Indian Army Data Centre Peripherals Tender Telangana 2026 – Installation, Data Sheet Verification & OEM Installation

Bid Publish Date

24-Oct-2026, 2:10 pm

Bid End Date

03-Nov-2026, 3:00 pm

Progress

Issue24-Oct-2026, 2:10 pm
AwardPending

Tender Overview

The Indian Army, Department Of Military Affairs, seeks quotes for Data Centre Peripherals to be delivered and installed at FEL, MCEME, Trimulgherry, Secunderabad, Telangana. The procurement covers unspecified item types under the Data Centre Peripherals category with the potential for quantity adjustments up to 25% during and after contract award. Bidders must provide PAN, GSTIN, cancelled cheque, and EFT mandate; the delivery address and commissioning responsibilities are explicit. The ATC requires that the supplier not be under liquidation and that products have at least 5 years of residual market life. This tender emphasizes data sheet verification, OEM capability, and adherence to non-obsolescence clauses, with installation/commissioning handled by OEM-certified personnel where applicable.

Technical Specifications & Requirements

  • Delivery/Installation site: Faculty of Electronics (FEL), MCEME, Trimulgherry, Secunderabad-500015, Telangana
  • Data sheets must be uploaded and align exactly with offered product specifications; mismatches may cause bid rejection
  • Manufacturer must have 3+ years of regular government or large-entity supply experience for similar items; contracts to be submitted as evidence
  • Bid must include evidence of not being in liquidation or bankruptcy; undertaking to be uploaded
  • Products must not be declared end-of-life within the residual market life of at least 5 years by the OEM; non-obsolete in market with documented support
  • Installation/commissioning/training (if applicable) to be performed by OEM or OEM-certified resource
  • No BOQ items are listed; the scope is defined by data sheets and ATC terms

Terms, Conditions & Eligibility

  • EMD: not specified; bid must meet vendor qualification through ATC requirements
  • Delivery timeline: alignment with original and extended delivery periods as per option clause; minimum extensions subject to calculation rules
  • Payment terms: not specified in the ATC; likely as per standard government procurement terms
  • Documentation: PAN, GSTIN, cancelled cheque, EFT mandate; data sheets; OEM authorizations may be required
  • Eligibility: bidder must demonstrate 3+ years of supplying similar category products to central/state Govt or PSUs; OEM certifications and installation capability required
  • Warranty/Support: not explicitly defined; OEM-certified installation implied
  • Obsolescence: offered products must have at least 5 years residual market life

Key Specifications

  • Delivery/Installation site: FEL, MCEME, Trimulgherry, Secunderabad, Telangana

  • Data Sheet alignment: data sheet must match offered product specifications

  • Experience: 3+ years supplying similar category products to government entities

  • Market life: products must have at least 5 years residual life and not be OEM-end-of-life

  • Installation: OEM or OEM-certified resource to perform installation, commissioning, and training

  • BOQ: No items listed; scope defined by data sheets and ATC terms

Terms & Conditions

  • Quantity option: +25% during contract/extended period at contracted rates

  • Delivery window linked to last date of original delivery order and extended period

  • Non-liquidation/Bank undertaking required from bidder

  • Data sheet verification mandatory; mismatches may lead to rejection

  • 3+ years government/PSU experience for similar products required

  • OEM certification/authorization required for installation and commissioning

Important Clauses

Payment Terms

Payment terms are not explicitly stated in ATC; bidders should anticipate standard government terms and confirm during bid submission

Delivery Schedule

Delivery begins from last date of original delivery order; additional time for increased quantity calculated as (Increase/Original) × Original delivery period, minimum 30 days

Penalties/Liquidated Damages

LD details are not specified; suppliers should verify applicable penalties for delays during bid submission

Bidder Eligibility

  • Regularly manufactured and supplied similar category products to central/state government bodies for 3 years

  • Not under liquidation, court receivership, or bankruptcy; undertaking to be uploaded

