date
29-Jul-2025, 3:30 pm
Extended Deadline
29-Jul-2025, 12:00 pm
Opening Date
29-Jul-2025, 12:30 pm
Extended Deadline
25-Jul-2025, 12:00 pm
Opening Date
25-Jul-2025, 12:30 pm
Extended Deadline
22-Jul-2025, 12:00 pm
Opening Date
22-Jul-2025, 12:30 pm
Extended Deadline
17-Jul-2025, 12:00 pm
Opening Date
17-Jul-2025, 12:30 pm
Extended Deadline
11-Jul-2025, 12:00 pm
Opening Date
11-Jul-2025, 12:30 pm
Extended Deadline
08-Jul-2025, 12:00 pm
Opening Date
08-Jul-2025, 12:30 pm
Extended Deadline
03-Jul-2025, 12:00 pm
Opening Date
03-Jul-2025, 12:30 pm
Extended Deadline
28-Jun-2025, 12:00 pm
Opening Date
28-Jun-2025, 12:30 pm
Extended Deadline
24-Jun-2025, 12:00 pm
Opening Date
24-Jun-2025, 12:30 pm
Extended Deadline
16-Jun-2025, 2:00 pm
Opening Date
16-Jun-2025, 2:30 pm
Start
11-Sep-2025, 12:00 pm
End
16-Sep-2025, 2:00 pm
Duration: 122 hours
Reverse Auction Document
✅ RA concluded. Check financial results for final rankings.
| S.No | Seller | Item | Date | Status |
|---|---|---|---|---|
| 1 | ********** Under PMA | - | 29-07-2025 14:35:07 | |
| 2 | ********** Under PMA | - | 27-06-2025 21:36:08 |
Key insights about WEST BENGAL tender market
The eligibility requirements include being a registered entity capable of supplying the specified centrifugal pumps and gear pumps for the ORV project. Bidders should demonstrate previous experience in similar projects, ensuring compliance with all regulatory standards relevant to government contracts.
Bidders must provide detailed technical specifications that meet the required performance metrics for both centrifugal and gear pumps. This involves adherence to energy efficiency ratings, durability, and quality assurance certifications relevant to defence applications. Documentation confirming compliance with applicable regulatory standards is necessary.
All submission methods are conducted electronically via the official tender portal. Bidders must ensure compliance with the specified document formats and types outlined in the tender. It is crucial to adhere to the submission guidelines to prevent disqualification.
Bidders will need to furnish a performance security that guarantees fulfillment of the contract terms upon award. The specifics regarding the amount and format of the performance security will be detailed in the final contract documentation.
This tender includes special provisions aimed at supporting Micro, Small, and Medium Enterprises (MSEs) and startups. These benefits highlight a commitment to fostering local businesses and encouraging innovative approaches that meet the contract requirements, promoting inclusivity in defense procurement.
Sign up now to access all documents
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS