Bharat Petroleum Corporation Limited Valve Changing Machine & Correction Unit Tender Uluberia LPG Plant West Bengal 2026

Bid Publish Date

07-Aug-2026, 9:23 pm

Bid End Date

31-Aug-2026, 2:00 pm

Generate Docs

Progress

Issue07-Aug-2026, 9:23 pm
Corrigendum28-Aug-2026
AwardPending

Key Highlights

  • Brand/OEM requirements: Not specified in data
  • Technical standards/certifications: ASTM A106 Schedule 40 piping standard referenced
  • Special clauses: Option clause allowing ±25% quantity variation during/after contract
  • Eligibility: Two-part bid (techno-commercial and price) through GEM portal

Tender Overview

Bharat Petroleum Corporation Limited invites bids for the supply, installation & commissioning of a Valve Changing Machine and a Correction Unit at the Uluberia LPG Plant, Howrah, West Bengal. The scope encompasses ancillary electrical cabling (4C x 6 sqmm, 3C x 1.5 sqmm 1 kV armoured copper conductors), FLP junction boxes, above-ground piping fabrication (1 inch), seamless ASTM A106 Sch 40 piping, and 300 class 1 inch ball valves. The project is structured as a two-part GEM bid (techno-commercial and price). The tender emphasizes quantities may vary under option clauses and mandates alignment to BPCL’s contract formats.

Technical Specifications & Requirements

  • Scope items include: Valve Changing Machine, Correction Unit, 4C x 6 sqmm 1 kV armoured cables, 3C x 1.5 sqmm 1 kV armoured cables, FLP junction boxes (4 inch Ex D, Group IIA/IIB), FLP glands/plugs, 1 inch above-ground pipeline fabrication, seamless ASTM A106 Schedule 40 with fittings, and 300 class 1 inch ball valves.
  • Annexures referenced: Instructions to Bidders, Bid Qualification Criteria, Scope of Work, GPC, SCC, and Unpriced SOR format. Deployment at Uluberia LPG Plant implies on-site commissioning under BPCL procurement standards. The exact ERD/EMD values and BOQ item specifics are not disclosed in the data provided.

Terms, Conditions & Eligibility

  • The buyer reserves quantity variation up to 25% at contract award and during the currency at contracted rates. Delivery period calculations are based on last delivery order date with a minimum extension framework and a 30‑day minimum extended period. BPCL requires bidders to comply with these option terms and follow the stated contract formats (GPC/SCC). The two-part bid submission is mandatory on GEM Portal, with technical and price components. Bidders should prepare to meet standard BPCL procurement terms and conditions as detailed in Annexures.

Key Specifications

  • Valve Changing Machine & Correction Unit scope

  • Cabling: 4C x 6 sqmm 1 kV, 3C x 1.5 sqmm 1 kV armoured copper conductors

  • Electrical: FLP Junction Box 4 inch Ex D Gas Group IIA/IIB, FLP gland and plug

  • Piping: Seamless ASTM A106 Sch 40 with fittings

  • Valves: 300 class Ball Valve 1 inch

  • Fabrication: 1 inch above-ground pipeline construction at site

Terms & Conditions

  • Option clause allows ±25% quantity variation during contract

  • Delivery period starts from last date of original delivery order

  • Delivery extension calculations use ratio formula with minimum 30 days

Important Clauses

Payment Terms

Not specified in data; bidders should anticipate BPCL standard terms in Annexure V (SCC)

Delivery Schedule

Delivery timeline linked to last delivery order date with potential extended period per option clause

Penalties/Liquidated Damages

Not disclosed in data; BPCL procurement terms likely apply via SCC Annexure

Bidder Eligibility

  • Eligibility to bid via GEM Portal with two-part submission

  • Experience in supply/installation of valve changing machines or similar gas plant equipment

  • Compliance with ASTM A106 Sch 40 piping and 1 kV armoured cable installation

Authority & Contact

Tender Data

Bid Details

Quantity

1512

Category

Supply and Installation of Valve Changing Machine

Bid Type

Two Packet Bid

Bid Validity

120 (Days)

Bid Type

Service

Evaluation

Total value wise evaluation

Inspection Required

No

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

No

MII Purchase Preference

Yes

MII Preference Band

L1+20%

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

Yes

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Min. Avg. Annual Turnover

8

Past Performance

30 %

Experience Required

3 Year (s)

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

No

Item Category

Supply and Installation of Valve Changing Machine , Supply and Installation of Weight Correction Unit , Supply and Laying of 4C X 6 Sqmm 1 point 1 Kv Grade Armoured copper Conductor Cables , Supply and Laying of 3C X 1.5 Sqmm 1 point 1 Kv Grade Armoured copper Conductor Cables , FLP JUNCTION BOX 4 inch Ex D Gas Group IIA IIB FLP 4 way and WP Junction box with FLP Gland and FLP Plug , Supply Fabrication welding 1 inch of above ground pipeline SEAMLESS ASTM A 106 SCH 40 including all fitting , Supply and Fixing of 300 class Ball Valve 1 inch

