Tender Notice for centrifugalhouse fabrication work 1,centrifugalhouse fabrication work 2,centrifugalhouse fabricatio in BIJNOR, UTTAR PRADESH

Bid Publish Date

25-Aug-2026, 12:38 pm

Bid End Date

04-Sep-2026, 1:00 pm

Value

₹2,30,000

Location

BIJNOR , UTTAR PRADESH

Progress

Issue25-Aug-2026, 12:38 pm
AwardPending

N/a invites bids for centrifugalhouse fabrication work 1, centrifugalhouse fabrication work 2, centrifugalhouse fabrication work 3, centrifugalhouse fabrication work 4, centrifugalhouse fabrication work 5, centrifugalhouse fabrication work 6, centrifugalhouse fabrication work 7, centrifugalhouse fabrication work 8, centrifugalhouse fabrication work 9, centrifugalhouse fabrication work 10, centrifugalhouse fabrication work 11, centrifugalhouse fabrication work 12, centrifugalhouse fabrication work 13, centrifugalhouse fabrication work 14, centrifugalhouse fabrication work 15, centrifugalhouse fabrication work 16, centrifugalhouse fabrication work 17, centrifugalhouse fabrication work 18, centrifugalhouse fabrication work 19, centrifugalhouse fabrication work 20, centrifugalhouse fabrication work 21, centrifugalhouse fabrication work 22, centrifugalhouse fabrication work 23, centrifugalhouse fabrication work 24, centrifugalhouse fabrication work 25, centrifugalhouse fabrication work 26, centrifugalhouse fabrication work 27 in BIJNOR, UTTAR PRADESH. Quantity: 154. Submission Deadline: 04-09-2026 13: 00: 00. Submit your proposal before the deadline.

Tender Data

Bid Details

Quantity

154

Category

centrifugalhouse fabrication work 1

Bid Type

Two Packet Bid

Bid Validity

30 (Days)

Bid Type

Service

Evaluation

Total value wise evaluation

Inspection Required

No

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

No

MII Purchase Preference

No

MSE Purchase Preference

No

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Min. Avg. Annual Turnover

1

Past Performance

50 %

Experience Required

3 Year (s)

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

No

Item Category

centrifugalhouse fabrication work 1 , centrifugalhouse fabrication work 2 , centrifugalhouse fabrication work 3 , centrifugalhouse fabrication work 4 , centrifugalhouse fabrication work 5 , centrifugalhouse fabrication work 6 , centrifugalhouse fabrication work 7 , centrifugalhouse fabrication work 8 , centrifugalhouse fabrication work 9 , centrifugalhouse fabrication work 10 , centrifugalhouse fabrication work 11 , centrifugalhouse fabrication work 12 , centrifugalhouse fabrication work 13 , centrifugalhouse fabrication work 14 , centrifugalhouse fabrication work 15 , centrifugalhouse fabrication work 16 , centrifugalhouse fabrication work 17 , centrifugalhouse fabrication work 18 , centrifugalhouse fabrication work 19 , centrifugalhouse fabrication work 20 , centrifugalhouse fabrication work 21 , centrifugalhouse fabrication work 22 , centrifugalhouse fabrication work 23 , centrifugalhouse fabrication work 24 , centrifugalhouse fabrication work 25 , centrifugalhouse fabrication work 26 , centrifugalhouse fabrication work 27

Payment Timelines

Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

Delivery Details

Max Delivery Days

60

Delivery Locations

1

Delivery Cities

Bijnor

Delivery Pincodes

246763

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Anurag Singh246763,KISAN SAHKARI CHINI MILLS LTD., Sneh Road Najibabad PIN CODE- 246763 GST NO - 09AAAAK1634P1ZD Contact no- 9411427852,6397805612BijnorUttar Pradesh246763860-

Authority Records

UTTAR PRADESH COOPERATIVE SUGAR FACTORIES FEDERATION LIMITED

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 5

GeM-Bidding-9794710.pdf

Main Document

Other Documents

OTHER

BOQ Document

BOQ

BOQ Document

BOQ

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Authority & Contact

Organization

N/a

Office Name

Lucknow

Grievance Contact

[email protected]

Bill of Quantities (BOQ) 27 Items Sign in for GEM prices

#1

centrifugalhouse fabrication work 1

Centrifugal & drier house dismantle the damaged pipeline at various locations, dispose of it in the scrap yard, and install a new pipeline (12inch).

8 pcdm Delivery: 60 days
#2

centrifugalhouse fabrication work 2

Centrifugal & drier house dismantle the damaged pipeline at various locations, dispose of it in the scrap yard, and install a new pipeline (6inch).

40 pcdm Delivery: 60 days
#3

centrifugalhouse fabrication work 3

Centrifugal & drier house dismantle the damaged pipeline at various locations, dispose of it in the scrap yard, and install a new pipeline (4inch).

12 pcdm Delivery: 60 days
#4

centrifugalhouse fabrication work 4

Centrifugal & drier house dismantle the damaged pipeline at various locations, dispose of it in the scrap yard, and install a new pipeline (3inch).

