Bids are Invited For CAPACITOR BANK 12A,CAPACITOR BANK 80A,CABLE TIE,HRC FUSE NH1 TYPE 160 A,HRC FUSE NH1 TYPE 100A,HNO0 in PURNIA, BIHAR

Bid Publish Date

02-Jul-2025, 5:51 pm

Bid End Date

12-Jul-2025, 6:00 pm

Value

₹6,89,875

Location

Progress

RA
Issue02-Jul-2025, 5:51 pm
Reverse AuctionCompleted
Award23-Jul-2025, 2:37 am
Explore all 4 tabs to view complete tender details

Quantity

628

Category

CAPACITOR BANK 12A

Bid Type

Two Packet Bid

Categories 50

Hindustan Petroleum Corporation Ltd announces a tender for CAPACITOR BANK 12A, CAPACITOR BANK 80A, CABLE TIE, HRC FUSE NH1 TYPE 160 A, HRC FUSE NH1 TYPE 100A, HNO00 FUSE 80A, NH000 FUSE 63A, HEF TYPE FUSE 20A, HEF TYPE FUSE 32A, HEF TYPE FUSE 10A, HEF TYPE FUSE 16A, SCREW DRIVER, LED 90 KW KIT, INSULATION TAPE, TOOL BOX SET, PIPE WRENCH 8 inch, PIPE WRENCH 10INCH, PIPE WRENCH 12INCH, PIPE WRENCH 14INCH, LED TUBE LIGHT 20W, HIGH MAST LIGHT, FLP HOOTER, TT GANTRY EARTHING CABLE, BLEEDER WIRE BROAD, SILICA GEL, OVERLOAD RELAY 6 TO 10A, OVERLOAD RELAY 9 TO 15A, OVERLOAD RELAY 15 TO 25A, LED CONSTANT DRIVER, MCC PANEL LOCK, EXHAUST FAN, EARTH LEAKAGE CIRCUIT BREAKER, SURGE PROTECTION DEVICE 220V, SURGE PROTECTION DEVICE 415V, MNX 25 CONTACTOR, HEATER COIL FOR MANUAL SEAL MACHINE, TEMPERATURE CONTROLLER, PVC INSULATING MAT in PURNIA, BIHAR. Quantity: 628. Submission Deadline: 12-07-2025 18: 00: 00. Last date to apply is approaching fast!

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

Yes

Item Category

CAPACITOR BANK 12A , CAPACITOR BANK 80A , CABLE TIE , HRC FUSE NH1 TYPE 160 A , HRC FUSE NH1 TYPE 100A , HNO00 FUSE 80A , NH000 FUSE 63A , HEF TYPE FUSE 20A , HEF TYPE FUSE 32A , HEF TYPE FUSE 10A , HEF TYPE FUSE 16A , SCREW DRIVER , LED 90 KW KIT , INSULATION TAPE , TOOL BOX SET , PIPE WRENCH 8 inch , PIPE WRENCH 10INCH , PIPE WRENCH 12INCH , PIPE WRENCH 14INCH , LED TUBE LIGHT 20W , HIGH MAST LIGHT , FLP HOOTER , TT GANTRY EARTHING CABLE , BLEEDER WIRE BROAD , SILICA GEL , OVERLOAD RELAY 6 TO 10A , OVERLOAD RELAY 9 TO 15A , OVERLOAD RELAY 15 TO 25A , LED CONSTANT DRIVER , MCC PANEL LOCK , EXHAUST FAN , EARTH LEAKAGE CIRCUIT BREAKER , SURGE PROTECTION DEVICE 220V , SURGE PROTECTION DEVICE 415V , MNX 25 CONTACTOR , HEATER COIL FOR MANUAL SEAL MACHINE , TEMPERATURE CONTROLLER , PVC INSULATING MAT

Authority Records

MINISTRY OF PETROLEUM AND NATURAL GASHINDUSTAN PETROLEUM CORPORATION LTD

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 5

GeM-Bidding-8038763.pdf

Main Document

BOQ Document

BOQ

BOQ Document

BOQ

Buyer uploaded ATC document

ATC

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Bill of Quantities (BOQ) 38 Items Sign in for GEM prices