Advisory Bank

ICICI

ePBG Percentage

5%

ePBG Duration (Months)

18

Payment Timelines

Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

Pre-Bid & Qualification

Pre-Bid Date

14-08-2026 11:00:00

Pre-Bid Venue

https://teams.microsoft.com/meet/437517192708390? p=y00jrtMBoFmABkYlKK

Delivery Details

Max Delivery Days

120

Delivery Locations

1

Delivery Cities

Kolkata

Delivery Pincodes

700095

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Amitava Das700095,PRINCE GULAM MD SHAH ROAD GOLF GREEN KOLKATAKolkataWest Bengal7000951120-

Authority Records

MINISTRY OF PETROLEUM AND NATURAL GASBHARAT PETROLEUM CORPORATION LTD

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 8

GeM-Bidding-9727729.pdf

Main Document

BOQ Document

BOQ

BOQ Document

BOQ

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Bill of Quantities (BOQ) 7 Items Sign in for GEM prices

#1

Supply and Installation of Valve Changing Machine

Supply and Installation of Valve Changing Machine

1 ea Delivery: 120 days
#2

Supply and Installation of Weight Correction Unit

Supply and Installation of Weight Correction Unit

1 ea Delivery: 120 days
#3

Supply and Laying of 4C X 6 Sqmm 1 point 1 Kv Grade Armoured copper Conductor Cables

Supply and Laying of 4C X 6 Sqmm 1 point 1 Kv Grade Armoured copper Conductor Cables

1,200 rm Delivery: 120 days
#4

Supply and Laying of 3C X 1.5 Sqmm 1 point 1 Kv Grade Armoured copper Conductor Cables

Supply and Laying of 3C X 1.5 Sqmm 1 point 1 Kv Grade Armoured copper Conductor Cables

200 rm Delivery: 120 days
#5

FLP JUNCTION BOX 4 inch Ex D Gas Group IIA IIB FLP 4 way and WP Junction box with FLP Gland and FLP Plug

FLP JUNCTION BOX 4 inch Ex D Gas Group IIA IIB FLP 4 way and WP Junction box with FLP Gland and FLP Plug

4 no Delivery: 120 days
#6

Supply Fabrication welding 1 inch of above ground pipeline SEAMLESS ASTM A 106 SCH 40 including all fitting

Supply Fabrication welding 1 inch of above ground pipeline SEAMLESS ASTM A 106 SCH 40 including all fitting Bend Tee Flange Reducer Flange Joint Flange weld as per site Spacification

100 inm Delivery: 120 days
#7

Supply and Fixing of 300 class Ball Valve 1 inch

Supply and Fixing of 300 class Ball Valve 1 inch

6 no Delivery: 120 days

Corrigendum Updates

1 Update
#1

Update

28-Aug-2026

Extended Deadline

31-Aug-2026, 8:30 am

Opening Date

31-Aug-2026, 9:00 am

Required Documents

1

GST registration certificate

2

PAN card

3

Experience certificates for similar valve changing machine & correction unit projects

4

Financial statements (audited if available)

5

EMD/Security deposit details (amount not specified in data)

6

Technical bid documents demonstrating compliance with Scope of Work

7

OEM authorizations or dealership certificates (if applicable)

Frequently Asked Questions

Key insights about WEST BENGAL tender market

How to bid for BPCL valve changing machine tender in West Bengal

Bidders must submit a two-part GEM bid (techno-commercial and price) with Annexure I-IV documents. Ensure ASTM A106 seamless piping compliance, armoured copper cables (4C6sqmm, 3C1.5sqmm), and BPCL scope for Uluberia LPG Plant. Include OEM authorizations if required and meet delivery-extension terms.

What documents are required for BPCL Uluberia LPG bid

Submit GST, PAN, experience certificates for valve/maintenance projects, audited financial statements, EMD details, technical bid demonstrating scope adherence (valve changing machine, correction unit), and OEM authorizations if applicable, along with GCC/GPC/SCC annexures per BPCL terms.

What are the essential technical specifications BPCL requires

Key specs include valve changing machine, correction unit, 4C6sqmm 1 kV armoured cables, 3C1.5sqmm 1 kV armoured cables, 4 inch Ex D FLP junction boxes, ASTM A106 seamless piping, and 1 inch BPCL ball valves. Detailed Scope of Work is in Annexure III.

When will BPCL allow quantity variation in the contract

BPCL may increase or decrease quantity up to 25% of bid quantity at contract placement and during the currency at contracted rates, with delivery extensions calculated per formula and a minimum of 30 days.

What are the delivery terms for BPCL Uluberia project

Delivery is linked to the last date of the original delivery order; extended periods depend on the option clause. If exercised, the additional time = (increased quantity / original quantity) × original delivery period, subject to a minimum 30 days.

What standards apply to piping and cables in this tender

Piping must be seamless ASTM A106 Schedule 40 with fittings; electrical cabling uses 1 kV rated armoured copper conductors (4C6sqmm and 3C1.5sqmm). Ex D gas group IIA/IIB FLP junction boxes are specified for hazardous area installation.