12 pcdm Delivery: 60 days
#5

centrifugalhouse fabrication work 5

Centrifugal & drier house dismantle the damaged pipeline at various locations, dispose of it in the scrap yard, and install a new pipeline (2inch).

12 pcdm Delivery: 60 days
#6

centrifugalhouse fabrication work 6

Fabricate and install bends at various locations in the centrifugal house (12inch).

2 pcdn Delivery: 60 days
#7

centrifugalhouse fabrication work 7

Fabricate and install bends at various locations in the centrifugal house (8inch).

2 pcdn Delivery: 60 days
#8

centrifugalhouse fabrication work 8

Fabricate and install bends at various locations in the centrifugal house (6inch).

8 pcdn Delivery: 60 days
#9

centrifugalhouse fabrication work 9

Fabricate and install bends at various locations in the centrifugal house (4inch).

2 pcdn Delivery: 60 days
#10

centrifugalhouse fabrication work 10

Fabricate and install bends at various locations in the centrifugal house (3inch).

2 pcdn Delivery: 60 days
#11

centrifugalhouse fabrication work 11

Fabricate and install flanges at various locations in the centrifugal house (12inch).

4 pcdn Delivery: 60 days
#12

centrifugalhouse fabrication work 12

Fabricate and install flanges at various locations in the centrifugal house (6inch).

6 pcdn Delivery: 60 days
#13

centrifugalhouse fabrication work 13

Fabricate and install flanges at various locations in the centrifugal house (4inch).

4 pcdn Delivery: 60 days
#14

centrifugalhouse fabrication work 14

Fabricate and install flanges at various locations in the centrifugal house (2inch).

2 pcdn Delivery: 60 days
#15

centrifugalhouse fabrication work 15

Fabricate and install nipples at various locations in the centrifugal house (4inch).

4 pcdn Delivery: 60 days
#16

centrifugalhouse fabrication work 16

Fabricate and install nipples at various locations in the centrifugal house (2inch).

5 pcdn Delivery: 60 days
#17

centrifugalhouse fabrication work 17

Open and reassemble valves at various locations in the centrifugal house (6inch).

5 pcdn Delivery: 60 days
#18

centrifugalhouse fabrication work 18

Open and reassemble valves at various locations in the centrifugal house (4inch).

4 pcdn Delivery: 60 days
#19

centrifugalhouse fabrication work 19

Open and reassemble valves at various locations in the centrifugal house (3inch).

5 pcdn Delivery: 60 days
#20

centrifugalhouse fabrication work 20

Open and reassemble valves at various locations in the centrifugal house (2inch).

2 pcdn Delivery: 60 days
#21

centrifugalhouse fabrication work 21

Centrifugal No. 1 & 2 and KCP Machine No. 1 & 2, cut and remove the damaged monitor casing and ribs, repair them using 10/12 mm MS plate, and carry out a satisfactory trial.

2 lumpsum Delivery: 60 days
#22

centrifugalhouse fabrication work 22

In KCP Machine No. 1 & 2, cut and remove the damaged center shaft and arm inside the pug mill, fabricate a new one from 8 to 10 mm plate, install it, and conduct a satisfactory trial.

2 lumpsum Delivery: 60 days
#23

centrifugalhouse fabrication work 23

Dismantle the damaged portion of the upper cover of continuous machines No. 6 and 7 and put it in the scrap yard, then fabricate and install a new cover using 10/12 mm plate, making holes as per the sample, and fit the feed/flow pipe

2 each Delivery: 60 days
#24

centrifugalhouse fabrication work 24

Dismantle the damaged plate of the sugar discharge chute from the sugar elevator to the sugar grader, fabricate and install a new one from 6 mm thick plate, and dispose of the scrap in the scrap yard.

3 meter square Delivery: 60 days
#25

centrifugalhouse fabrication work 25

Remove the old tray of Sugar Hopper No. 1, dispose of it in the scrap yard, fabricate and install a new one from 3/5 mm MS plate, and carry out a satisfactory trial.

2 lumpsum Delivery: 60 days
#26

centrifugalhouse fabrication work 26

Remove the transient heater installed above the C Centi machine, open its side plates, clean it, carry out hydraulic testing, reinstall it in its original position, and complete all connections.

1 each Delivery: 60 days
#27

centrifugalhouse fabrication work 27

Centrifugal machine No. 4, cut and remove the damaged/weak top and bottom sugar discharge chute along with the flange, and dispose of it in the scrap yard. Fabricate a new chute as per the sample using a 6 mm MS plate, prepare all required connections such as angles, channels, etc., install it on the side, and conduct a satisfactory trial.

1 lumpsum Delivery: 60 days

Categories 34

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Required Documents

1

Experience Criteria

2

Past Performance

3

Bidder Turnover

4

Certificate (Requested in ATC) *In case any bidder is seeking exemption from Experience / Turnover Criteria

5

the supporting documents to prove his eligibility for exemption must be uploaded for evaluation by the buyer