#1

CAPACITOR BANK 12A

CAPACITOR BANK 12A

1 ea Delivery: 360 days
#2

CAPACITOR BANK 80A

CAPACITOR BANK 80A

1 ea Delivery: 360 days
#3

CABLE TIE

CABLE TIE

20 ea Delivery: 360 days
#4

HRC FUSE NH1 TYPE 160 A

HRC FUSE NH1 TYPE 160 A

20 ea Delivery: 360 days
#5

HRC FUSE NH1 TYPE 100A

HRC FUSE NH1 TYPE 100A

10 ea Delivery: 360 days
#6

HNO00 FUSE 80A

HNO00 FUSE 80A

10 ea Delivery: 360 days
#7

NH000 FUSE 63A

NH000 FUSE 63A

10 ea Delivery: 360 days
#8

HEF TYPE FUSE 20A

HEF TYPE FUSE 20A

30 ea Delivery: 360 days
#9

HEF TYPE FUSE 32A

HEF TYPE FUSE 32A

30 ea Delivery: 360 days
#10

HEF TYPE FUSE 10A

HEF TYPE FUSE 10A

30 ea Delivery: 360 days
#11

HEF TYPE FUSE 16A

HEF TYPE FUSE 16A

30 ea Delivery: 360 days
#12

SCREW DRIVER

SCREW DRIVER

1 ea Delivery: 360 days
#13

LED 90 KW KIT

LED 90 KW KIT

30 ea Delivery: 360 days
#14

INSULATION TAPE

INSULATION TAPE

100 ea Delivery: 360 days
#15

TOOL BOX SET

TOOL BOX SET

4 ea Delivery: 360 days
#16

PIPE WRENCH 8 inch

PIPE WRENCH 8 inch

1 ea Delivery: 360 days
#17

PIPE WRENCH 10INCH

PIPE WRENCH 10INCH

1 ea Delivery: 360 days
#18

PIPE WRENCH 12INCH

PIPE WRENCH 12INCH

1 ea Delivery: 360 days
#19

PIPE WRENCH 14INCH

PIPE WRENCH 14INCH

1 ea Delivery: 360 days
#20

LED TUBE LIGHT 20W

LED TUBE LIGHT 20W

20 ea Delivery: 360 days
#21

HIGH MAST LIGHT

HIGH MAST LIGHT

5 ea Delivery: 360 days
#22

FLP HOOTER

FLP HOOTER

10 ea Delivery: 360 days
#23

TT GANTRY EARTHING CABLE

TT GANTRY EARTHING CABLE

100 ea Delivery: 360 days
#24

BLEEDER WIRE BROAD

BLEEDER WIRE BROAD

20 ea Delivery: 360 days
#25

SILICA GEL

SILICA GEL

1 ea Delivery: 360 days
#26

OVERLOAD RELAY 6 TO 10A

OVERLOAD RELAY 6 TO 10A

10 ea Delivery: 360 days
#27

OVERLOAD RELAY 9 TO 15A

OVERLOAD RELAY 9 TO 15A

10 ea Delivery: 360 days
#28

OVERLOAD RELAY 15 TO 25A

OVERLOAD RELAY 15 TO 25A

4 ea Delivery: 360 days
#29

LED CONSTANT DRIVER

LED CONSTANT DRIVER

15 ea Delivery: 360 days
#30

MCC PANEL LOCK

MCC PANEL LOCK

25 ea Delivery: 360 days
#31

EXHAUST FAN

EXHAUST FAN

10 ea Delivery: 360 days
#32

EARTH LEAKAGE CIRCUIT BREAKER

EARTH LEAKAGE CIRCUIT BREAKER

20 ea Delivery: 360 days
#33

SURGE PROTECTION DEVICE 220V

SURGE PROTECTION DEVICE 220V

10 ea Delivery: 360 days
#34

SURGE PROTECTION DEVICE 415V

SURGE PROTECTION DEVICE 415V

10 ea Delivery: 360 days
#35

MNX 25 CONTACTOR

MNX 25 CONTACTOR

10 ea Delivery: 360 days
#36

HEATER COIL FOR MANUAL SEAL MACHINE

HEATER COIL FOR MANUAL SEAL MACHINE

2 ea Delivery: 360 days
#37

TEMPERATURE CONTROLLER

TEMPERATURE CONTROLLER

5 ea Delivery: 360 days
#38

PVC INSULATING MAT

PVC INSULATING MAT

10 ea Delivery: 360 days

Required Documents

1

Experience Criteria

2

Past Performance

3

Bidder Turnover

4

Additional Doc 1 (Requested in ATC) *In case any bidder is seeking exemption from Experience / Turnover Criteria

5

the supporting documents to prove his eligibility for exemption must be uploaded for evaluation by the buyer

Reverse Auction Schedule

Completed

Start

15-Jul-2025, 1:00 pm

End

16-Jul-2025, 1:00 pm

Duration: 24 hours

Reverse Auction Document

✅ RA concluded. Check financial results for final rankings.

Technical Results

S.No Seller Item Date Status
1
MANAS ELECTRIC CO   Under PMA
-12-07-2025 12:00:57
2
NATIONAL ELECTRIC AND SERVICE CENTRE   Under PMA
-12-07-2025 09:49:06
3
SWDARSHAN CONSULTANT PRIVATE LIMITED   Under PMA
-12-07-2025 17:37:09
4
THANGA TECH SYSTEMS   Under PMA
-12-07-2025 12:04:14

Reverse Auction Results Final Prices

These are the final prices after the reverse auction event. Prices may be lower than initial bids.

Rank Seller Final Price Item
L1NATIONAL ELECTRIC AND SERVICE CENTRE(MSE,MII)   Under PMA Winner ₹7,77,140Item Categories : CAPACITOR BANK 12A,CAPACITOR BANK 80A,CABLE TIE,HRC FUSE NH1 TYPE 160 A,HRC FUSE NH1 TYPE 100A,HNO0
L2THANGA TECH SYSTEMS (MSE)   Under PMA₹8,38,159Item Categories : CAPACITOR BANK 12A,CAPACITOR BANK 80A,CABLE TIE,HRC FUSE NH1 TYPE 160 A,HRC FUSE NH1 TYPE 100A,HNO0
L3MANAS ELECTRIC CO (MSE,MII)   Under PMA₹8,90,090Item Categories : CAPACITOR BANK 12A,CAPACITOR BANK 80A,CABLE TIE,HRC FUSE NH1 TYPE 160 A,HRC FUSE NH1 TYPE 100A,HNO0

🎉 L1 Winner

NATIONAL ELECTRIC AND SERVICE CENTRE(MSE,MII)   Under PMA

Final Price: ₹7,77,140

Contract / Result Documents 1