  • Product offered must not be obsolete and must have at least 5 years remaining market life

Advertisement

Tender Data

Bid Details

Quantity

1

Bid Type

Two Packet Bid

Bid Validity

180 (Days)

Bid Type

Service

Evaluation

Total value wise evaluation

Inspection Required

No

RA Qualification Rule

H1-Highest Priced Bid Elimination

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

No

MII Purchase Preference

Yes

MII Preference Band

L1+20%

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

Yes

Startup Exemption/Relaxation

Yes

Bid Splitting Applied

No

Requirements

Min. Avg. Annual Turnover

75

Past Performance

30 %

Warranty Period

1 years

Experience Required

3 Year (s)

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

Yes

Item Category

Data Centre Peripherals

Delivery Details

Max Delivery Days

30

Delivery Locations

1

Delivery Cities

RANGAREDDY

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
-RANGAREDDYRANGAREDDY--130-

Authority Records

MINISTRY OF DEFENCEMILITARY AFFAIRS DEPARTMENT

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 3

GeM-Bidding-10054971.pdf

Main Document

Other Documents

OTHER

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Authority & Contact

Organization

Indian Army

Office Name

Not disclosed yet

Grievance Contact

[email protected]

Categories 1

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Required Documents

1

Copy of PAN Card

2

Copy of GSTIN

3

Copy of Cancelled Cheque

4

Copy of EFT Mandate certified by Bank

5

Data Sheet of the offered product

6

OEM authorization/verification documents

7

Evidence of 3+ years of supplying similar category products to government/PSU/PSU-listed entities

8

Undertaking of non-liquidation or bankruptcy

9

Contract copies for similar supplies (yearly) as applicable

Frequently Asked Questions

How to bid for Indian Army data centre peripherals tender in Telangana 2026?

Bidders must submit PAN, GSTIN, cancelled cheque, and EFT mandate, along with the product data sheet and OEM authorizations. Ensure your product has at least 5 years of residual market life and provide evidence of 3+ years of government or PSU supply experience. Installation may require OEM-certified personnel.

What documents are required for data centre peripherals bid in Secunderabad?

Required documents include PAN Card, GSTIN, Cancelled Cheque, EFT Mandate, Data Sheet of the offered product, OEM authorization, and evidence of 3+ years of government/PSU supply experience. Also include undertakings regarding non-liquidation and bank status.

What are the installation responsibilities for the FEL site in Telangana?

Installation, commissioning, and training (if applicable) must be performed by the OEM or OEM-certified resource. The installation location is Faculty of Electronics (FEL), MCEME, Trimulgherry, Secunderabad-500015, Telangana, with the delivery address specified in the ATC.

What are the eligibility criteria for suppliers in this government data centre tender in 2026?

Eligibility requires non-liquidation status, 3+ years of supplying similar items to central/state government or PSUs, and a data sheet-aligned product offering not declared end-of-life within a 5-year residual market life. OEM certifications may be required.

What is the delivery extension rule for quantity changes in this tender?

The purchaser may increase quantity up to 25% during or after award. Extended delivery time is calculated as (Increased quantity / Original quantity) × Original delivery period, with a minimum of 30 days, and may extend up to the original delivery period.

What are the key data sheet requirements for bid submission in Telangana?

Bidder must upload a Data Sheet that exactly matches offered product specifications. Any unexplained mismatch could lead to bid rejection. Data sheets should align with the tender’s product category and installation scope.

Which site location governs the installation of data centre peripherals in this bid?

The installation scope is defined at Faculty of Electronics (FEL), MCEME, Trimulgherry, Secunderabad-500015, Telangana, with commissioning performed by OEM-certified personnel where applicable.

What is the expected experience requirement for suppliers in this procurement?

The bidder or its OEM must have supplied the same or similar category products to central/state government bodies or PSUs for 3 years prior to bid opening, with relevant contracts submitted as evidence.